Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee. Cabling for Shunt/Trim P/S’s on 1VQ5. - Enable Vault Quad 1VQ5 to double as Steerer by adding Shunt/Trim P/S circuits - Replaces horizontal & vertical steerers 1VSM2 and 1VSM3 (space for UCN Kicker)
E N D
Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee
Cabling for Shunt/Trim P/S’s on 1VQ5 - Enable Vault Quad 1VQ5 to double as Steerer by adding Shunt/Trim P/S circuits - Replaces horizontal & vertical steerers 1VSM2 and 1VSM3 (space for UCN Kicker) - Add Shunts/Trims with flexible options 5 P/S cables ran during 2013 S/D (SASP0154) 1VSM2 1VSM3 1VQ5 1VQ6 1VQ4 BL1V BL1A
Location of Quad Shunt P/S and Cable Run End: Vault, at 1VQ5 Start: Service Annex B2 Level Cable run summary (Shunt P/S at B2 Level) Start at P/S (on B2 Level) Run east (20m) along B2 Level cable-trays Down (4m), thru vertical section, to B3 Level West & North (21m) along B3 Level cable-trays North (4m), thru Vault wall, into Lower Vault East (12m), along Lower Vault cable-tray Up, North & Up (10m), to Upper Vault Shunt P/S Cables: # of cables ran: 5 Length of cable (ea): ~70 m Current: 100 A (DC) Fire: FT4 Rad.’n: R.I. = 5 OKO-112-24-2351 1/0-1C TS CPE EPR 600V FT4 C.M.,R.C. DC power cable spec’s (Much discussion ensued) Total run ~ 70 m (each cable) (see details on following pages) R.Creanga Contractors (ENTEC Systems Inc) [ Mar.4-13 ]
Cable Run for Quad Trim P/S (Lower-Vault Level) (B2 Level) (Lower-Vault Level) 20 m 4 m (down to B3) 4 m (B3/Lower-Vault Level) +6 m (up to vault) 13 m 4 m 12 m 3 m 5 m Total Run (per cable) ~ 70 m
Cabling for Quad Shunts 1VQ5 (main P/S) 1VQ5 (main P/S) Short “Sacrificial” Cable to Quad (DP) Shunt P/S Vault Wall Beam Plane GENESYS 40V-85A RED BLK Main Cable Run (~ 65 m) LOOKING DOWNSTREAM RED BLK - RED BLK + Bus-bar Config’n with Unipolar P/S’s 1 2 3 4 5 Cable: 1 2 3 4 5 Shunt P/S’s
Cable Run for Quad Shunt/Trim-PS (B2 Level) 1VQ1 1VSM0 15 m 1VQ2 1VQ3 N
Rack for Quad Shunt/Trim-PS (B2 Level) D.Louie (3/22/2013)
ARIEL & Shutdown Plan (2012-2016) - DRAFT Oct. 17, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) 2013 Meson Hall Cleanup Plan Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (M11 Platform, Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services July-2013: M11,M13 floor area cleared Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)
2013 Meson Hall Cleanup Plan ( Durations [dashed] & Actual Work [solid, 100% FTE’s] ) Legend: 2013 Shutdown Jobs A F M M J A N D J S O Non Shutdown Jobs J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (M11 Platform, Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 July-2013: M11, M13 floor area cleared (Almost completed ) Cleanup of M11 & M13 Expt. Area (Started in March) Cabling work for Quad steerer M11 platform work
M11 Platform Cleanup & Removal: 1. Disconnect gas-lines & recover gas-panel [MG] 2. Disconnect power to DAQ equipment (racks, bins, scopes, PC’s) on platform [SY] 3. Store M11 Hodoscope controller box [SY] (?) 4. Decouple Safety Group equipment from platform (siren, warning light, n-det.,…) [JD] 5. Disconnect/decouple water and compressed-air services from platform 6. Disconnect/decouple miscellaneous cables/hoses /etc from platform 7. Remove/recover DAQ equipment from platform [Crane req.] (75%) 8. Remove furniture (desks, chairs,…) and misc items [Crane req.] 9. Disassemble/Remove infrastructure (ducts, cable-trays) [Crane req.] (75%) 10. Disassemble/Remove platform floor-panels [Contractor: Select Steel] 11. Disassemble/Remove platform beams & columns [Contractor: Select Steel] [DM] 2 days $2.7k
Cleanup M13 Floor Area Remove PIENU and clear M13 floor area Removal of M13 B/L (Q1–B2) requires shutdown (in 2015) March 2013 2012 Japan - BL4N (CB) - swap w/ UCN septum storage loc.’n (or ISAC-2) outside
Summary: 1. Vault mods: Cleanup issues; BL1B & Vault mods Mar.5-Mar.13 Run cable & rewire Vault Quads for Steering Capability Work Estimate2 weeks; 1 BL, 1 Contractor (Electrician) 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks Jan.2-Apr.15 M11 Platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Mar.1-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate12 weeks; 1 crane operator, 2 riggers, 1 BL 3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services Finish Feb.28 PIENU BG/Calib and remove detectors (PIENU personnel) Mar.1-Jun.30 Remove PIENU and clear M13 floor area Work Estimate6 weeks; 1 crane operator, 2 riggers, 1 BL Jul.1-Sep.30 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL Needed for 2014 S/D
Historical Plots
MAP OF BEAM-SPILL MONITORS Note: BSM-47 BSM Scint ~ @ beam-height
HISTORICAL DATA from BSM-47 mSv/h or mGy/h BSM Rate ~ 100 – 300 mGy/h ~ 0.1 – 0.3 Gy/h
HISTORICAL DATA from BSM-47 mSv/h or mGy/h mSv/h or mGy/h
Currents to 1VQ4,Q5,Q6 (Historical) 192 A 129 A 106 A
Currents to 1VSM2, SM3 (Historical) Corresponds to ~ 40 A on Quad shunt
Location of Quad Shunt P/S Service Annex B2 Level SW Meson Hall Mezzanine Level 1VQ1 1VSM0 1VQ2 1VQ3 Location of Shunt vs Main P/S’s Lockout (?) Cable run Path & Shielding Blocks?
Comments: 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks M11 Platform Reroute services & cables; Clear & Remove platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Cleanup M11 expt area and above 1A/1B shielding blocks Clear M11 area for temporary storage (activated blocks) or staging area (for 2014 S/D) Clear area above 1A/1B for 2014 S/D (Excavate shielding in MH SouthWest corner) Work Estimate2.8 months (11 weeks); 1 crane operator, 2 riggers, 1 BL Flexible Does not impact UCN 2014 S/D