An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPCC Rule Update Iowa AWMA SPCC Workshop March 9, 2004 *Excerpts taken from SPCC Rule Update presentation given by Mark Howard, USEPA at the API 2003 Storage Tank Conference November 5, 2003

  2. History of EPA’s Oil Program • Federal Water Pollution Control Act Amendments • Original SPCC Rule 40 CFR Part 112 • Ashland Oil Spill – SPCC Task Force • Exxon Valdez in Alaska • Oil Pollution Act • Proposed SPCC Rule – complete revision of existing rule • Proposed SPCC Rule – amendments • Final Facility Response Plan (FRP) Rule • Additional proposed SPCC amendments • Draft Final SPCC Rule – remanded to OMB • Final SPCC rule published 7/17/02, effective 8/16/02 • SPCC compliance date extension issued

  3. Major Issues Associated with July 2002 Rule • Litigation • American Petroleum Institute (API) • Petroleum Marketers Association of America (PMAA) • Marathon Oil • Policy questions and concerns • Compliance dates extended 18 months

  4. Deadlines to Amend or Prepare and Implement SPCC Plan NOTE: Facilities subject to 40 CFR Part 112 and in operation before August 16, 2002, and without an existing Plan, must immediately prepare and implement a Plan and are considered in violation until Plan implementation.

  5. Litigation Update • Three complaints have been consolidated (API, PMAA, Marathon) • All EPA SPCC policy analysis since June 2003 has focused on lawsuit items termed “Tier 1” • Settlement discussions have been ongoing for several months • Environmental groups have shown interest in the litigation • Discussions associated with the litigation are very limited • Work on non-litigation issues, termed “Tier 2” has been impacted

  6. Tier I – Litigation Issues • Secondary containment / cost-impracticability (can cost play a factor?) • Loading racks (definition of?) • Navigable waters (SWANCC) • Produced waters (want wastewater exemption extended to) • Should to shall/must – SBREFA (procedural challenge; didn’t consider small business impacts)

  7. Tier II – High Priority Non Litigation Issues • Applicability to motive power (airplanes, “John Deere Issue”) • Scope and definition of operational equipment / process vessels • Distinction between various secondary containment requirements • Applicability of rule to various forms of piping • Integrity testing for small bulk containers (tie to SBREFA Tier I issue) • Applicability of rule to mobile / portable containers (tanker truck issues) • Wastewater exemption & applicability of rule to oil water separators

  8. Status of EPA Tier II Policy Review • Extensive interaction with stakeholders • EPA technical workgroup has reviewed and provided recommendations • Senior EPA mgmt briefings held • Decisions pending on actions EPA will take to address Tier I policy issues • Other offices in EPA must be consulted on the technical workgroup’s recommendations

  9. EPA 10 Policy Papers Red: Litigation Issue

  10. Stakeholder Meetings / White Papers • Small Business Association (SBA) • API Coalition • Utility Solid Waste Activities Group (USWAG)** • Edible Oil Industries** • API • Airline Industry • Hogan & Hartson – (Law firm representing a company coalition comprised of, for example, GE & Verizon) • Agriculture ** EPA has stated that Electrical and Food/Edible Oils Industry concerns will require specific attention

  11. SBA Activities • New policy proposals • Electrical • SPCC/Stormwater overlap • PE tiered certification proposal • 1st Tier: <5,000 gallons of oil, exempt from having a written plan and/or PE certification • 2nd Tier: 5,000 to 10,000 gallons of oil, required to have a written plan but not necessarily certified by a PE; PE site visit would not be required • 3rd Tier: >10,000 gallons of oil, written plan certified by a PE

  12. API-led Coalition • Coalition’s white papers align with EPA 10 policy papers • Concerns: • Upcoming compliance deadline • Budgeting/Capital Improvements

  13. USWAG • USWAG has provided policy recommendations for electrical equipment • USWAG Proposal • Allow each piece of equipment to be designated a facility • Tier I: Designate a “qualified facility” • 20,000 gallon threshold • No SPCC Plan requirement • Tier II: All other regulated facilities

  14. Food / Edible Oil • Concerns with the applicability of the rule to unique equipment/processes • Some SPCC sections can be deleted, others might be modified

  15. Agricultural Sector • EPA has met with USDA, EPA Agricultural Center and EPA Agricultural Liaison – Jean Mari Peltier • Impact of rule on farmers • Potentially large area of non-compliance

  16. Airline Industry • Mobile fuelers • Scope of rule • Applicability to motive power (Jet SPCC Plans???)

  17. Timetable for Policy Clarification • EPA Goal: Clarify Tier I & II issues by March 2004 • Stakeholder meeting planned for first week in March • Proposed revisions to be published in the Federal Register • Guidance, policy, and regulatory change are all possible • All issues will not be resolved • Performance based rulemaking • Role of the PE

  18. Timetable Notes • EPA does not anticipate another extension… however • Litigation timing is impacting Tier II issues • EPA has stated they will provide a six-month notice for amending SPCC Plans in areas impacted by the Tier I & II issues

  19. Melody Evans Maytag - Amana Appliances

  20. Alan J. Arnold Alliant Energy

  21. SPCC Project for John Deere Ottumwa Works Liping Zhang, P.E. Deere & Company March 9, 2004

  22. Project Background • Five loading/unloading locations for oils and chemicals. • None of them has containment • Consolidates all the loading/unloading areas into one location and install one concrete containment • Chemical loading/unloading area is also considered in this project

  23. Lessons Learned • The ramp design • The land survey

  24. Art Potratz General Mills, Inc.