DØ Fiber TrackerInstallation and Commissioning Don Lincoln DØ Collaboration Fermilab Director’s Review December 7, 1999
Fiber Tracker Overview stereo axial stereo axial • Scint Fibers • 830mm Æ, multiclad • 1.6-2.5m active length • 10m clear waveguide to photodetector • rad hard (100 krad) (10yr @ 20cm @1032) • Fiber Ribbons • 8 axial doublets • 8 stereo doublets (3o pitch) • Readout • 77,000 channels • VLPC readout • run at low temp (9 K) • fast pickoff for trigger • SVXII readout side view end view
Prototype Commissioning • At Lab 3, a prototype cosmic ray test has been underway for about a year. • To date: • Tested two cylinders (3A & 3B) • Lightguides and connectors • Prototype cassettes (final design) • Cryogenics and control • Prototype analog electronics boards (‘stereo’ boards, with SVX-II readout) • Standalone sequencer • DAQ • Soon • Final sequencers • VRB readout • Eventually • Final analog board (AFE) shakedown
Cosmic Ray Test of CFT Proportional Drift Tubes v v v v v v 2(3 deg) Stereo Ribbons x x x x x x 4 Axial Ribbons 110 cm Forward and Central Preshower Modules 19.05 cm 88 cm 4096 VLPC pixels 4 Cassettes Cryostat 127 cm Jadzia Warchol Notre Dame 110 cm 19.05 cm Light Guides
DAQ Jadzia Warchol Notre Dame Stan Krzywdzinski FE board on Cassette CAMAC (TDCs for drift tubes) VME CRATE Stand Alone Sequencers XVME 200 (GENERATES INTERRUPT) MVME 162 Motorola 68k CBD 8210 Ethernet link DART event in lab3sgi1
Prototype Commissioning Jadzia Warchol Volker Buescher Juan Estrada Stefan Grunendahl • Cosmic Ray Test • Installed two separate cylinders (3A/3B) • Tested lightguides • Tested prototype electronics • Tested DAQ
Pre-installation Commisisoning • At Lab 3, all components of the CFT will be tested. • Fiber positions are surveyed. • During nesting, each cylinder is aligned to the others on CMM. • CFT arrives at DAB as a single-piece unit. • Each VLPC cassette is qualified at Lab 3 • Each lightguide is tested at ND or IU prior to shipping.
Necessary Components • Installation • Support fixtures • Installation fixtures • Fiber bundles • Installation and Commission • Cassettes • Cryostat and cryogenics plant • Electronics (readout, temperature and voltage control, LEDs) • Gas system • DA system • Tracking code • Examines, etc. • Pre-Installation and Pre-Commissioning
Cryogenics Russ Rucinski Bob Barger • Two independent cryostats • Most material either in house or on order. • Fabrication 11/4/99 - 4/7/00 • Installation 4/10/00 - 4/28/00 • Shakedown 4/28/00 - 6/12/00 • Prototype installed and running at Lab 3 7/15/97. Cryostat positions, relative to DØ (Nothing to Scale)
Lab 3 VLPC Cryostat Russ Rucinski Bob Barger Test Cryostat - holds 4, full-size VLPC cassettes. Provided input to final cryo design Fully Tested Meets specification
Lightguide Production Notre Dame Indiana University • Magnitude of the problem • CPS 30 bundles of 256 fibers • FPS 64 bundles of 256 fibers • CFT 300 bundles of 256 fibers, with each cylinder having a different connector • 106 m of fiber (500 kg) • 100 CFT bundles of unconnectorized fiber, pulled to correct length • Many CPS bundles under construction. • 50% of waveguides 3/1 • 100% of waveguides 7/6
Fiber Routing I VLPC CRYOSTAT FORWARD DETECTORS ECS INSTALLATION FORWARD PRE-SHOWER SEPT 98 ICD LEVEL ZERO WAVE GUIDE FIBER BUNDLE INSTALLATION CFW CFE TRACKER CENTER CABLING SLOT BEAM WAVE GUIDE PATCH PANEL VLPC CASSETTE VLPC CASSETTE VLPC CRYOSTAT VLPC CRYOSTAT SILICON TRACKER POWER SUPPLIES 2-FRONT • Waveguide bundles consist of 256 fibers in light-tight nylon sheath • Curved connector (256 ch.) at detector • 2 128 ch. Connector at cassette end
Waveguide Installation Manpower • Waveguide Installation 5/11/00 Duration 8 weeks • Physicists: Wayne 25% ND • Shepard 25% ND • PostDoc 100% ND • 1 student 100% ND • Ray 50% • Gutierrez 50% • Engineer: Cease 50% • Techs: (All Lab 3) • Butler 100% • Kubinski " • Spartana " • Garramone " • Tolian " • C. Davis " • Flores "
