An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Responding to a High Profile Crisis:A Case Study Penny Neferis Director Emergency Response & Care

  2. Outline • JetBlue Overview • Infrastructure of our Plan • Operational Challenges • Lessons Learned

  3. Who We Are • Started February 11, 2000 • 12,015 Crewmembers • 4 Support Centers • Corporate - Forest Hills, NY • Reservations - SLC, UT • Finance - Darien, CT • Training – Orlando, FL • 5 Crew Bases • JFK, BOS, FLL, LGB, MCO

  4. Where We Jet • 51 BlueCities • 500 Flights per day • 134 Aircraft • Over 100 million customers

  5. Dilbert’s Crisis Plan

  6. Emergency Response & Care Program • Maintain Emergency Operations Manual • Ensure compliance with Aviation Family Assistance Disaster Plan 1996 • Maintain Family Assistance Plan • Support & oversight of Station Emergency Plans “Red Bag” • Manage over 300 crisis/ER team members & 750 Care Team • Conduct corporate, station training and exercises • Support Business Continuity initiative • Manage Employee Assistance Program and employee crisis

  7. Crisis/Emergency Response Teams

  8. Emergency Command Center • Key Team Members • Flight Ops • Inflight • Legal • Finance • Care • 60 members • Technical Ops • Airports • Communications • Security • IT

  9. Go Team • The Go Team consists of all personnel who are designated to go to the accident site • Participate in the accident investigation • Coordinate family assistance activities • Provide incident management and support • 75 Team members • Location for deployment:JFK Building 81

  10. Family Support Team • Key Roles • Lock & reconcile manifest • Staff crisis call center • Conduct family notifications • Coordinate travel • Launch Care Team • 120 FST members & 100 Leaders/Support

  11. Drill Pictures

  12. What We Have Prepared For

  13. Operational Challenges

  14. FANTASY: What Ice Storms Look Like

  15. 2007 Ice Storms: Round ONE February 14, 2007 - What happened? • Ice Pellets Regulation • Wanted to “do the right thing” and not cancel flights • Aircraft could land but could not take off • No gate space at JFK/aircraft on the runway • Crews out of position/unable to get to work • Incredibly high load factor (President’s Day)

  16. REALITY: What Ice Storms Look Like

  17. REALITY: What Ice Storms Look Like

  18. 2007 Ice Storms: Round ONE How we got through it….

  19. 2007 Ice Storms: Round TWO March 17, 2007 - What happened? • Major ice storm forecasted for Northeast • Crews (ONCE AGAIN) out of position/unable to get to work • Relatively high load factor (St. Patrick’s Day) • Intense pressure to “GET IT RIGHT”

  20. 2007 Ice Storms: Round TWO March 17, 2007 - How we did it? • Had decisions made early on • Cancellations made early on • Communications sent out early and throughout event • Extra support staff brought in to help at airports • Operated with a new “Customer Bill of Rights”

  21. March 2007 Ice Storm: Timeline of Notifications 3/16/07 @ 3:23am378 notifications… 3/16/07 @ 12:43pm4,430 notifications… 3/16/17 @ 1:04pm2,683 notifications … 3/16/07 @ 3:25pm2,683 notifications… 3/16/07 @ 3:49pm4,427 notifications… 3/16/07 @ 9:31pm444 notifications… 3/17/07 @ 3:12am601 notifications Grand Total: notifications 15,646

  22. Our Lessons Learned • When you are in a battle with Mother Nature, she will win • Get the most out of your notification system – be creative • Debrief from events, document, change/add procedures so that you can learn from your mistakes • Communicate, communicate, communicate • Have key players identified to make the tough decisions with 2nd, 3rd, and 4th back ups identified • Don’t wait for a crisis to assess major needs – start planning and testing your plan now include events that are outside of your normal operation!

  23. Our Next Steps • Implement Business Continuity into our culture • Taking the time and resources to be proactive to be prepared • Drill scenarios to expand beyond accidents • Create checklists and procedures for high impact critical events • Debrief after events, create reports and new procedures

  24. Comments “I was so surprised and touched to be contacted by the Care Team to know if I was ok, which I am. … thank you for your support.” -JetBlue Inflight Crewmember, San Diego Wildfires, October 23, 2007

  25. Responding to a High Profile Crisis:A Case Study Thank you! Contact: Penny Neferis 718-709-3511 penny.neferis@jetblue.com