An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Advisory Circular150-5370-2 Operational Safety on Airports During Construction Presented to: AEA Hershey Conference By: Dr. Michael T. McNerney, P.E., Assistant Manager, AAS-100 Date: March 2, 2011 Prepared By: Khalil E. Kodsi, P.E. PMP <Audience> <Presenter’s Name, Title> <Date>

  2. Purpose • Avoid Compromise to Airport’s operational safety • Minimize disruption of normal aircraft operations • Enhance Safety to Day-to-Day maintenance operations • Standardize Airport’s Construction Safety & Phasing Plan (CSPP) • Clearly Identify the CSPP Requirements

  3. Whom this AC affect - • Certificated Airports under Title 14 Code of Federal Regulations (CFR), part 139 • Construction projects for airports receiving funds under the Airport Improvement Program Not Required but Recommended: • Non-certified airports without grant agreements.

  4. Responsibility for Safety During Construction • On Airport activities including construction safety is the responsibility of the Airport Operator • Construction Contractor must comply with the Airport Operator’s plans for safety • Airport tenants / sponsor must also comply with the airport’s safety requirements.

  5. Safety Areas • Revised AC will make the RSA requirement consistent with incursion prevention. • 200 feet minimum distance from runway centerline will be removed. • No Construction may occur within RSA while runway is open for aircraft operations.

  6. Construction Safety & Phasing Plan (CSPP) Streamlined to address Safety Requirements: • Clearly list all areas to be impacted by a “construction project” • Provide a CSPP “Template” • For Consultants to follow in submitting a CSPP • For Reviewers to reference • Provide a Guideline to Airport Operators on how to prepare a CSPP. • Provide a check list for Airport Operators during their inspection of construction activities.

  7. Milestones - Accomplishments • A Work group has been formed and collaboration on AC content and Templates is on going. • AC Draft version is ready for internal FAA distribution for comments. • CSPP Template will be ready by March 31 • AC should be Finalized by June and submitted to FAA legal department. • Final publication by September 30

  8. Runway Design- (Table 3-1) Runway Design- (Table 3-2)

  9. Runway Design - Table 3-3