An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drawings supplied by firms ( As-built drawings ) LHC Quality Assurance Working Group - M. Mottier September 2000

  2. Contents • Registration and archiving • Verification and approval • Confidentiality • Folder for As-Built drawings • Process step by step LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 2

  3. Registration and archiving (1) Two possible ways: • It is done by the firm, using the Web interface of CDD • It is done at CERN. The firms supplies the drawing files on a CD ---------- The Web is suitable if: • The firm has a fast Web connection • Strict confidentiality is not required It needs registration of the firm as a CDD user and training of one operator LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 3

  4. Registration and archiving (2) The CD is suitable in all cases where the Web is not practical • The firm copies the drawings on a CD • The CD is sent to CERN • Drawings are copied from the CD to CDD at CERN It needs a central service at CERN to do the registration and copying of the files LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 4

  5. Verification and approval Once in CDD, as-built drawings should be checked and approved like tender drawings: • A technical verification by a designer • An approval by the Project Engineer LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 5

  6. Confidentiality Confidentiality of the drawings supplied by a firm may be required, for example when the execution of a contract for prototypes is going on at the same time as a call for tender for a series production. • By default, firm drawings should be considered confidential, accessible only to authorized persons • The needs for confidentiality should be discussed when placing the contract LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 6

  7. Folder for As-Built drawings As built drawings should be placed in a drawing folder attached to the baseline and the technical specification The folder containing tender drawings should be named “TENDER DRAWINGS” The folder containing the production drawings should be named “AS-BUILT DRAWINGS” See the example on the next slide LHC Quality Assurance Working Group - M. Mottier - September 2000 Page 7