1 / 13

Fire Island Wind

Fire Island Wind. CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska ’ s first utility-scale wind project. Aerial view of Fire Island photo from fact sheet. Project Overview. Located on Fire Island, near Railbelt load center, three miles west of Anchorage

tierra
Download Presentation

Fire Island Wind

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fire Island Wind CIRI, through its Fire Island Wind LLC subsidiary, is developing Southcentral Alaska’s first utility-scale wind project Aerial view of Fire Island photo from fact sheet

  2. Project Overview • Located on Fire Island, near Railbelt load center, three miles west of Anchorage • First power fall 2012 • Chugach Electric Association power purchase agreement 25-year term starts Jan. 1, 2013

  3. Project description • 11 General Electric 1.6 MW XLE wind turbines • 17.6 MW capacity • 32.8 percent net capacity factor • 51,000 MW-hours annually ~ 6,000 households • Offset 0.5 bcf natural gas consumption annually • On-island infra-structure: roads, electrical collection and transmission systems and operations and maintenance building with overnight facilities • Subsequent phases could include up to 33 turbines

  4. Project Status Report • Chugach is buyer for up to 100 % of first phase power • Regulatory Commission of Alaska approved inclusion of cost for FIW power in CEA’s rates • Financing complete. All contracts and permits are complete.

  5. Transmission Interconnection • 12.5 mile double-circuit transmission line • $25 million State of Alaska appropriation • Construction managed by CIRI • Land based construction contractor • Submarine based construction contractor • Transmission cable and switchgear • Chugach to own and maintain line at COD

  6. Construction Contractors • Delaney Construction Group • Northern Powerline Constructors • Cruz Construction • Local Supplemental Contractors • IBEW • GMC • Spernak • Chugach Electric • CRW, RSE, EPS, D&L, TBC • Hydro Ax, Alaska Structures • Carlos Tree Service, NW Landscaping

  7. Project Schedule • 2011 • RCA approval of power purchase agreement • Complete all commercial contracts and financing • Complete transmission-related construction contracts • Complete civil and structural BOP engineering • Order long lead-time construction materials • Complete transmission-related pre-construction field work

  8. Project Schedule

  9. Project Schedule

  10. Project Schedule • 2012 • Complete on-island civil and electrical construction • Construct O&M facility • Deliver and erect wind turbines • Construct transmission interconnection • Project commissioning – wind turbines and intertie • Commercial operation

  11. Project supports Alaska energy goals • Sustainable energy project • Private investment • Creates many local jobs • Locally owned and operated • Local energy supply diversification • Long-term energy price stability • Environmentally responsible

More Related