1 / 48

ECE 476 POWER SYSTEM ANALYSIS

ECE 476 POWER SYSTEM ANALYSIS. Lecture 3 Three Phase, Power System Operation Professor Tom Overbye Department of Electrical and Computer Engineering. Reading and Homework. For lecture 3 please be reading Chapters 1 and 2 For lectures 4 through 6 please be reading Chapter 4

tea
Download Presentation

ECE 476 POWER SYSTEM ANALYSIS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ECE 476POWER SYSTEM ANALYSIS Lecture 3 Three Phase, Power System Operation Professor Tom Overbye Department of Electrical andComputer Engineering

  2. Reading and Homework • For lecture 3 please be reading Chapters 1 and 2 • For lectures 4 through 6 please be reading Chapter 4 • we will not be covering sections 4.7, 4.11, and 4.12 in detail • HW 1 is 2.7, 12, 21, 26; due Thursday 9/4

  3. Balanced 3 Phase () Systems • A balanced 3 phase () system has • three voltage sources with equal magnitude, but with an angle shift of 120 • equal loads on each phase • equal impedance on the lines connecting the generators to the loads • Bulk power systems are almost exclusively 3 • Single phase is used primarily only in low voltage, low power settings, such as residential and some commercial

  4. Balanced 3 -- No Neutral Current

  5. Advantages of 3 Power • Can transmit more power for same amount of wire (twice as much as single phase) • Torque produced by 3 machines is constrant • Three phase machines use less material for same power rating • Three phase machines start more easily than single phase machines

  6. Three Phase - Wye Connection • There are two ways to connect 3 systems • Wye (Y) • Delta ()

  7. Vcn Vab Vca Van Vbn Vbc Wye Connection Line Voltages -Vbn (α = 0 in this case) Line to line voltages are also balanced

  8. Wye Connection, cont’d • Define voltage/current across/through device to be phase voltage/current • Define voltage/current across/through lines to be line voltage/current

  9. Ic Ica Ib Iab Ibc Ia Delta Connection

  10. Three Phase Example • Assume a -connected load is supplied from a 3 13.8 kV (L-L) source with Z = 10020W

  11. Three Phase Example, cont’d

  12. Delta-Wye Transformation

  13. Delta-Wye Transformation Proof

  14. Delta-Wye Transformation, cont’d

  15. Three Phase Transmission Line

  16. Per Phase Analysis • Per phase analysis allows analysis of balanced 3 systems with the same effort as for a single phase system • Balanced 3 Theorem: For a balanced 3 system with • All loads and sources Y connected • No mutual Inductance between phases

  17. Per Phase Analysis, cont’d • Then • All neutrals are at the same potential • All phases are COMPLETELY decoupled • All system values are the same sequence as sources. The sequence order we’ve been using (phase b lags phase a and phase c lags phase a) is known as “positive” sequence; later in the course we’ll discuss negative and zero sequence systems.

  18. Per Phase Analysis Procedure • To do per phase analysis • Convert all  load/sources to equivalent Y’s • Solve phase “a” independent of the other phases • Total system power S = 3 Va Ia* • If desired, phase “b” and “c” values can be determined by inspection (i.e., ±120° degree phase shifts) • If necessary, go back to original circuit to determine line-line values or internal  values.

  19. Per Phase Example • Assume a 3, Y-connected generator with Van = 10 volts supplies a -connected load with Z = -j through a transmission line with impedance of j0.1 per phase. The load is also connected to a -connected generator with Va”b” = 10 through a second transmission line which also has an impedance of j0.1 per phase. • Find • 1. The load voltage Va’b’ • 2. The total power supplied by each generator, SY and S

  20. Per Phase Example, cont’d

  21. Per Phase Example, cont’d

  22. Per Phase Example, cont’d

  23. Per Phase Example, cont’d

  24. Power System Operations Overview • Goal is to provide an intuitive feel for power system operation • Emphasis will be on the impact of the transmission system • Introduce basic power flow concepts through small system examples

  25. Power System Basics • All power systems have three major components: Generation, Load and Transmission/Distribution. • Generation: Creates electric power. • Load: Consumes electric power. • Transmission/Distribution: Transmits electric power from generation to load. • Lines/transformers operating at voltages above 100 kV are usually called the transmission system. The transmission system is usually networked. • Lines/transformers operating at voltages below 100 kV are usually called the distribution system (radial).

