An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NA62 Gigatracker cooling28thOctober 2011EN/CVPiero Valente, Michele Battistin

  2. Thermodynamic requirements • Fluid: C6F14 • Total required cooling power : 300 W (safety factor=2) • Number of distribution loops = 3 • Supply temperature = -25C • Loop temperature stability = ± 0.5K • Temperature difference between loops = 2 K • Design pressure: 16 bar • Pressure drop : to be defined by GTK collaboration

  3. User requirements • VDF pump power supply for smooth start-up sequence • PVSS-UNICOSS control and supervision • Control cupboards installed in the remote protected area (200 m far) • Automatic control of loop flowrate • Automatic control of loop temperature • Remote control of delivery temperature and flow rate for each loop • Interlocks for high delivery pressure • Fully redundant operation: double chiller, heat exchanger and circulation pump • Oil free cooling station • Pneumatically actuated valves • Cooling station to be tested in Meyrin site

  4. Proposed solution • HCFC refrigerant redundant primary chiller (-40 °C) • Chiller overall cooling power: 1.5 kW (including heat losses) • C6F14 total mass flow = 0.330 kg/s (pre-design figure) • Three main pipelines (OD 12) carrying 0.100 kg/s C6F14 flow each • Three smaller pipelines (OD6) carrying a 0.011 kg/s C6F14 flow to each detector • A heat exchanger for each line, located ≈1 meter close to the detector, will guarantee operating temperature setting of -25C

  5. Proposed solution : P&I Detector pipelines OD 6 Main pipelines OD 12

  6. Planning • System design ……………………………………. November-December2011 • Procurement ……………………………………… January 2012-March 2012 • Installation ………………………………………… April-June 2012 • Tests…………………………………………………… July-September 2012 • Commissioning…………………………………… October2012 • Engineering specificationapproval …….. End October2011

  7. Budget • Electrical and control equipments ….……..30 kCHF • Manpower………………………………….….……..40 kCHF • Total180 kCHF • Material ………………………………………………..110 kCHF