An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DS3The Network and its Output DataPaul Alexander SKADS Review 2006

  2. Overview • Overall aim of this design study • Examine the System Design issues associated with producing the most cost-effective overall architectural design for the SKA “network” SKADS Review 2006

  3. processor User network Telescope response The physical network: Data flow, processing and analysis signal and data transport & power SKADS Review 2006

  4. The Structure of DS3 • Six tasks • T1 – Network infrastructure and data transmissionManchester • T2 – Data handling; control and distributed computingASTRON • T3 – Architecture and the functional simulatorCambridge • T4 – Siting and related issuesOPAR • T5 – SKA for the userCambridge • T6 – Scaleable design and implementationASTRON SKADS Review 2006

  5. DS3 and the SKA system design • Concerned with the overall SKA architecture not just the Aperture Array • Will consider compare and evolve: • SKADS Benchmark specification • ISPO reference design • Other emerging system designs SKADS Review 2006

  6. Current Status • All tasks underway • No DS deliverables or milestones in the first 12 month period • Relatively slow start for some tasks: • Planned in the description of work • Later than anticipated availability of UK funds • At kickoff meetings identified: • the need for close inter task discussions and also with other DS SKADS Review 2006

  7. Some of the interactions DS3-T1 Network DS3-T6 Scaleup DS3-T2 Processing DS4-T2 DSP DS2-T2 Science DS3-T3 Simulator DS4-T6… 2-Pad DS5… Embrace DS3-T4 Siting SKADS Review 2006

  8. Current Status • All tasks underway • No DS deliverables or milestones in the first 12 month period • Relatively slow start for some tasks: • Planned in the description of work • Later than anticipated availability of UK funds • At kickoff meetings identified: • the need for close inter task discussions and also with other DS • cost control and cost constraints central to system design SKADS Review 2006

  9. Cost modelling in DS3 • In the original description of work there exist many work packages which are required to produce explicit cost models for particular aspects of SKADS technology • Cost control central to work in DS3, DS4, DS5 and DS6 • Aim to coordinate this work and provide a good link to the wider project Single identified point of contact to bring together the SKADS costing work Provide an interface between SKADS costing work and the ISPO development of a cost model Communicate emerging cost output from SKADS to ISPO and communicate relevant aspects of ISPO cost model to SKADS team SKADS Review 2006

  10. Highlights so far DS3-T1 (more in a moment) Network infrastructure and data transmission • A first good costing model for the physical network DS3-T2 (more in a moment) Data handling, control and distributed computing DS3-T3 (more in a moment) Overall architecture and network simulator DS3-T5 (planned start end 06) SKA for the user DS3-T6 • Need to adopt good practice for how we model and go about the design process especially as we move into the Engineering Design phase • Initial review of available methodologies SKADS Review 2006

  11. Highlights – DS3-T4 DS3-T4 Siting and related issues Original view of the task “The production of a full plan for siting and related issues for the SKA, encompassing environmental issues (including signal conditioning, impact and adopting the advanced technology to arid lands), radio frequency monitoring/protection over a long term and potential maintenance regimes.” SKADS Review 2006

  12. Highlights – DS3-T4 DS3-T4 Siting and related issues • Significant unforeseeable changes since SKADS planned in particular delay of site selection well beyond late 2006 as originally envisaged • Some work originally planned in SKADS will now be done by International Project (specifically the Site Evaluation Working Group and its Task Group on Regulatory Issues, and the ISSC ) SKADS Review 2006

  13. Highlights – DS3-T4 DS3-T4 Siting and related issues • SKADS participants played central roles in helping to define regulatory requirements for radio quiet zones at each possible site • ASTRON engineers have carried out the extensive and homogeneous Radio Frequency Interference (RFI) monitoring campaign of all four proposed SKA sites • SKADS participants contributed towards ISPO Memo 73 on “Spectrum Protection Criteria for the SKA” SKADS Review 2006

  14. DS3-T3: Overall Architecture and Network simulation SKADS Review 2006

  15. DS3-T3: Refining the Benchmark Specification Aperture Array stations on long baselines • Benchmark specification has AA providing n < 1GHz collector throughout. Can we define more precisely the requirements of an AA station? • Consider basic parameters: station size, filling factor and data rate • Constraint: ability to calibrate the station SKADS Review 2006

  16. DS3-T3: Refining the Benchmark Specification Consider the ionosphere: • typical size of isoplanatic patch at 300MHz is ~ 2 degrees • Calibration is relativelystraightforward if each stationbeam subtends an anglesmaller than the isoplanaticpatch SKADS Review 2006

  17. DS3-T3: Refining the Benchmark Specification • For a larger beam we need a more complex ionospheric model which can be solved for if reltively short baselines available as in compact core • On long baselines however, sparse station coverage • d ~ 70 m SKADS Review 2006

  18. log(N or dN/dS / sq degree) log(S / Jy) DS3-T3: Refining the Benchmark Specification • Need 1 source on average per beam/isoplanatic patch to calibrate; Poisson statistics to give P(1) for 99% of time needs N = 10 sq deg-1 • At 1.4GHz, use FIRST counts(unresolved or model) • Require DS ~ 15 mJy; for 70m AA,70% efficiency • f > 20% Integrated FIRST source count SKADS Review 2006

  19. DS3-T3: Refining the Benchmark Specification • Long baseline AA station • Diameter 70 m • Filling factor > 20% • Data rate: • assume 8-bit digitisation for 300 – 1000 MHz • Per square degree full bandwidth 24 Gbs-1 • 250 beams ( 250 sq degrees or ~ 60 uniform sensitivity) gives 6 1012 bs-1 • Compare to LNSD station giving 1 sq degree at 1.4 GHz • f = 10% and 25 13m antennae • Beam form in central processor • Data rate 6.4 1012 bs-1 SKADS Review 2006

  20. DS3: Dynamic range • Sensitivity from large collecting area is only sensible if the telescope can also achieve the necessary dynamic range given is FOV, beam shape, side lobes etc. • e.g. Tim Cornwell as investigated in detail the effects of the telescope quadrupod on the producing asymmetries in the beam and hence limiting the dynamic range: This is a big issue which needs to be carefully considered for any antenna used in a given band SKADS Review 2006

  21. DS3: The Next 18 Months SKADS Review 2006

  22. DS3: Next 18 months • People now in post for DS3-T1 and T3 in UK and very significant ramp-up of these tasks is underway confidently expect to meet SKADS milestones and deliverables on time • DS3-T2 is now ramping up as planned • DS3-T4 effectively complete; report will be written after ISSC complete site selection • First “SKA for the user” workshop planned in next 4 months (DS3-T5) • Scaleup and design issues: work on track as planned SKADS Review 2006

  23. SKADS Review 2006

  24. Overview • Overall aim of this design study • Examine the System Design issues associated with producing the most cost-effective overall architectural design for the SKA “network” • By Network we mean • The physical network: signal and data transport & power • The data network: data flow, processing and analysis • The output network: telescope response warts and all • The user network: how the telescope appears to the end-user astronomer SKADS Review 2006

  25. The next 18 months On track to meet milestones and deliverables • Phase transfer links (T1) • Frame work for the network simulation / analysis (T3) • Overview report on site selection (T4) • Report MDA constructs, interfaces and platforms (T6) SKADS Review 2006