  26. Small PowerWorld Simulator Case Load with green arrows indicating amount of MW flow Note the power balance at each bus Used to control output of generator Direction of arrow is used to indicate direction of real power (MW) flow

  27. Power Balance Constraints • Power flow refers to how the power is moving through the system. • At all times in the simulation the total power flowing into any bus MUST be zero! • This is know as Kirchhoff’s law. And it can not be repealed or modified. • Power is lost in the transmission system.

  28. Basic Power Control • Opening a circuit breaker causes the power flow to instantaneously(nearly) change. • No other way to directly control power flow in a transmission line. • By changing generation we can indirectly change this flow.

  29. Transmission Line Limits • Power flow in transmission line is limited by heating considerations. • Losses (I2 R) can heat up the line, causing it to sag. • Each line has a limit; Simulator does not allow you to continually exceed this limit. Many utilities use winter/summer limits.

  30. Overloaded Transmission Line

  31. Interconnected Operation • Power systems are interconnected across large distances. For example most of North America east of the Rockies is one system, with most of Texas and Quebec being major exceptions • Individual utilities only own and operate a small portion of the system, which is referred to an operating area (or an area).

  32. Operating Areas • Transmission lines that join two areas are known as tie-lines. • The net power out of an area is the sum of the flow on its tie-lines. • The flow out of an area is equal to total gen - total load - total losses = tie-flow

  33. Area Control Error (ACE) • The area control error is the difference between the actual flow out of an area, and the scheduled flow. • Ideally the ACE should always be zero. • Because the load is constantly changing, each utility must constantly change its generation to “chase” the ACE.

  34. Automatic Generation Control • Most utilities use automatic generation control (AGC) to automatically change their generation to keep their ACE close to zero. • Usually the utility control center calculates ACE based upon tie-line flows; then the AGC module sends control signals out to the generators every couple seconds.

  35. Three Bus Case on AGC Generation is automatically changed to match change in load Net tie flow is close to zero

  36. Generator Costs • There are many fixed and variable costs associated with power system operation. • The major variable cost is associated with generation. • Cost to generate a MWh can vary widely. • For some types of units (such as hydro and nuclear) it is difficult to quantify. • For thermal units it is much easier. These costs will be discussed later in the course.

  37. Economic Dispatch • Economic dispatch (ED) determines the least cost dispatch of generation for an area. • For a lossless system, the ED occurs when all the generators have equal marginal costs. IC1(PG,1) = IC2(PG,2) = … = ICm(PG,m)

  38. Power Transactions • Power transactions are contracts between areas to do power transactions. • Contracts can be for any amount of time at any price for any amount of power. • Scheduled power transactions are implemented by modifying the area ACE:ACE = Pactual,tie-flow - Psched

  39. 100 MW Transaction Scheduled 100 MW Transaction from Left to Right Net tie-line flow is now 100 MW

  40. Security Constrained ED • Transmission constraints often limit system economics. • Such limits required a constrained dispatch in order to maintain system security. • In three bus case the generation at bus 3 must be constrained to avoid overloading the line from bus 2 to bus 3.

  41. Security Constrained Dispatch Dispatch is no longer optimal due to need to keep line from bus 2 to bus 3 from overloading

  42. Multi-Area Operation • If Areas have direct interconnections, then they may directly transact up to the capacity of their tie-lines. • Actual power flows through the entire network according to the impedance of the transmission lines. • Flow through other areas is known as “parallel path” or “loop flows.”

  43. Seven Bus Case: One-line System has three areas Area top has five buses Area left has one bus Area right has one bus

  44. Seven Bus Case: Area View Actual flow between areas System has 40 MW of “Loop Flow” Scheduled flow Loop flow can result in higher losses

  45. Seven Bus - Loop Flow? Note that Top’s Losses have increased from 7.09MW to 9.44 MW Transaction has actually decreased the loop flow 100 MW Transaction between Left and Right

  46. Pricing Electricity • Cost to supply electricity to bus is called the locational marginal price (LMP) • Presently some electric makets post LMPs on the web • In an ideal electricity market with no transmission limitations the LMPs are equal • Transmission constraints can segment a market, resulting in differing LMP • Determination of LMPs requires the solution on an Optimal Power Flow (OPF)

  47. 3 BUS LMPS - OVERLOAD IGNORED Gen 2’s cost is $12 per MWh Gen 1’s cost is $10 per MWh Line from Bus 1 to Bus 3 is over-loaded; all buses have same marginal cost

  48. LINE OVERLOAD ENFORCED Line from 1 to 3 is no longer overloaded, but now the marginal cost of electricity at 3 is $14 / MWh

More Related