1 / 53

Welcome to VRF System Design Training Course for

Welcome to VRF System Design Training Course for. System & Sales engineer Pin CAI Akimasa SHIRAI. 1. EQUIPMENT SELECTION. 1-1 EQUIPMENT SELECTION PROCEDURE / LINE-UP 1-2 MODEL SELECTION AND CAPACITY CALCULATION 1-3 RESTRICTIONS ON EQUIPMENT SELECTION.

tori
Download Presentation

Welcome to VRF System Design Training Course for

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome to VRF System Design Training Course for System & Sales engineer Pin CAI Akimasa SHIRAI

  2. 1. EQUIPMENT SELECTION 1-1 EQUIPMENT SELECTION PROCEDURE / LINE-UP 1-2 MODEL SELECTION AND CAPACITY CALCULATION 1-3 RESTRICTIONS ON EQUIPMENT SELECTION

  3. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  4. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  5. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ INDOOR UNIT LINEUP (1/2)

  6. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ INDOOR UNIT LINEUP (2/2)

  7. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  8. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ REQUIRED OPTIONAL PARTS

  9. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  10. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OUTDOOR UNIT LINEUP Controller Box

  11. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OUTDOOR UNIT COMBINATION ■ CAPACITY RANGE

  12. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  13. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ CONTROLLER UNIT LINEUP

  14. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  15. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ ADAPTOR / CONVERTOR LINEUP

  16. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  17. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OPTIONAL PARTS (OTHERS) (1/2)

  18. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OPTIONAL PARTS (OTHERS) (2/2)

  19. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP

  20. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP 7 to 84 14 to 90 7 to 60 174 to 560 181 to 567 7 to 252 ■ OPTIONAL PARTS (BRANCH KIT) (1/3) 90, 91, 180 and 181 are the total values for the indoor unit model code connected downstream. 84 to 173 91 to 180 7 to 90

  21. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OPTIONAL PARTS (BRANCH KIT) (2/3) 2 branches Separation tube 90, 91 180 are the total values for the indoor unit model code connected downstream.

  22. 1-1 EQUIPMENT SELECTION PROCEDURE / LINEUP ■ OPTIONAL PARTS (BRANCH KIT) (3/3)

  23. 1-2 MODEL SELECTION AND CAPACITY CALCULATION

  24. 1-2 MODEL SELECTION AND CAPACITY CALCULATION ■ EXAMPLE

  25. 1-2 MODEL SELECTION AND CAPACITY CALCULATION COOLING HEAT LOAD : 120W / m2

  26. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (TCin)f From capacity table

  27. 1-2 MODEL SELECTION AND CAPACITY CALCULATION Compensation coefficient = 0.903 H = 20m L = 67m

  28. 1-2 MODEL SELECTION AND CAPACITY CALCULATION

  29. 1-2 MODEL SELECTION AND CAPACITY CALCULATION Room 5 (TCin)e < Heat load Change indoor unit

  30. 1-2 MODEL SELECTION AND CAPACITY CALCULATION AU30 8.80 9.43 8.52 (TCin)e > Heat load

  31. 1-2 MODEL SELECTION AND CAPACITY CALCULATION ① ② Sum of ① 68.4 Sum of ② 73.3

  32. 1-2 MODEL SELECTION AND CAPACITY CALCULATION 22HP(AJ*126LATF + AJ*A72LATF) 62.4 68.4 / 62.4 = 109.6%

  33. 1-2 MODEL SELECTION AND CAPACITY CALCULATION

  34. 1-2 MODEL SELECTION AND CAPACITY CALCULATION 22HP(AJ*126LATF + AJ*A72LATF) 62.4 68.4 / 62.4 = 109.6% 68.99 0.903 69.88 x 0.903 = 63.1

  35. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (i) Total indoor unit capacity at design temperature 73.3 (ii) Compensated capacity of outdoor unit63.1 The smaller one of (i) and (ii) 63.1 22HP (AJ*126LATF + AJ*A72LATF) 69.88 0.903 69.88 x 0.903 = 63.1

  36. 1-2 MODEL SELECTION AND CAPACITY CALCULATION I. U.capacity System capacity x Total of I. U. capacity 11.7 11.711.7 11.7 8.12 8.12

  37. 1-2 MODEL SELECTION AND CAPACITY CALCULATION Smaller than heat load

  38. 1-2 MODEL SELECTION AND CAPACITY CALCULATION 22HP ⇒ 24HP 24HP(AJ*126LATF + AJ*A90LATF) 68.0 68.4 / 68.0 = 100.6%

  39. 1-2 MODEL SELECTION AND CAPACITY CALCULATION

  40. 1-2 MODEL SELECTION AND CAPACITY CALCULATION 22HP ⇒ 24HP 24HP(AJ*126LATF + AJ*A90LATF) 68.0 68.4 / 68.0 = 100.6% 73.10 0.903 66.0 Total of indoor unit : 73.3 kW 66.0 12.3 12.3 12.3 12.3 8.49 8.49 12.0 12.0 12.0 12.0 7.44 8.40 Actual capacity ⇒ Heat load

  41. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Cooling

  42. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Cooling Indoor temp 19℃WB

  43. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Cooling Rated capacity ratio 100%

  44. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Heating

  45. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Heating Indoor temp 20℃DB

  46. 1-2 MODEL SELECTION AND CAPACITY CALCULATION (System capacity characteristic) Heating Rated capacity ratio 100%

  47. 1-3 RESTRICTIONS ON EQUIPMENT SELECTION

  48. 1-3 RESTRICTIONS ON EQUIPMENT SELECTION ■ CONNECTABLE UNIT IN ONE REFRIGERANT SYSTEM Master Unit Slave Unit Slave Unit

  49. 1-3 RESTRICTIONS ON EQUIPMENT SELECTION ■ MAXIMUM CONNECTABLE INDOOR UNIT (1/2)

  50. 1-3 RESTRICTIONS ON EQUIPMENT SELECTION ■ MAXIMUM CONNECTABLE INDOOR UNIT (1/2) ΣIndoor units capacityOutdoor unit capacity Based on rated cooling capacity

More Related