Presentation Title One Programme – Two Clients 19 June 2012 Jenni MacGregor BSc(Hons) CEng MICE
Introduction • The First Client - External • The Second Client - Internal • Approach to servicing both • Practical Programme Challenges
Introduction Jenni MacGregor • Chartered Civil Engineer • I have 36 years of diverse civil engineering experience, principally within Major Projects and Asset Management • I have worked for two major UK civil engineering contractors, Costain and BAM Nuttall • I moved into full time planning over 25 years ago • I am currently Head of Planning for BAM Nuttall, a £800+m turnover company within the Royal Bam Group. • I have a company wide functional responsibility for providing support and guidance in relation to planning matters to all operational staff including some 70 planning engineers. I also enjoy the strategic vision and goal setting facets of the role • I contribute to several industry wide forums
Introduction BAM Nuttall – “A leading UK civil engineering company” Royal BAM – “One of Europe’s leading construction companies”
History First Mersey Tunnel Built in 1926 Liver Buildings Liverpool. Built in 1910 One of the earliest reinforced concrete buildings Mulberry Harbour World War 2
BAM Group Royal BAM Markets Netherlands, Belgium, Germany, UK, Ireland, International Construction, Property, Civil Engineering, PPP
External Clients • Transport for London • Blackwall Tunnel Northbound • Tottenham Court Road and Victoria Station redevelopments • Olympic Delivery Authority and Legacy Company • Argent at Kings Cross • Local Authorities • Network Rail • GSMR National Telecoms Programme • Rail South Framework • Airdrie to Bathgate Regeneration • Reading Station Upgrade • Other Railways • Chiltern Railways Evergreen Phase 3 • Borders Railway ECI and Design
Approach • Our approach to serving / supporting both Clients includes • A consistent approach & closer liaison with each major client • Systems – Internal growth and consolidation • Specific Sector solutions • Addressing ongoing challenges
Approach • Our External Client Project Managers and their teams require a programme that: • defines the contracted work • conforms to their WBS • allows them to predict and manage their cashflow • aligns with their reporting cycle • demonstrates progress against a baseline of their choosing • defines timing and relationship with both their and third party activities • summarises build sequences and complex relationships • accommodates change • supports EVA techniques
Approach Our Internal Project teams and Management require a programme that: • defines our contracted work • demonstrates build sequences and complex relationships • defines timing and relationship with both client and third party activities • provides output for specific customers • captures complete and demonstrates current and future activities • allows us to predict and manage our cashflow • provides output to meet internal reporting cycles • demonstrates the impact of change • supports Earned Budget techniques
The Project Project level Design 1 Construction2 Level 1 Level 2 Structures 1.1 Highways 1.2 Highways 2.2 Structures 2.1 Level 3 Rail bridge 1.1.1 River bridge 1.1.2 Retaining walls 1.1.3 Rail bridge 2.1.1 River bridge 2.1.2
Systems2008 • Large SureTrak Estate • adopted as company standard in 1994 • well established system • well embedded use • in house training • Pockets of P3 and P3e variants • Rail sector • Olympics • Complimentary in house developed systems
Systems Strategic Plan 2008 • Maximize license recovery • Manage estate centrally • Improve data security & disaster recovery • Introduce tiered license model Named & Concurrent users, single d/b only
Systems Oracle buys Primavera Licensing model changes • Named User only • Access to multiple databases permissible • Generic ID license • Greater onus on customer license management
Systems Updated Strategic Plan 2009 • Maximize license recovery • Administer and manage estate centrally • Improve data security & disaster recovery • Update all to common version (currently P6.2) • Consolidate to Sector Specific databases
Sector Solutions Consider the Rail Sector • Network Rail • London Underground (LUL) • Crossrail My role is to understand and share the key structural programme requirements which generally centre around the WBS, Cost Loading and Coding • All have Planning and Project Controls standards • The standards are accessible
Sector Solutions Outsourcing - External Hosting LoadSpring delivers Web-based application hosting Customer provides Internet access & Software licenses • SpringBoard Control Console™ interface • Robust security with strong passwords • 24/7 access with UK and US support • Scalable, efficient, collaborative working • Removes company firewall issues • New instance available within days • Dilutes in house IT resource demand
Practical Programme Challenges • Do you see what I see? • Matching system settings • Sharing layouts & filters • Retrofitting of coding structures • WBS • Activity Codes • Calendars • A moving target and lots of clients!
One Programme – Two Clients Presented to: UKOUG Primavera SIG meeting Presenter: Jenni MacGregor Contact details: 01276 63484 jenni.macgregor@bamnuttall.co.uk Date: 19 June 2012