1.) A work breakdown structure is
a hierarchy of tasks, subtasks, and work packages
a Cost and Performance tracking schedule
a structure that is incompatible with the Critical Path Method
a simple list of the activities making up a project
2.) The vertical axis on a Gantt chart is usually which of the following?
Activities
Time
Cost
Profit
3.) Which of the following identifies a key principle of Reengineering?
Organize around tasks.
Downsize (lay-off) workers and do the same amount of work as before.
Merge information-processing work into the real work that produces the information.
Capture information both at the source and where it is interpreted.
4.) At the onset, a project originates as which of the following?
A Gantt chart
A series of milestones
Critical path method (CPM)
A statement of work (SOW
5.) Consulting firms typically use which of the following techniques to plan and monitor the engagements of the firm or specific projects?
CPM/PERT
Qualitative forecasting
Materials requirements planning (MRP)
Quantitative layout
6.) A Responsibility Chart specifically identifies which of the following?
Planning the tasks for a project
Customer satisfaction
Commitment to quality
Level of inventory
7.)Which of the following would be the result of subdividing a project?
Job orders
Work events
Job categories
Tasks
8.) Which project progress technique includes the essential features of a project plan, budgeted cost of work scheduled and budgeted cost of work performed?
Earned value management
Critical path method
Cost analysis
Gantt chart
9.) An example of a graphic project report utilized within project management is:
Project proposal
Equipment and supplies chart
Humphrey chart
Cost and performance tracking schedule