Preliminary Evaluation Observations Joe Crossett, TransTech Management

Implementation of Adopted Transportation Vision for the Metropolitan Washington Region: Development of Circulation Systems and Green Space. Preliminary Evaluation Observations Joe Crossett, TransTech Management TCSP Workshop, Sept. 14, 15 2000. Project Overview.

tuyen
Download Presentation

Preliminary Evaluation Observations Joe Crossett, TransTech Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Implementation of Adopted Transportation Vision for the Metropolitan Washington Region: Development of Circulation Systems and Green Space Preliminary Evaluation Observations Joe Crossett, TransTech Management TCSP Workshop, Sept. 14, 15 2000

  2. Project Overview Sponsor: National Capital Region Transportation Planning Board/ Metropolitan Washington Council of Governments (TPB/COG) Yr. Funded: 1999 Total Cost: $380,000 grant + $100,000 in-kind match (Includes $80,000 for evaluation)

  3. Goals & Objectives Goal: Build stakeholder support for two frequently overlooked elements of region’s Transportation Vision Statement: • Design circulation systems within regional core & regional activity centers that maximize use of transit, ped., & bike facilities • Integrate greenways into a connected regional greenways system Objective: Produce two reports that establish regional frameworks for greenways and circulation systems respectively

  4. Critical Challenges TCSP funding designed to get more from the region’s MPO planning process: • Promoting Visibility: Greenway & circulation systems are low priorities in area’s project selection process • Building Consensus: Regional planning across 7 counties, 2 states, and the District of Columbia is complex • Securing Implementation: TPB’s project implementation role is indirect – state & local agencies allocate funds

  5. Two-track process with separate committees Committees led by 2 key elected officials on TPB Board Each committee included 20+ key stakeholder group representatives Planning consultant & TPB staff provided technical support Priority Projects Stakeholder Advisory Committees Consultants TPB Staff Innovative Development Process - Stakeholder-Led Committees

  6. Greenways Committee: Washington Parks & People Anacostia Watershed Society Trust for Public Lands Washington Area Bicyclist Assoc. American Farmland Trust Potomac Heritage Trust National Park Service MD Greenways Commission City of Takoma Park Sierra Club DC Office of Planning No VA Planning District Commission Circulation Sys. Committee: Montgomery Co. Dept. of Public Wks Assoc. of Ped. & Bicycle Professionals MD Transit Administration Surface Transp. Policy Project TYTRAN Washington Area Bicyclist Assoc. Action Committee for Transit Transit Action Partnership Dulles Area Transportation Assoc. Private Providers Task Force Stakeholder Participants

  7. Five Key Steps • Inventory region’s existing greenways & circulation systems • Inventory 150 proposed greenway projects/50 circulation system projects, based on consultation with state/local planners • Select 8-10 regional priority projects for each report • Develop persuasive profiles of priority greenway and circulation systems projects • Take to TPB Board for final endorsement

  8. Timeline 1999 2000 2001 Sept: Committees Established Mar: Grant Submitted Oct: TPB Approval May: Grant Awarded Oct-April: 4 Greenway Committee Mtgs Held Feb-June: 4 Circ. Syst. Committee Mtgs Held IMPLEMENT

  9. Innovative Elements • Spotlight on non-traditional projects: Improves visibility of TCSP-type projects that are typically a low priority • Stakeholder-led committees: Decision-making process strengthens buy-in for non-traditional projects, achieves consensus. • Project-level recommendations: Priorities described in reports are actual projects with local support, hence stronger implementation feasibility

  10. Evaluation Methodology Independent evaluation consultant: • Observe meetings, interview participants, review documents • Describe project innovations/lessons learned • Measure process & products • Evaluation timeframe too short to measure outcomes

  11. Sample Evaluation Measures –Process Element • Did process help build constituency for projects among stakeholders? • Range of stakeholders is adequate? • Effective use of stakeholders? • Was a systematic approach for process used? • Thorough project inventory? • Effective project selection criteria? • Adequate information for decision-making?

  12. Sample Evaluation Measures -Product Element • Does report create cohesive regional vision? • Support of local agencies for projects selected? • Inter-jurisdictional coordination? • Regional connectivity? • Does report provide sufficient implementation guidance? • Funding opportunities? • Barriers to implementation? • Political feasibility?

  13. Conclusions • A “work in progress” – but signs of success are promising… • What if no funding had occurred? Evidence is clear – these types of projects are not in the 2000 CLRP/TIP, despite Transportation Vision. • Big question, will they be there next year or year after? • Keep stakeholders involved/accountable • Apply process to other types of project development

  14. Outside praise for greenways report: • “your report is a wise investment of federal funds (that) provides an overarching framework & blueprint for local jurisdictions… It should become a model for the nation.” • (Tom Downs, former CEO, Amtrak)