This report provides an update on the workforce utilization and diversity in construction projects at the University of Massachusetts Boston. It includes data on M/WBE participation, veterans' efforts, and general academic building and utility corridor and roadway relocation projects.
E N D
Boston-Access & Opportunity Committee Bi-Monthly Report November 24, 2015 The University of Massachusetts Building Authority Patricia A. Filippone, Executive Director
UMass Boston Project Labor Agreement Historical Workforce Utilization Snapshot
UMBA Staffing Director of Capital Projects – Joe Naughton Capital Projects Coordinator – Sean Regan Compliance Analyst – Maggie Drouineaud
UMass Boston Project Labor Agreement Projects • General Academic Building 1 • Stage: Construction • Estimated Construction Cost: $105 M • OPM: Joslin, Lesser + Associates • CM: Gilbane, Inc. • Steve Duvel, Senior Project Executive • Jim Driscoll, Senior Project Manager • Danielle Skilling, EEO Compliance Officer • Utility Corridor and Roadway Relocation • Stage: Bidding/Construction • Estimated Construction Cost: $148 M • OPM: Joslin, Lesser + Associates • CM: BOND • Bob Mischler, Project Executive • Mike Spodek, Senior Project Manager • Elio DiBiase, Project Manager • Samantha Bond, Assistant Project Manager
Workforce Utilization Snapshot *Veterans goal was not established in the PLA and is measured on a “Best Faith Efforts” basis.
MBE/WBE Construction Business Participation *Some firms are both M and WBE.
General Academic Building 1 Project – to – Date M/WBE Update • Boston Residents – 35% • Minority – 30% • Female – 6% • Veterans – 5% • M/WBE – 12.51% • Percentage of Contracts Awarded-to-date – 100 %
General Academic Building 1 Results by Contractor- October 2015
General Academic Building 1 Results by Contractor- Project to Date
General Academic Building 1 Results by Trade –Project to Date
GAB 1 Workforce Diversity October 2015 Project-to-Date • Residents – 35.93% • Minority – 28.77% • Female – 5.55% • Veterans – 4.80% June 2015 • Residents – 36.89% • Minority – 31.82% • Female – 6.18% • Veterans – 3.63%
Utility Corridor & Roadway Relocation Project Project – to – Date M/WBE Update • Boston Residents – 29% • Minority – 23% • Female – 7% • Veterans – 3% • M/WBE – 14% • Percentage of Contracts Awarded-to-date – 97%
Utility Corridor and Roadway RelocationResults by Contractor – October 2015
Utility Corridor and Roadway RelocationResults by Trade – October 2015
Utility Corridor and Roadway RelocationResults by Trade – Project to Date
Utility Corridor & Roadway Relocation Project Project-to-Date • Boston Residents – 30% • Minority – 24% • Female – 7% • Veterans – 4% Month of June • Boston Residents – 19% • Minority – 22% • Female – 6% • Veterans – 0% *Graph courtesy of Policy Group on Tradeswomen Issues (PGTI)
Upcoming UMBA Projects at UMass Boston • Renovation of Existing Academic Buildings • Stage: Schematic Design • Construction Commencement – Fall 2016 • Project Budget = $75 million • OPM: Hill International • Architect: Cannon Design • Energy Producing Facility • Stage: Entering Design Development • Construction Commencement – Summer 2016 • Project Budget = $32 million • OPM: Jacobs • Architect: Cambridge 7 • CM: Gilbane • Parking Garage • Stage: Study • Construction Commencement – Summer 2016 • Project Budget = $45 million • OPM: Skanska • Residence Hall • Stage: Study • Construction Commencement – Summer 2016 • Project Budget = $120 million