Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee

Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee. Cabling for Shunt/Trim P/S’s on 1VQ5. - Enable Vault Quad 1VQ5 to double as Steerer by adding Shunt/Trim P/S circuits - Replaces horizontal & vertical steerers 1VSM2 and 1VSM3 (space for UCN Kicker)

tocho
Download Presentation

Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Shutdown 2013: Cabling for Quad Steerer & Meson Hall Clean-up (Mar 27, 2013) L.Lee

  2. Cabling for Shunt/Trim P/S’s on 1VQ5 - Enable Vault Quad 1VQ5 to double as Steerer by adding Shunt/Trim P/S circuits - Replaces horizontal & vertical steerers 1VSM2 and 1VSM3 (space for UCN Kicker) - Add Shunts/Trims with flexible options  5 P/S cables ran during 2013 S/D (SASP0154) 1VSM2 1VSM3 1VQ5 1VQ6 1VQ4 BL1V BL1A

  3. Location of Quad Shunt P/S and Cable Run End: Vault, at 1VQ5 Start: Service Annex B2 Level Cable run summary (Shunt P/S at B2 Level)  Start at P/S (on B2 Level)  Run east (20m) along B2 Level cable-trays  Down (4m), thru vertical section, to B3 Level  West & North (21m) along B3 Level cable-trays  North (4m), thru Vault wall, into Lower Vault  East (12m), along Lower Vault cable-tray  Up, North & Up (10m), to Upper Vault Shunt P/S Cables: # of cables ran: 5 Length of cable (ea): ~70 m Current: 100 A (DC) Fire: FT4 Rad.’n: R.I. = 5 OKO-112-24-2351 1/0-1C TS CPE EPR 600V FT4 C.M.,R.C.  DC power cable spec’s (Much discussion ensued) Total run ~ 70 m (each cable) (see details on following pages) R.Creanga  Contractors (ENTEC Systems Inc) [ Mar.4-13 ]

  4. Cable Run for Quad Trim P/S (Lower-Vault Level) (B2 Level) (Lower-Vault Level) 20 m 4 m (down to B3) 4 m (B3/Lower-Vault Level) +6 m (up to vault) 13 m 4 m 12 m 3 m 5 m Total Run (per cable) ~ 70 m

  5. Cabling for Quad Shunts 1VQ5 (main P/S) 1VQ5 (main P/S) Short “Sacrificial” Cable to Quad (DP) Shunt P/S Vault Wall Beam Plane GENESYS 40V-85A RED BLK Main Cable Run (~ 65 m) LOOKING DOWNSTREAM RED BLK - RED BLK + Bus-bar Config’n with Unipolar P/S’s 1 2 3 4 5 Cable: 1 2 3 4 5 Shunt P/S’s

  6. Cable Run for Quad Shunt/Trim-PS (B2 Level) 1VQ1 1VSM0 15 m 1VQ2 1VQ3 N

  7. Rack for Quad Shunt/Trim-PS (B2 Level) D.Louie (3/22/2013)

  8. ARIEL & Shutdown Plan (2012-2016) - DRAFT Oct. 17, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) 2013 Meson Hall Cleanup Plan Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (M11 Platform, Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services July-2013: M11,M13 floor area cleared Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  9. 2013 Meson Hall Cleanup Plan ( Durations [dashed] & Actual Work [solid, 100% FTE’s] ) Legend:  2013 Shutdown Jobs A F M M J A N D J S O Non Shutdown Jobs J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (M11 Platform, Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 July-2013: M11, M13 floor area cleared (Almost completed ) Cleanup of M11 & M13 Expt. Area (Started in March) Cabling work for Quad steerer M11 platform work

  10. M11 Platform Cleanup & Removal: 1. Disconnect gas-lines & recover gas-panel [MG]  2. Disconnect power to DAQ equipment (racks, bins, scopes, PC’s) on platform [SY]  3. Store M11 Hodoscope controller box [SY] (?) 4. Decouple Safety Group equipment from platform (siren, warning light, n-det.,…) [JD]  5. Disconnect/decouple water and compressed-air services from platform  6. Disconnect/decouple miscellaneous cables/hoses /etc from platform  7. Remove/recover DAQ equipment from platform [Crane req.] (75%) 8. Remove furniture (desks, chairs,…) and misc items [Crane req.] 9. Disassemble/Remove infrastructure (ducts, cable-trays) [Crane req.] (75%) 10. Disassemble/Remove platform floor-panels [Contractor: Select Steel] 11. Disassemble/Remove platform beams & columns [Contractor: Select Steel] [DM] 2 days $2.7k

  11. M11 Platform Cleanup & Removal:

  12. Cleanup M13 Floor Area Remove PIENU and clear M13 floor area Removal of M13 B/L (Q1–B2) requires shutdown (in 2015) March 2013 2012 Japan - BL4N (CB) - swap w/ UCN septum storage loc.’n (or ISAC-2) outside

  13. Summary: 1. Vault mods: Cleanup issues; BL1B & Vault mods Mar.5-Mar.13 Run cable & rewire Vault Quads for Steering Capability Work Estimate2 weeks; 1 BL, 1 Contractor (Electrician) 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks Jan.2-Apr.15 M11 Platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Mar.1-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate12 weeks; 1 crane operator, 2 riggers, 1 BL 3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services Finish Feb.28 PIENU BG/Calib and remove detectors (PIENU personnel) Mar.1-Jun.30 Remove PIENU and clear M13 floor area Work Estimate6 weeks; 1 crane operator, 2 riggers, 1 BL Jul.1-Sep.30 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL Needed for 2014 S/D

  14. Historical Plots

  15. MAP OF BEAM-SPILL MONITORS Note: BSM-47 BSM Scint ~ @ beam-height

  16. HISTORICAL DATA from BSM-47 mSv/h or mGy/h BSM Rate ~ 100 – 300 mGy/h ~ 0.1 – 0.3 Gy/h

  17. HISTORICAL DATA from BSM-47 mSv/h or mGy/h mSv/h or mGy/h

  18. Currents to 1VQ4,Q5,Q6 (Historical) 192 A 129 A 106 A

  19. Currents to 1VSM2, SM3 (Historical) Corresponds to ~ 40 A on Quad shunt

  20. Location of Quad Shunt P/S Service Annex B2 Level SW Meson Hall Mezzanine Level 1VQ1 1VSM0 1VQ2 1VQ3 Location of Shunt vs Main P/S’s  Lockout (?) Cable run  Path & Shielding Blocks?

  21. Shunting for Quad Steerers

  22. Comments: 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks M11 Platform Reroute services & cables; Clear & Remove platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Cleanup M11 expt area and above 1A/1B shielding blocks Clear M11 area for temporary storage (activated blocks) or staging area (for 2014 S/D) Clear area above 1A/1B for 2014 S/D (Excavate shielding in MH SouthWest corner) Work Estimate2.8 months (11 weeks); 1 crane operator, 2 riggers, 1 BL Flexible Does not impact UCN 2014 S/D