230 likes | 485 Views
OM480. Managing Project Risk (With Material from the Text Authors). Overview. Project Control Risk Defined Risk and Control Project Control Approaches Project Control Process Project Control Techniques Preventative Control Cost Control Control as Change Management.
E N D
OM480 Managing Project Risk (With Material from the Text Authors)
Overview • Project Control • Risk Defined • Risk and Control • Project Control Approaches • Project Control Process • Project Control Techniques • Preventative Control • Cost Control • Control as Change Management
Project “Potential” Control • Project plan implementation and monitoring • Anticipate risk • Discover problems • Resolve problems • Bosses hate problems but…. • Despise Surprises! • Murphy’s Law • O’Toole’s Corollary
Risk Management Process • ID Sources • Analyze and Assess • Respond • Contingency Planning • Establish Contingency Reserves
“Sourcing” Risk • Undesirable Event • All Potential Outcome(s) • Magnitude and Severity • Chances/Probability of Event • Where in Project Timeline Occurs • Interaction w/ Other Project Events
Risk Categories • Schedule • Use of Slack • Imposed Duration • Compression • Cost • Time/Cost Dependency • Cash Flow Decisions • Price Protection • Technological
Risk Cost High Cost to fixrisk event Chances of risksoccurring Low Project life cycle Risk Event Graph
Detecting Problems • Visibility • Approachability • Internal/External Communication • Multiple Communication Channels • Reward “Gatekeepers” • Avoid Assumptions • Monitor Schedule Continuously
Contingency Planning • Nonquantitative Scenario Analysis • Ratio/Range – Prior data extrapolated • Hybrid – “rules of thumb” databases • Probability – PERT-like • Semi-quantitative • More than PERT • Confidence Intervals • Regression Analysis • Modeling
Best-case schedule 10% 470 days Baseline schedule 50% 500 days Worst-case schedule 90% 590 days Actual tracking schedule Forecast completion schedule Actual schedule 300 days 550 days Risk Schedules
Detectiondifficulty-LMH Severity-LMH Chance-LMH When Risk event Risk Assessment Matrix
Risk Responses • Reduce/Retain • “Robust” Potential Failure Points • Assume and “Do Nothing” • Transfer • Passing Risk • Subcontracting • Fixed-prices • Sharing Risk • Partnering
Accept, reduce,share, transfer Contingencyplan Risk event Trigger Responses to Risk Matrix
Problem Solving • Supportive communication • Multi-level communication • Explore multiple implications • Symptoms mask “root cause” • Brainstorm alternatives • Evaluate possibilities • Anticipate “Law of Unintended Consequences” • Respond v. React
3/29/ Y2K-Machine Dept. Project _________________Originator ________________ Date _________________ Ext. 4942 CEG Phone ________________ Impact Areas Baseline Impact 1.3M Deliverable # __________ Scope Contingency 1.313M Work Package # __________ X Staff X Budget 1.31M Cost Account # __________ Equipment Schedule X X IS-M Dept. Organization Unit __________ Description of change Install Y2K compatible chip in six computer controlled milling machines Justification (include impact if not implemented) Reprogramming cost is higher than estimated, and risk of old chips failing is higherthan estimated. (Eliminating reprogramming cost is -$10,000. Cost of Y2K chipsinstalled is +$15,000) Disposition Priority Funding Source X Approve Mgmt. Reserve $ _____________ Emergency Approve as amended 5,000. X Urgent Budget. Reserve $ _____________ Disapprove Routine Other $ _____________ Deferred S.P 4/7/ Authorized _________________ Scheduled start _________________ 4/3/ 5/10/ Date ______________________ Scheduled finish ________________ Change Request
Project Control Approaches • Dogmatic • Schedule – “Etched in Concrete” • Trade time for cost overruns • Laid-Back • Schedule – “A Ripple in a Pond” • Trade budget for schedule overrun • Pragmatic • Schedule – “Etched in Jello” • Focus on EPF • Balance time and cost implications
Project Manager Accountability • Accountability to Organization First! • Friendliness over Friendship • Camaraderie • Administer Consequences • Reward superior performance • “Pull the trigger” – Don’t Hesitate • Balanced Proaction • Continuous vigilance • Avoid Micro-management
Project Control Process • Communication • Concise and Relevant • Participation • Consensus over Compromise • Analysis • Assess Schedule & Budget Statuses • Action • Assertive Leadership • Commitment • Goals, Schedule, and PM Concepts
Summary • Project Control • Risk Defined • Risk and Control • Project Control Approaches • Project Control Process • Project Control Techniques • Preventative Control • Cost Control • Control as Change Management