1 / 21

The University of Massachusetts Building Authority

This report provides an update on the workforce utilization and diversity in construction projects at the University of Massachusetts Boston. It includes data on M/WBE participation, veterans' efforts, and general academic building and utility corridor and roadway relocation projects.

tuckerb
Download Presentation

The University of Massachusetts Building Authority

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Boston-Access & Opportunity Committee Bi-Monthly Report November 24, 2015 The University of Massachusetts Building Authority Patricia A. Filippone, Executive Director

  2. UMass Boston Project Labor Agreement Historical Workforce Utilization Snapshot

  3. UMBA Staffing Director of Capital Projects – Joe Naughton Capital Projects Coordinator – Sean Regan Compliance Analyst – Maggie Drouineaud

  4. UMass Boston Project Labor Agreement Projects • General Academic Building 1 • Stage: Construction • Estimated Construction Cost: $105 M • OPM: Joslin, Lesser + Associates • CM: Gilbane, Inc. • Steve Duvel, Senior Project Executive • Jim Driscoll, Senior Project Manager • Danielle Skilling, EEO Compliance Officer • Utility Corridor and Roadway Relocation • Stage: Bidding/Construction • Estimated Construction Cost: $148 M • OPM: Joslin, Lesser + Associates • CM: BOND • Bob Mischler, Project Executive • Mike Spodek, Senior Project Manager • Elio DiBiase, Project Manager • Samantha Bond, Assistant Project Manager

  5. Workforce Utilization Snapshot *Veterans goal was not established in the PLA and is measured on a “Best Faith Efforts” basis.

  6. MBE/WBE Construction Business Participation *Some firms are both M and WBE.

  7. General Academic Building 1 Project – to – Date M/WBE Update • Boston Residents – 35% • Minority – 30% • Female – 6% • Veterans – 5% • M/WBE – 12.51% • Percentage of Contracts Awarded-to-date – 100 %

  8. General Academic Building 1 Results by Contractor- October 2015

  9. General Academic Building 1 Results by Contractor- Project to Date

  10. General Academic Building 1 Results by Trade- October 2015

  11. General Academic Building 1 Results by Trade –Project to Date

  12. GAB 1 Workforce Diversity October 2015 Project-to-Date • Residents – 35.93% • Minority – 28.77% • Female – 5.55% • Veterans – 4.80% June 2015 • Residents – 36.89% • Minority – 31.82% • Female – 6.18% • Veterans – 3.63%

  13. GAB Project – M/WBE Construction Business Detail

  14. Utility Corridor & Roadway Relocation Project Project – to – Date M/WBE Update • Boston Residents – 29% • Minority – 23% • Female – 7% • Veterans – 3% • M/WBE – 14% • Percentage of Contracts Awarded-to-date – 97%

  15. Utility Corridor and Roadway RelocationResults by Contractor – October 2015

  16. UCRRResults by Contractor – Project to Date

  17. Utility Corridor and Roadway RelocationResults by Trade – October 2015

  18. Utility Corridor and Roadway RelocationResults by Trade – Project to Date

  19. Utility Corridor & Roadway Relocation Project Project-to-Date • Boston Residents – 30% • Minority – 24% • Female – 7% • Veterans – 4% Month of June • Boston Residents – 19% • Minority – 22% • Female – 6% • Veterans – 0% *Graph courtesy of Policy Group on Tradeswomen Issues (PGTI)

  20. Utility Corridor & Roadway Relocation Project

  21. Upcoming UMBA Projects at UMass Boston • Renovation of Existing Academic Buildings • Stage: Schematic Design • Construction Commencement – Fall 2016 • Project Budget = $75 million • OPM: Hill International • Architect: Cannon Design • Energy Producing Facility • Stage: Entering Design Development • Construction Commencement – Summer 2016 • Project Budget = $32 million • OPM: Jacobs • Architect: Cambridge 7 • CM: Gilbane • Parking Garage • Stage: Study • Construction Commencement – Summer 2016 • Project Budget = $45 million • OPM: Skanska • Residence Hall • Stage: Study • Construction Commencement – Summer 2016 • Project Budget = $120 million

More Related