IMO/EPPR Guide Oil Spill Response in ice and snow. EPPR I – June 16.-17, 2014. Activities since last EPPR. Funding in place – Canada and Norway Contractor selected and contract signed – Owens Coastal Consultants Information to IMO OPRC HNS Technical group
E N D
IMO/EPPR Guide Oil Spill Response in ice and snow EPPR I – June 16.-17, 2014
Activities since last EPPR • Funding in place – Canada and Norway • Contractor selected and contract signed – Owens Coastal Consultants • Information to IMO OPRC HNS Technical group • Agreement on the draft Table of Content
Project Plan • First draft: May 30 – delivered June 9 • To be discussed at EPPR I June 16.- 17, 2014 • Written comments within July 9, 2014 • Second draft: October 30 • To be discussed at EPPR II in November • Written comments within: TBD • Final document from Consultant – December 1
Actions for EPPR • To take note of the information provided in this document • To review the first draft report submitted to EPPR as soon as possible after June 9 and give initial feedback at the EPPR I meeting and written comments by July 9th. • Discuss and decide • A separate EPPR Guide in addition to the IMO guide built on the same basis • Any other issues