1 / 18

“Materials” Group under Sub group 7 of working group on power

“Materials” Group under Sub group 7 of working group on power. “Materials” group under sub group 7. 1 st meeting of the above group held on 27.06.2011 at BHEL New Delhi. The meeting was attended by CEA, SAIL, NALCO, CMA, IEEMA, PGCIL, FIMI, MoMines.

trygg
Download Presentation

“Materials” Group under Sub group 7 of working group on power

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. “Materials” Group under Sub group 7 of working group on power

  2. “Materials” group under sub group 7 • 1st meeting of the above group held on 27.06.2011 at BHEL New Delhi. The meeting was attended by CEA, SAIL, NALCO, CMA, IEEMA, PGCIL, FIMI, MoMines. • 2nd meeting held on 04.07.2011 at BHEL New Delhi. The meeting was attended by CEA, SAIL, CMA, PGCIL, FIMI, MoMines.

  3. Areas covered • Capacity addition projections • Material requirement • Cement • Structural steel • Reinforcement steel • Castings & Forgings for TG sets • Tubes & Pipes • Thick Boiler Quality Plates • Copper, Aluminum, Zinc • Thermal insulation • CRGO steel • Impediments • Short circuit testing facilities • Gas Insulated Substation • EHV XLPE cables • New Initiatives • Materials for Advanced Ultra Supercritical Thermal Power Plants • Constraints/ Policy supports • CRGO, CRNGO, Thick Boiler Quality Plates • Recommendations

  4. Capacity addition projections • The likely capacity addition during 11th Plan would be about 52000 MW. Further, the capacity likely to be added during 12th plan would be 76489 MW and during 13th Plan would be 96200 MW as per the all India demand supply analysis carried out by CEA.

  5. Material Requirements for Generating Stations • Cement & Steel for Thermal Projects were considered keeping in view the norms developed by CEA and historical data for NTPC’s Plants.

  6. Material Requirement for Power System Network Based on norms developed by CEA and historical data of PowerGrid

  7. Requirement of Cement & Steel • Total requirement of Cement for Power Sector* is projected to be 211 lakh MT and 269 lakh MT for 12th and 13th plan respectively. The production of Cement for the year 10-11 was 2310 lakh MT (CMA). • Total requirement of structural steel* is projected to be 90 lakh MT and 110 lakh MT for 12th and 13th plan respectively. The production of structural steel for the year 10-11 was 55 lakh MT (JPC). • Total requirement of reinforcement steel is projected to be 45 lakh MT and 57 lakh MT for 12th and 13th plan respectively. The production of structural steel for the year 10-11 was 244 lakh MT (JPC). * Excluding Distribution system networks & power and distribution transformers

  8. Requirement of other materials • As per the details provided by Equipment Manufacturer* for thermal 500/660/800 MW sets assuming 60% supercritical sets in 12th plan and 100% supercritical sets in 13th plan. • Indigenous capacity for Tubes & Pipes is projected as 4.4 lakh MT and 5.3 lakh MT for 12th and 13th plan respectively. * BHEL

  9. Requirement of other materials – copper, aluminium Power Sector requirement of Copper would be approx. 12.5 lakh MT* for the 12th plan. This is expected to grow at a CAGR of approx. 10% p.a. At the end of 12th plan, the projected production of Copper is 15.0 lakh MT** p.a. Projected production of Aluminium is 145.58 lakh MT during 12th plan and 178.82 lakh MT# during 13th plan. Projected requirement for Aluminium in Power Sector is 12.54 lakh MT and 13.7 lakh MT for 12th and 13th plan respectively. * IEEMA ** FIMI # FIMI & NALCO

  10. Requirement of other materials - zinc • Requirement of Zinc based on industry norms. The annual production capacity of Zinc is 10.0 lakh MT*. * Source - FIMI

  11. Requirement of other materials – thermal insulation Average thermal insulation requirement for a 500/660/800 MW unit is about 2000 MT* per set. For thermal capacity addition of about 64516 MW in 12th Plan and about 78600 MW in 13th Plan, thermal insulation requirement in 12th Plan and 13th Plan would be about 2.1 lakh MT and 2.7 lakh MT respectively. * Source - BHEL

  12. Total requirement of various materials for Capacity Addition planned during 12th & 13th Plans

  13. Impediments • Lack of Short Circuit Testing Facilities in India for large Power transformers of 100 MVA and above. Initiative by National High Power Test Laboratory Private Limited (NHPTL - a Joint Venture of NTPC, NHPC, POWERGRID & DVC) to develop “On Line High Power Short Circuit Test Facility” in India expected by Dec’2012. • Gas Insulated Substation: 220 kV and above GIS are being imported. One indigenous manufacturing facility has come up recently (M/s Areva). Further manufacturing capacity needs to be augmented. • EHV XLPE cables: Indigenous Manufacturing facilities needed for 400 KVA and above.

  14. New initiatives Materials for Advanced Ultra Supercritical Thermal Power Plants • The development of Advanced Ultra Supercritical (Adv-USC) (steam parameters: pressure ≥300 kg/cm2, temperature ≥700 °C) technology for thermal power plants has been initiated under the proposed National Mission for Development of Clean Coal (Carbon) Technologies. • BHEL, NTPC and IGCAR (Indira Gandhi Centre for Atomic Research) have been identified as the partners for developing the technology and setting up an 800 MW Adv-USC power plant.

  15. Constraints/ Policy support CRGO* • Critical and strategic input for Power transformers • Worldwide only 12 manufacturers controlling the supply, sales and prices • Total worldwide production 18.5 lakh MT against present Indian consumption of 2.5 lakh MT p.a. (fully imported) • Restrictions imposed on imports by Quality Control Order (dt: 24.06.2011) of Ministry of Steel with mandatory BIS certification – only six months time given for certification while as per BIS, minimum time required for certification is six months • Restriction of competition to only BIS certified suppliers will drive the cost of Power Sector equipements • Supply constraints may lead to disruption of manufacturing of Power and Distribution transformers impacting National Power Capacity addition program • Similar situation for Higher grade of CRNGO which is being imported for use in Electrical Rotating Machines * Source - IEEMA

  16. Constraints/ Policy support Boiler Quality Thick Plates* • Presently BQ plates thickness above 63 mm with required width and length being imported. Projected requirement is 1 lakh MT each for 12th and 13th plan • Only 4-5 qualified foreign Steel Mills • Indigenous capacities being built up by Welspun, JSPL, Essar and SAIL may meet partial requirement • Also put under mandatory BIS certification reqmt. • Restriction of competition to only BIS certified suppliers will drive the cost • Supply constraints may lead to disruption impacting National Power Capacity addition program * Source - BHEL

  17. Recommendations • There is no likelihood of shortage of key materials (except CRGO, higher grade CRNGO, thicker boiler quality steel plates) including the imports requirements • For power capacity addition planned for 12th and 13th plans, detailed analysis needs to be done by Planning Commission considering requirement of all sectors of the economy.

  18. Thank You

More Related