260 likes | 361 Views
LRTP Consistency Review for STIP Amendments and NEPA Approval. Office of Policy Planning, FDOT Office of Project Development, FHWA September 10, 2013. Guidance. Purpose: Sets thresholds for project changes that trigger LRTP amendments at: STIP approval STIP amendment NEPA approval
E N D
LRTP Consistency Review for STIP Amendments and NEPA Approval Office of Policy Planning, FDOT Office of Project Development, FHWA September 10, 2013
Guidance • Purpose: • Sets thresholds for project changes that trigger LRTP amendments at: • STIP approval • STIP amendment • NEPA approval • Addition or change to plan • Provide • Analytical framework for consistency review 2
Coordination/Communication District Coordination/Communication REQUIRED FHWA 3
Consistency • Project must be consistent with Adopted LRTP Cost Feasible Plan. • Variables for Review: • Cost • Timing • Project Scope 4
First STEP • Clearly identify project within LRTP: • Whole • Segment (corridor) • New • Identification facilitates communication LRTP Project 5
Analyze * Base document 6
Analyze TILT INVALID START OVER * Base document 7
Analyze * Base document 8
Cost for Determining LRTP Amendment • Project cost includes: • Phases after PD&E • Design/PE • ROW • Construction Cost 9
Principle: Cost • Amendment Needed • Project cost > 50% AND > $50 million • Ramifications • Change of scope • Project justification $100 $90 Amendment Needed $80 $70 $60 Cost: Percent increase over original 60% 80% 100% 40% 70% 20% 30% 90% 10% $40 $30 $20 $10 Cost Increase (millions) 10
Analyze * Base document 11
Principle: Timing • Automatic LRTP amendment: • Project added to LRTP 1st 5 years (TIP/STIP years) causes imbalance resulting in project moved out • Automatic modification: • Project/phases: = or < $5 million Project Costs Available Funding LRTP TIP/STIP Years • Automatic amendment: • Full project deleted from LRTP CFP 12
Timing • Projects within LRTP displayed in bands of years • 5 year increments 13
Timing (Amendment) • Required Amendment when: • Advancing project > 2 bands (10 years) • Adding phase from CFP to LRTP 1st 5-year band (TIP/STIP years) causing imbalance • Adding new project to Cost Feasible Plan • Adding new phase to LRTP 1st 5-year band (TIP/STIP years) from Needs Plan causing imbalance 14
Analyze * Base document 15
Principle: Scope • Major change in scope: automatic amendment • Change in project termini (expansion) • Addition (add bridge, lanes, interchange) • Minor change: • Project termini may have minor variations = or < 5% of total project length • Cost analyses may indicate scope change 16
Review Project Principles • Coordination/communication essential & continual • Project description – consistent with LRTP • Establish cost, timing, scope for project (phase) analysis Automatic Amendments • Change in scope • Increase in cost of over 50% AND $50 million • Advancing project > 10 years or (2) five-year bands • Adding new project to CFP • Moving project to first LRTP 1st 5-years (TIP/STIP years), causing imbalance 17
TIP/STIP Consistency with LRTP • When assessing for LRTP Consistency, look at: • Project costs • Initiation phase • Project scope • Look to Florida LRTP Amendment Thresholds document for further guidance. 18
Questions? 19
NEPA CONSISTENCY NEPA Document Consistency • NEPA Approval Granted If: • Environmental Requirements Satisfied; and • Amendment to LRTP, STIP or TIP is NOT Needed; and • Funding Scenarios Are Met Planning Consistency 20
Final NEPA Document Approval Progress/Commitment Variable • “Open ended project” • Allocation of funds (PDE/Design) for a project with no clear time frame or commitment for construction. • Ramifications: • Inefficient use of limited transportation funds • Potential projects based on outdated planning assumptions and design • Demonstrate progress and commitment towards construction of project Variable: 21
Acceptable Project Funding Scenarios for FHWA NEPA Approval Note: PE means Design 22
Acceptable Project Funding Scenarios for FHWA NEPA Approval Note: PE means Design 23
Acceptable Project Funding Scenarios for FHWA NEPA Approval Note: PE means Design 24
Unacceptable Project Funding Scenario for NEPA Approval 20 Years Note: PE means Design 25
Questions? 26