An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FRCC Compliance Programand Entity Registration 2007 FRCC Compliance Workshop

  2. FRCC Compliance Organization • FRCC will be a Regional Entity with delegated responsibility and authority from NERC and FERC to monitor, assess, and enforce compliance with Reliability Standards • NERC provides oversight of the FRCC compliance program • FERC provides oversight of the NERC and FRCC compliance programs

  3. FRCC Compliance Organization • Organization Basics • FRCC Compliance Staff • FRCC Compliance Committee • FRCC Board of Directors • FRCC Board Compliance Committee • FRCC Compliance Advisory Panel

  4. Entity Registration • In 2005, the FRCC conducted the first entity registration that was limited to: • Balancing Authorities • Planning Authorities • Reliability Coordinators • Transmission Operators • Transmission Planners • Regional Reliability Organizations

  5. Entity Registration • September 3, 2006 - Federal Energy Regulatory Commission, (FERC) issued Order 672. • The order directs owners, operators and users of the bulk power system to be registered with the Electric Reliability Organization (NERC). • FERC recognized the functional model as the best method for determining who must comply with the Reliability Standards.

  6. Entity Registration • FRCC maintains a proactive registration process • The owners, operators and users of the bulk electric system maintain the responsibility to become a registered entity. • Organizations shall register for any functional designation applicable to them as soon as it becomes aware of its responsibility to register. • Changes to a registered entity’s status are to be submitted to the FRCC within 30 days of becoming known.

  7. Entity Registration FRCC submitted updated registration list to NERC March 2, 2007 • Based on NERC’s Statement of Compliance Registry Criteria (Version 3) • Consistency between regions and across the continent with respect to which entities are registered, and; • Requires that any entity reasonably deemed material to the reliability of the bulk power system will be registered, irrespective of other considerations.

  8. Entity Registration Criteria • Load Serving Entities • Peak Load > 25MW or, • Responsible for UFLS facilities or, • Responsible for UVLS facilities • Distribution Provider • System serving > 25 MW or, • Responsible for UFLS facilities or, • Responsible for UVLS facilities or, • Responsible for required SPS

  9. Entity Registration Criteria • Generator Owner/Operator • Individual Unit > 20 MVA or, • Generating Plant/Facility >75 MVA or, • Black-start unit part of restoration plan or, • Any generator material to reliability • Transmission Owner/Operator • Transmission element 100 KV or above, or lower voltage defined by FRCC as necessary for reliable operation of the grid, or that is included on a critical facilities list defined by FRCC.

  10. Entity Registration Criteria • Joint Registration Organization • May register on behalf of one or more of its members • Must accept compliance reporting responsibility for all standards applicable to the members that it registered on behalf of • Shall provide FRCC with an annual “Agency Member Registry” • Must identify primary compliance contact

  11. Entity Registration Criteria • Joint Registration • May agree on division of compliance responsibility for one or more applicable reliability standards applicable to that functions • Must have written agreement to clearly specify respective responsibilities • Both entities register for the applicable function • Must provide FRCC detailed description of division of responsibilities

  12. Disputed Registrations • Entities may be in disagreement with the FRCC regarding the appropriate functions for their company. • The FRCC and the entity will attempt to resolve the difference. • FRCC will submit to NERC the registration it believes is best supported by the registration criteria. • Entity may appeal the registration at NERC

  13. Registration Timeline • NERC is reviewing the data submitted 3/2 • Regions are to provide any revisions to NERC by 3/23 • NERC to provide updated list to trade associations week of 3/26 • NERC to send letters to each registered entity by mid-April

  14. ? Questions? Please call the FRCC Compliance Team 813-207-7965