LOS ALAMOS COUNTYJUDICIAL / POLICE – JAIL COMPLEX 60% SUBMITTAL August 8, 2008
SITE PLAN ` Public & Staff parking ENTRANCE POINTS TO SITE Police Parking Public & Staff parking Judicial Parking
SITE PLAN A-JAIL/POLICE C-JUDICIAL B-POLICE-EXISTING
A-JAIL/POLICE C-JUDICIAL Overall Plan – 1st Floor B-POLICE-EXISTING
Overall Plan – 2nd Floor Mechanical / Support Mechanical / Support A-JAIL/POLICE C-JUDICIAL B-POLICE-EXISTING
MAIN ENTRANCE Building A - Jail First floor POLICE JAIL SECURE ENTRANCE
Building B - PoliceFirst Floor ACCESS TO COURTS POLICE POLICE JAIL UNASSIGNED SPACE
SECURE ENTRANCE COURT NON-JURY MAIN LOBBY EXIT Building C - Judicial First Floor HEARING ROOM
COURT - JURY UPPER LOBBY Building c - Judicial Second floor
A-JAIL Building A - Jail Future Second floor VERTICAL CIRCULATION
SOUTH ELEVATION (TRINITY DRIVE) NORTH ELEVATION (MAIN PARKING LOT)
WEST ELEVATION EAST ELEVATION
Bullets here Bullets here Bullets here FROM NORTHWEST
CHANGES SINCE 2007 EXISTING GENERATOR RELOCATED PUMPS FOR DOMESTIC WATER ADDED PUMPS FOR FIRE PROTECTION ADDED MECHANICAL ROOM ADDED FOR PUMP 4” GAS SERVICE LINE RELOCATED TRINITY SIDE SITE IMPROVEMENTS CHANGED TO MEET NEW DOWNTOWN REQUIREMENTS
CHANGES SINCE 2007 FOUNDATIONS CHANGE TO DRILLED PIER AFTER ADDITIONAL SOIL INVESTIGATION ASBESTOS CONTAINING MATERIALS (LAC) ADD RECYCLE DUMPSTER – SCREENED ADD SCREEN WALL AT WEST PARKING
CHANGES SINCE 2007 Remove Gas line New Gas line New Gas line Remove Sewer Pump bldg Generator bldg New Sewer Remove Gas line Remove Sewer Pump bldg ACM’s Removal Drilled Pier foundation system New Sewer ACM’s Removal Gen bldg
BUILDING AREA SCHEMATIC DESIGN ‘07 DESIGN DEVELOPMENT ‘08 Existing Police/Jail 1st Floor 11,075 gsf 2nd Floor 1,361 gsf 12,436 total gsf • Existing Police/Jail • 1st Floor 11,586 gsf • 2nd Floor 1,361 gsf • 12,947 total gsf
BUILDING AREA SCHEMATIC DESIGN ‘07 DESIGN DEVELOPMENT ‘08 New Jail 1st Floor Added Generator 469 nsf Added Stair 173 nsf Added Elevator 69 nsf Added Elev eq. elec 151 nsf Added Pump room 220 nsf 2nd Floor (req’d for expansion) Added 2nd Floor mech, plumb, stair, elec, elevator space, equipment room 1,436 nsf Total = 15,905 gsf • New Jail • 1st Floor • 12,529 gsf • 2nd Floor • none • Total = 12,529 gsf
BUILDING AREA SCHEMATIC DESIGN ‘07 DESIGN DEVELOPMENT ‘08 Judicial 1st Floor 8,315 gsf 2nd Floor 7,282 gsf 15,497 total gsf Total Building New & Old 43,938 gsf • Judicial • 1st Floor 8,289 gsf • 2nd Floor 7,514 gsf • 15,803 total gsf • Total Building New & Old • 41,279 gsf
SCHEDULE IMPORTANT DATES • Los Alamos County Council approval of 60% - 8/21/08 • WHPacific continue to 90% Construction Docs – 8/22/08 • Submit JPJ for Foundation Only Permit – 8/25/08 • CMAR Approved by Los Alamos County Council – 9/9/08 • CMAR/WHPacific/Los Alamos Staff project refinement and cost savings measures (September & October) • Begin Construction – September 08 • Submit Final Construction Documents – 11/26/08 • Los Alamos County Council approval of FINAL- 12/16/08 • Submit for Building Permit – 12/17/08 • Complete Construction – 5/15/10or sooner