An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LINAC System Engineering / Design StatusC.E. Rago

  2. Design Elements • Detailed design requirements • Engineering Specification Document (ESD) • Documents to support fabrication & installation. • Detailed drawings and models. • Assembly procedures, component travelers, fabrication QA. • Documents for long term operation & maintenance. • System Schematics • Project Data Base • Design data and operational histories.

  3. LCLS Installation and Commissioning Time-Line X-Ray tunnel/FEH Install X-Rays in FEH LTU/Und/Dump FEE/NEH Install First Spont. Light CF Early Occupancy X-Ray Systems Checkout - Commission e- beam & Photon Systems Checkout CD-4b CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M 2007 2008 2009 2010 PPS PPS Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 Operations LTU/Und/FEE Commissioning NEH Operations Linac/BC2 Commissioning linac/BC2 Install FEL Commissioning

  4. Design and Fabrication Tracking Schedule

  5. BC2/L3/BSY Status2007 Installation • BC2 Status • Designs are almost complete! • Spot Shielding – drawings ready waiting RP final approval. • Seismic proofing of center movable magnets is working. • L3 Status • Designs are complete! • All beam line components/supports are in fabrication. Sufficient documentation for installation SOW. • BSY Status • Corrector & Quad Modification – with Accelerator Dept.

  6. 2007 Installation Status (cont.)BC2

  7. 2007 Installation Status (cont.)L3

  8. BTH StatusLTU Co-occupancy 2008 • 6/11 Section ID drawings released. • Component Stands out for fabrication. • Support Drawings for SOW / Stand Installation complete. • Magnet Drawings Complete • BYKIK Assembly • Drift Tubes / Prototype & Standard Lengths complete. • Working • Repackaged diagnostics where necessary. • Spot Shielding / Collimation

  9. Electron DumpsCo-occupancy 2008 • 2/3 ESD pending RP analysis. • 80% of design for fabrication complete. • Working • Main Electron Dump • Electron Safety Dump • ST1,2,3 (3 XES Stoppers d.s.Safety Dump) • TDUND (Tune-Up Dump between LTU & UND) • PCPM1 / Shielding (Collimator at Dump Vertex) • Wall 1 Interface (Shield Wall d.s. of electrons)

  10. Design / Data Base Sector 21 Simplified Models / Project Data Base Laser stopper BLM BC1 LX L1 Ins/SAB Wall

  11. 6-Months Look-ahead • Complete Design2 for LTU & E-Dumps. • Prepare Models for Operations. • Secure all non-model information into DB. • Support all Undulator & LUSI requests. • Prepare to get small!