Chapter 6Dowel Bar Retrofit From… Maintenance Technical Advisory Guide (MTAG)
Load Transfer Restoration Through Dowel Bar Retrofit
Learning Objectives • List benefits of load transfer restoration • Describe recommended materials and mixtures • Describe recommended construction procedures • List important quality control activities • Describe potential construction and performance problems • Identify associated solutions
Presentation Outline • Introduction • Material selection • Construction • Quality control • Troubleshooting 3-5.4
Load Transfer • Definition Mechanism of transferring wheel loads across a joint or crack • Accomplished through: • Mechanical devices (dowel bars) • Aggregate interlock • Foundation support • Load transfer efficiency (LTE)
100% Load Transfer Wheel Load Direction of Traffic Approach Slab Leave Slab Load Transfer (continued) 0% Load Transfer Wheel Load Direction of Traffic Approach Slab Leave Slab
Causes of Poor Load Transfer • Absence of load transfer devices • Failed load transfer device • Excessive crack/joint opening • Poor pavement drainage • Erodible base
Results of Poor Load TransferDeteriorated Mid-Panel Cracking
Load Transfer Restoration • Definition Installation of mechanical devices in an existing pavement to restore load transfer • Suitable for transverse joints or cracks
65 mm (2.5 in) min. 100 mm (6 in) max. Retrofitted Dowel Bar Temporary joint insert for sealant reservoir End view As required Mill or Saw cut 350* mm + 5 mm (14 in + 0.2 in) Full depth joint forming medium & dowel support T/2 T Dowel bar cap (at least one side) 6 mm (0.25 in) expansion 40 mm (1.5 in) *460 mm (18 in) max. Side view 3-5.13
Load Transfer RestorationBenefits • Reduced probability of pumping, faulting, and corner breaks • Improved long-term rideability • Increased service life
Good Candidate Projects • Relatively good condition but with: • Poor load transfer • Faulting between 3 and 13 mm (0.125 and 0.5 in) • <10% slabs with multiple cracks • Pavements expecting overlays • Medium to heavy truck traffic
Typical Item Codes http://i80.dot.ca.gov/hq/esc/oe/awards/#item_code
Module 6-1 Design, Materials & Specifications From… Maintenance Technical Advisory Guide (MTAG)
Presentation Outline • Introduction • Material selection • Construction • Quality control • Troubleshooting 3-5.18
Material Selection • Load transfer devices • Retrofitted dowel bars • Other devices • Repair (filler) materials • Portland cement concrete (PCC) • Rapid-setting proprietary materials • Polymer concretes • Epoxy-resin adhesives
Dowel Design and Layout 457 mm (18 in) 610 mm (24 in) 38-mm (1.5-in) dia. dowels 3 to 5 dowels @305 mm (12 in) 3 to 5 dowels @305 mm (12 in) Truck Lane Truck Lane 3.7 m (12 ft) 305 mm (12 in) 457 mm (18 in) AC Shoulder PCC Shoulder
Repair Material Requirements • Little or no shrinkage • Good ultimate strength • Thermal compatibility • Freeze-thaw durability • Good bond to existing concrete
Selecting Repair Materials • Partial-depth repair materials work well • Required time until opening to traffic • Laboratory testing
Module 6-2 Construction and Inspection From… Maintenance Technical Advisory Guide (MTAG)
Presentation Outline • Introduction • Material selection • Construction • Quality control • Troubleshooting 3-5.25
Construction • Slot creation • Slot preparation • Dowel bar placement • Repair material placement • Material consolidation and finishing
Slot Creation • Parallel to centerline • Diamond saw cutters vs. modified milling machines • Slot dimensions • Length: 1 m (3 ft) on surface • Width:65 and 100 mm (2.5 and 4 in) • Depth:13 mm (0.5 in) below dowel
Dowel Bar Placement • Apply bondbreaker to dowels • Attach expansion caps • Place dowel on chair at slab mid-depth • Filler board placed at mid-point of dowel bar to maintain joint • Proper alignment is critical
Repair Material Placement • Mix material in small quantities • Generally 10 mm (3/8 in) top size aggregate • Totally encase dowel bar • Consolidate with small 25 mm (1 in) spud vibrator • Apply curing compound
Presentation Outline • Introduction • Material selection • Construction • Quality control • Troubleshooting 3-5.49
Quality Control • Preliminary responsibilities • Inspection of equipment • Weather requirements • Traffic control • Construction inspection