Cassettes George Ginther Volker Buescher Greg Davis Dan Olis • VLPC’s and most mechanical components in house • Four prototype cassettes have been built • Production manufacture has begun • 50% completion 5/3/00 • 100% completion 9/13/00 • 2.5 cassettes/week
Cassette Engineering Drawing Constructed Cassette
Cassette Installation Manpower • Cassette Installation - First 50 4/26/00 Duration: 5 weeks • Physicists: All University of Rochester • Ginther 25% • Buescher 50% • G. Davis 50% • J. Estrada 50% • F. Canelli 50% • Engineer: • Anderson 20% • Fogelsong 25% • Techs: • B. Davis 100% Lab 3 • Barger 20% • Electronics 50% From MJ
Cassette Installation Manpower • Cassette Installation - Last 50 8/15/00 Duration: 5 weeks • Physicists: All University of Rochester • Ginther 25% • Buescher 50% • G. Davis 50% • J. Estrada 50% • F. Canelli 50% • Engineer: • Anderson 20% • Fogelsong 25% • Techs: • B. Davis 100% Lab 3 • Barger 20% • Electronics 50% From MJ
Electronics Status Marvin Johnson and crew • In House: prototype stereo boards (used in Lab3 CRT) • AFE ordered 3/8/00 • AFE 10 boards available 5/3/00 • AFE all available 8/11/00 • DFE ordered 12/15/99 • DFE 10 boards available 5/10/99 • DFE all available 9/1/00 • Mixer boards ordered 5/31/00 • Mixer boards available 7/27/00 • First crate operational 5/17/00
Tracking Test Kin Yip Norm Graf • Current Code can track single muons as long as impact parameter is not too big. • Run I algorithms allowed larger impact parameter
EXAMINE/Data Integrity Andrei Mayorov Indiana University • Code exists and is ready for data
Cosmic Ray Manpower • Cosmic Ray Run 7/15/00 Duration: 8 w • Physicists: • Warchol 100% • ND PostDoc 100% • Mayorov 100% • Lincoln 25% • ND Students 100% • Techs: • Electronics 25% From MJ
CFT Timeline 2000 2001 J F M A M J J A S O N D J F 4/27 Ribbon Mounting 5/11 Assembly Complete Roll in 2/1 3/13 4/24 9/25 10/30 9/18 Beam-ready Support Design/ Fabricate 5/12 5/25 7/24 FT install/hookup SMT install/ hookup 50% 3/1 7/6 Waveguide production 4/7 Cryo Fabrication 4/10 4/28 6/12 Cryo Install/Shakedown 50% 5/3 9/13 Cassette Assembly 8/01 10/4 5/17 50% Cassettes Installed 5/17 9/5 10/30 1st CFT crate operational Full System Test 3/8 4/7 Full DAQ Startup 6/12 10/30 Commission CFT
Technician Manpower Fiber Tracker Tech Effort FNAL 25 20 15 All FTEs Install. 10 5 0 Jul-99 Jul-00 Jan-99 Jan-00 Jan-01 Nov-99 Nov-00 Mar-99 Mar-00 Sep-99 Sep-00 May-99 May-00 Fiber Tracker Note about the legend: “All” - refers to effort assigned to all tasks in the relevant schedule “Install.” - refers to effort assigned to a subset of those tasks flagged as installation tasks Tech effort is sum of MTF112+ETF112
Summary • All components will be pre-tested and pre-commissioned, prior to arrival at DAB • Lightguide map is complete. • Manpower lists here are adequate for installation • Will need close cooperation with electronics group for cosmic ray commissioning
Ribbons s = 18.4 mm Ave. = 0.3 mm
Ribbons - Optical Connectors • Have now received »50% of curved connectors • Material - Torlon • Optical coupling efficiency > 90%
Mechanical SupportsWBS 1.1.2.7 Cylinder 8 50 meas. Along L 3.5 mil RMS 1 division = 6.25 mil
Ribbon Mounting G. Gutierrez Ron Ray John Krider
Support Fixtures • Two (three?) fixtures at 3 & 9 o’clock (possibly one at 6) • Aluminum plates • Connect to the FT between layers 6-8 • Design 2/1/00 - 3/13/00 • Fabricate 3/14/00 - 4/24/00 • Kurt Krempetz
Installation Fixturing Solenoid Rollers CFT • Technique same as inserting solenoid • Use same (modified) fixturing • Design/fabricate installation fixture 2/18/00 - 4/14/00
CFT Install Manpower • CFT moves to DØ 5/4/00 Duration: 1 week • Fnal Surveyors 100% • Krempetz 50% • D. Butler 100%