1 / 28

65 S. ROOP STREET * SUSANVILLE, CA * 96130 (530) 257-4174 * FAX (530) 257-2558

65 S. ROOP STREET * SUSANVILLE, CA * 96130 (530) 257-4174 * FAX (530) 257-2558. LMUD District Boundaries. LMUD STATS. Service territory is approximately 1,933 square miles. 80 miles of 60kV transmission and 425 miles of distribution. 2008 peak is approximately 30 MW.

tobit
Download Presentation

65 S. ROOP STREET * SUSANVILLE, CA * 96130 (530) 257-4174 * FAX (530) 257-2558

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 65 S. ROOP STREET * SUSANVILLE, CA * 96130 (530) 257-4174 * FAX (530) 257-2558 1

  2. 1 LMUD District Boundaries

  3. LMUD STATS • Service territory is approximately 1,933 square miles. • 80 miles of 60kV transmission and 425 miles of distribution. • 2008 peak is approximately 30 MW. • Summer and winter peaks are within 1 MW of each other and remained relatively flat for the past several years. • We operate 9 substations – all served by a 60kV transmission system. 1

  4. LMUD Transmission • LMUD has no internal generation of its own. • LMUD has a wholesale PPA with Western Area Power • The main power flow is through the 60kV PG&E Caribou Sub to LMUD’s Westwood Sub. • The is an alternate 60kV feed from PG&E’s Hat Creek Sub. • Westwood Sub have two 60kV circuits running from Westwood to the Milwood Sub in Susanville. • The line runs in the same ROW about 50% 0f the route. 1

  5. The two circuit are run in parallel with two breakers in the Westwood Sub and two at Milwood. • Out of Milwood there is a 60kV circuit that runs to our Janesville and Standish Substations. • The line continues south to the backside of the Sierra Army Depot the line from Standish to the depot is de-energized. • The second 60kV circuit runs to Wendel were the Honey Lake Power Bio-mass Plant is located. • The plant wheels through our 60kV system to PG&E. 1

  6. 1

  7. 1

  8. BLM Forest Service 1

  9. We have in our service area 3 co-generation plants. • 1 Biomass Plant – Honey Lake Power (HLP) • 35 MW nameplate (Generally runs at 27 to 28 MW) • 2 Small Geothermal Plants • 2 MW – Amedee (with planned expansion to 10MW) • 1 MW – Wineagle (New drilling is planned for the area for a 23.5MW goethermal Plant) • Generation from these plants is exported to PG&E through our Westwood meter point. 1

  10. The capacity of LMUD’s transmission system is approximately 110MW. LMUD’s peak load is approximately 30MW which leaves 80MW for future growth in our system. • If we were to reserve 10MW for growth we could provide 70MW for renewable export with our existing 60kV transmission with some minor upgrades. • There are more constraints with the PG&E transmission systems from Westwood to Caribou with only 42MW of available capacity left at this point. • There are several developers who have requested capacity in our system which, at this point, cannot be provided. • The interest in Renewable Transmission excess is evident when we review the results of a meeting hosted by LMUD. 1

  11. Proposed Renewable Projects • Also in attendance at the Renewable Transmission Planning Meeting were: • Fred Nagel (President, Lassen Municipal Utility District) • Jack Hansen (Lassen County Board of Supervisors) • John Ketelsen (Lassen County Administrative Officer) • Steve Thompson (Sr. Field Rep for Dan Logue) • Rocky Deal 1

  12. There were additional developers who were unable to attend our meeting who are also interested in accessing transmission with another couple of hundred megawatts each. • We continue to this day to get calls from renewable developers asking about access to transmission through our system. • We meant this month with a geothermal developer interested in and interconnect for a 30MW plant in the Wendel area. Drilling may be started as early as March. 1

  13. California Energy Commission Renewable Energy Transmission Initiative (RETI) Part of Lassen County 1

  14. 1

  15. 1

  16. Line Upgrades? • Can LMUD provide additional capacity? • We have existing transmission rights of way (“ROW's) from Honey Lake Power in Wendel, through Susanville to our Westwood Substation. • This line could possibly be upgraded to a higher transmission voltage in the same corridor we presently have. • The voltage would be the determining factor in the width of the ROW. • At the higher voltages there may be need for a wider corridor which would require new easements and or acquisitions of additional ROWs. 1

  17. LMUD’s 230kV Proposal • Lassen’s proposal is to build a double-circuit 230kV transmission line using a bundled conductor design to result in the maximum capacity for a 230kV system. • This would provide an east / west interconnection via the proposed 230kV line which could pick up various proposed renewable energy generation projects (“Projects”) within Lassen’s service territory. • A narrow profile, single pole transmission structure would be used in Lassen’s existing right-of-way and would wheel power from Viewland to a PG&E interconnection point near Westwood, CA. 1

  18. Lassen believes that such a design is the best fit for Lassen County and this existing corridor. • The envisioned build-out of these facilities would allow Lassen the ability to draw on the most affordable sources of electricity to serve its customers and improve reliability provided by a stronger transmission grid. • The proposed line would also support local community economic development, address future energy demand growth, and support the region’s renewable energy goals, customer expectations and environmental priorities. 1

  19. 1

  20. Site of proposed Viewland Substation and RAT Line Interconnect 1

  21. Phase I • Viewland Substation interconnection to Reno-Alturas Transmission Line 345/230kV • 230/60kV Build out 25.5 miles to Milwood Substation in Susanville. • Milwood Substation, build out 23 miles of 230kV line to Westwood Substation and Meter Point. Phase II • Westwood 230kV Substation Switchyard. • Permit and construct approximately 44 miles of 230kV double-circuit transmission line from the Westwood Substation, Westwood, CA, to the Round Mountain area northwest of the Burney area. 1

  22. The ROW from Westwood to Round Mountain is a 60kV PG&E ROW and LMUD would need access to this ROW to build the line. 1

  23. PG&E Hat Creek 60kV LIne 1

  24. 1

  25. Miscellaneous • Additional Rights of Way • Scoping Meetings • Permitting – directed by Fed & State to streamline • Existing corridors (power lines already exist) • EIR & CEQA • Helps the State of California aggressively pursue 33% by 2020 RPS goal • Regional cooperation (IOUs and POUs) • LMUD’s primary contribution lies in the value of the ROWs • LMUD is pursuing available federal stimulus funding to assist with cost of project 1

  26. Benefits for LMUD Consumers • Increases reliability for LMUD’s system • Revenues help LMUD stabilize rates. • Stable rates (energy costs, important for business—both existing and those looking to relocate). • Large potential for renewable energy development. • Construction jobs • Et Cetera 1

  27. 1

  28. 1

More Related