1 / 122

Engineering Project Management

Engineering Project Management. Civil Engineering Department. An- Najah National University Civil Engineering Department Faculty of Engineering Construction Engineering and Management Nabil Dmaidi. Your Expectations of Me Be prepared Be on time Teach for full 50 minute period

tcrosland
Download Presentation

Engineering Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Engineering Project Management Civil Engineering Department

  2. ENGINEERING MANAGEMENT An-Najah National University Civil Engineering Department Faculty of Engineering Construction Engineering and Management Nabil Dmaidi

  3. ENGINEERING MANAGEMENT Your Expectations of Me Be prepared Be on time Teach for full 50 minute period Fair grading system Front load the class work Do not humiliate students Practice golden rule Provide real world examples Make you think

  4. ENGINEERING MANAGEMENT Topics 1) Management Functions and introduction of construction project planning and scheduling 2)Construction scheduling techniques 3)Preparation and usage of bar charts 4)Preparation and usage of the Critical Path Method (CPM) 5)Preparation and usage of Precedence Diagramming Method (PDM) 6)Issues relating to determination of activity duration 7)Contractual provisions relating to project schedules 8)Resource leveling and constraining 9)Time cost tradeoff 10)Schedule monitoring and updating. 11)Communicating schedule 12) Project control and earned value Control 13) claims, Safety and Quality control

  5. ENGINEERING MANAGEMENT Course Outline Introduction and definitions Float Analysis Importance of Scheduling The CPM Calculations Networks, Bar Charts, and Brief introduction on: Imposed Finish Date and  Project Control and Earned Value Analysis  Resource Allocation /Leveling other CPM Issues  Time/Cost Trade-off Precedence Networks Updating Schedules Time-Scaled Logic Diagrams

  6. What is the Project ENGINEERING MANAGEMENT In order to understand project management, one must begin with the definition of a project. A project can be considered to be any series of activities and tasks that :. ● Have a specific objective to be completed within certain specifications ● Have defined start and end dates ● Have funding limits (if applicable) ● Consume human and nonhuman resources (i.e., money, people, equipment) ● Are multifunctional (i.e., cut across several functional lines)

  7. ENGINEERING MANAGEMENT OR ‘‘a temporary endeavor undertaken to create a unique product, service, or result’’

  8. Project Life Cycle ENGINEERING MANAGEMENT

  9. Five Process group ENGINEERING MANAGEMENT

  10. ENGINEERING MANAGEMENT

  11. ENGINEERING MANAGEMENT Successful project management can then be defined as having achieved the project objectives: ●Within Time ● Within Cost ● At the desired performance/Technology level ● While utilizing the assigned resources effectively and efficiently ● Accepted by the customer

  12. What is Project Management ENGINEERING MANAGEMENT Project management is the planning, organizing, directing, and controlling of company resources for a relatively short-term objective that has been established to complete specific goals and objectives.

  13. ENGINEERING MANAGEMENT The potential benefits from project management are: ● Identification of functional responsibilities ● Minimizing the need for continuous reporting ● Identification of time limits for scheduling ● Identification of a methodology for trade-off analysis. ● Measurement of accomplishment against plans

  14. ENGINEERING MANAGEMENT The above definition requires further comment. Classical management is usually considered to have five functions or principles: ● Planning ● Organizing ● Staffing ● Controlling ● Directing

  15. ENGINEERING MANAGEMENT Planning – Where the organization wants to be in the future and how to get there. Organizing – Follows planning and reflects how the organization tries to accomplish the plan. – Involves the assignment of tasks, grouping of tasks into departments, and allocation of resources.

  16. ENGINEERING MANAGEMENT Leading – The use of influence to motivate employees to achieve the organization's goals. – Creating a shared culture and values, communicating goals to employees throughout the organization, and infusing employees to perform at a high level. Controlling – Monitoring employees' activities, determining if the organization is on target toward its goals, and making corrections as necessary

  17. Management Skills ENGINEERING MANAGEMENT  Conceptual Skill—the ability to see the organization as a whole and the relationship between its parts.  Human Skill—The ability to work with and through people.  Technical Skill—Mastery of specific functions and specialized knowledge

  18. Constraints of the project ENGINEERING MANAGEMENT Project management is designed to manage or control company resources on a given activity, within time, within cost, and within performance. Time, cost, and performance are the constraints on the project.

  19. Resources ENGINEERING MANAGEMENT We have stated that the project manager must control company resources within time, cost, and performance. Most companies have six resources: ● Money ● Manpower ● Equipment ● Facilities ● Materials ● Information/technology

  20. ENGINEERING MANAGEMENT • Actually, the project manager does notcontrol any of these resources directly, except perhaps money (i.e., the project budget). • Resources are controlled by the line managers. • The project manager is responsible for coordinating and integrating activities across multiple, functional lines. The integration activities performed by the project manager include:

  21. ENGINEERING MANAGEMENT ● Integrating the activities necessary to develop a project plan ● Integrating the activities necessary to execute the plan ● Integrating the activities necessary to make changes to the plan

  22. ENGINEERING MANAGEMENT Project Scheduling Planning, Scheduling, and Control 1

  23. Planning and Scheduling ENGINEERING MANAGEMENT • Planning and scheduling are two terms that are often thought of as synonymous • They are not! • Scheduling is just one part of the planning effort.

  24. ENGINEERING MANAGEMENT • Project planning serves as a foundation for several • related functions such as cost estimating, scheduling, • and project control. • Project scheduling is the determination of the timing and sequence of operations in the project and their assembly to give the overall completion time

  25. ENGINEERING MANAGEMENT Planning is the process of determining how a project will be undertaken. It answers the questions: 1. “What” is going to be done, 2. “how”, 3. “where”, 4. By “whom”, and 5. “when” (in general terms: start and finish). Scheduling deals with “when” on a detailed level… See Figure 1 .

