1 / 13

Lecture #2: The Design and Construction Team

Lecture #2: The Design and Construction Team. Professor: Robert Powell, AIA TA: Matt O’Brien, AIA August 20, 2008. AREN 231: Methods and Materials. Diverse Roles of Team. KEY PLAYERS: -OWNER -ARCHITECT -CONSULTING ENGINEERS -CONSTRUCTION MANAGER. Diverse Roles of Team. CONTRACTUAL.

thad
Download Presentation

Lecture #2: The Design and Construction Team

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lecture #2: The Design and Construction Team Professor: Robert Powell, AIA TA: Matt O’Brien, AIA August 20, 2008 AREN 231: Methods and Materials

  2. Diverse Roles of Team KEY PLAYERS: -OWNER -ARCHITECT -CONSULTING ENGINEERS -CONSTRUCTION MANAGER

  3. Diverse Roles of Team CONTRACTUAL CONTRACTUAL NON-CONTRACTUAL

  4. Contractual Roles of Team CONTRACTUAL CONTRACTUAL NON-CONTRACTUAL CONTRACTUAL GENERAL CONTRACTOR CONTRACTUAL PRIME CONTRACTOR OTHER CONSULTING ENGINEERS SUB-CONTRACTORS

  5. The Pre-Design Phase *PROGRAMING *ECONOMIC FEASABILITY *SITE ASSESSMNET *GOVERNMENTAL CONSTRAINTS *DESIGN TEAM SELECTION

  6. The Design Phase *SCHEMATIC DESIGN or SD *DESIGN DEVELOPMENT or DD *CONSTRUCTION DOCUMENT or CD

  7. The Pre-Construction Phase *COMPETITIVE BIDDING *INVITATIONAL BIDDING *NEGOTIATED CONTRACTS *MULTIPLE PRIME CONTRACTS

  8. The Construction Phase *PROPOSE ACCURATE & COMPETITIVE BIDS *PREPARE DETAILED SUBMITTALS FOR APPROVAL *BUILD THE BUILDING & CONSTRUCTION ADMINISTRATION

  9. The Post-Construction Phase *SUBSTANTIAL COMPLETION *CERTIFICATE OF FINAL COMPLETION *RECORD DOCUMENTS

  10. The Owner’s CM is hired to intercept and resolve issues inherent to the design and construction of a building

  11. Prime Mechanical Contractors

  12. Prime Electrical Contractors

  13. Prime General Contractors

More Related