  26. ENGINEERING MANAGEMENT The Plan What How much when By whom where How Why Figure 1 . Planning and Scheduling

  27. The Plan ENGINEERING MANAGEMENT PMI defines project management plan as a ‘‘formal, approved document that defines how the project is executed, monitored and controlled”. The plan can include elements that has to do with scope, design and alternate designs, cost, time, finance, land, procurement, operations, etc.

  28. WHY SCHEDUALE PROJECTS ? ENGINEERING MANAGEMENT 1- To calculate the project completion. 2- To calculate the start or end of a specific activity. 3-To expose and adjust conflict between trades or subcontractor. 4- To predict and calculate the cash flow . 5-To evaluate the effect of changing orders ‘CH’ .

  29. ENGINEERING MANAGEMENT 6- To improve work efficiency. 7- To resolve delay claims , this is important in critical path method ‘CPM’ discussed later.. 8- To serve as an effective project control tool .

  30. The Tripod of Good Scheduling System ENGINEERING MANAGEMENT • The Human Factor : A proficient scheduler or scheduling team. • 2. The Technology : A good scheduling computer system (software and hardware) • 3. The Management : A dynamic, responsive, and supportive management. • If anyone of the above three ‘‘legs’’ is missing, the system will fail.

  31. Scheduling and project management ENGINEERING MANAGEMENT Planning, scheduling, and project control are extremely important components of project management. project management includes other components : • cost estimating and management, • procurement, • project/contract administration, • quality management, • and safety management. • These components are all interrelated in different ways.

  32. ENGINEERING MANAGEMENT Bar (Gantt) Charts 2

  33. DEFINITION AND INTRODUCTION ENGINEERING MANAGEMENT • A bar chart is ‘‘a graphic representation of project activities, shown in a time-scaled bar line with no links shown between activities’’ • The bar may not indicate continuous work from the start of the activity until its end. • or • Non continuous (dashed) bars are sometimes used to distinguish between real work (solid line) and inactive periods (gaps between solid lines)

  34. ENGINEERING MANAGEMENT • Before a bar chart can be constructed for a project, the project must be broken into smaller, usually homogeneous components, each of which is called an activity, or a task. Item Activity M 10 Mobilization Bars ( Month or Year )

  35. ADVANTAGES OF BAR CHARTS ENGINEERING MANAGEMENT 1- Time-scaled 2- Simple to prepare 3- Can be more effective and efficient if CPM based - Still the most popular method 4- Bars can be dashed to indicate work stoppage. 5- Can be loaded with other information (budget, man hours, resources, etc.)

  36. ENGINEERING MANAGEMENT Bar Charts Loaded with More Info. Such as : budget, man hours and resources . 500$ 220$ 400$ 850$ 140$ 500$ 900$ 10 12 7 11 10 9 15

  37. DISADVANTAGES OF BAR CHARTS ENGINEERING MANAGEMENT • 1- Does not show logic • 2- Not practical for projects with too many activities • As a remedy, we can use bar charts to show: • 1. A small group of the activities (subset) • 2. Summary schedules

  38. ENGINEERING MANAGEMENT Basic Networks 3

  39. DEFINITION AND INTRODUCTION ENGINEERING MANAGEMENT • A network is a logical and chronological graphic representation of the activities (and events) composing a project. • Network diagrams are the preferred technique for showing activity sequencing. • Two main formats are the arrow and precedence diagramming methods.

  40. ENGINEERING MANAGEMENT Two classic formats AOA: Activity on Arrow AON: Activity on Node Each task labeled with Identifier (usually a letter/code) Duration (in std. unit like days) There are other variations of labeling There is 1 start & 1 end event Time goes from left to right

  41. Arrow Diagramming Method (ADM) ENGINEERING MANAGEMENT 1. Also called activity-on-arrow (AOA) network diagram or (I-J) method (because activities are defined by the form node, I, and the to node, J) 2. Activities are represented by arrows. 3. Nodes or circles are the starting and ending points of activities. 4. Can only show finish-to-start dependencies.

  42. Basic Logic Patterns for Arrow Diagrams ENGINEERING MANAGEMENT Node (Event) i Node (Event) j i Activity Name j j > i Each activity should have a unique i – j value (a) Basic Activity

  43. ENGINEERING MANAGEMENT A B 2 4 10 12 (b) Independent Activities A B 3 6 9 (c) Dependent Activities

  44. ENGINEERING MANAGEMENT 4 A C 6 8 B 2 Activity C depends upon the completion of both Activities A & B (d) A Merge 6 B A 2 4 C 8 Activities B and C both depend upon the completion of Activity A (e) A Burst

  45. ENGINEERING MANAGEMENT 12 18 A C 16 D B 14 20 Activities C and D both depend upon the completion of Activities A and B (f) A Cross

  46. Example ENGINEERING MANAGEMENT Draw the arrow network for the project given next.

  47. ENGINEERING MANAGEMENT Solution : B D 30 A E 50 10 20 40 C

  48. Dummy activity (fictitious) ENGINEERING MANAGEMENT * Used to maintain unique numbering of activities. * Used to complete logic, duration of “0” * The use of dummy to maintain unique numbering of activities.

  49. ENGINEERING MANAGEMENT A 4 10 Divide node to correct B (a) Incorrect Representation A 4 10 B Dummy 11 (b) Correct Representation

  50. Example ENGINEERING MANAGEMENT Draw the arrow network for the project given next.

More Related