1 / 10

BMP Suggestion Module in Web-based LDC Tool

BMP Suggestion Module in Web-based LDC Tool. After LOADEST execution is finished, a new button will be shown in the bottom of Load Duration Curve table. In this case, we have exceeding pollutant loads in only “High-Flow” regime.

uzuri
Download Presentation

BMP Suggestion Module in Web-based LDC Tool

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BMP Suggestion Module in Web-based LDC Tool

  2. After LOADEST execution is finished, a new button will be shown in the bottom of Load Duration Curve table. In this case, we have exceeding pollutant loads in only “High-Flow” regime.

  3. An Approach for Using Load Duration Curves in the Development of TMDLs. US EPA. 2007 The table is an example for BMPs in the document. Based on the flow regimes, different BMPs need to be applied to reduce pollutant loads.

  4. Logic and Program (cgi) flow A BMP list for each flow regime requiring pollutant reduction needs to be built, The BMPs capable to reduce greater than the required reduction of pollutant load needs to be built, The area to be applied needs to be defined.For example, if the required reduction is 19.70 % :If the BMP efficiency is 20%, the BMP needs to be applied to 100% of the area.If the BMP efficiency is 80%, the BMP needs to be applied to approximately 25% of the area.This is the opposite way to calculate reduced pollutant loads by BMP in STEPL.

  5. STEPL has BMP lists and BMP efficiencies for each landuse Selected BMP categories from STEPL BMP Group 1: Post Development BMPs BMP Group 2: Streambank Stabilization BMP Group 3: Erosion Control Program BMP Group 4: Riparian Buffer Protection BMP Group 5: Municipal Wastewater Treatment Program

  6. Required Reduction Percentage Pollutant Load the user needs to define (N, P, BOD, or Sediment) Target Load in each flow regime Estimated Load by LOADEST in each flow regime

  7. To reduce N BMP List for each Landuse The user needs to select one of options in each landuse table.

  8. To reduce P BMP List for each Landuse The user needs to select one of options in each landuse table.

  9. The user needs to select one of options in each landuse table, for example, Scenario 1: Option 1. Contour Farming. 40.62 % against Cropland. Option 1. Diversion. 43.78 % against Feedlots. Option 1. Concrete Grid Pavement. 21.89 % against Urban. Scenario 2: Option 1. Contour Farming. 40.62 % against Cropland. Option 2. Terrace. 35.82 % against Feedlots. Option 2. Porous Pavement. 23.18 % against Urban. To reduce N, The module suggested 4 options for Cropland, 2 options for Feedlots, and 2 options for Urban. Thus, 16 scenarios are available in STEPL. The BMP suggestion was tested by STEPL. It was not exactly same, but was similar. This is because STEPL has complex calculations with DB and watershed inputs.

  10. Example This example can be found at https://engineering.purdue.edu/~ldc/2013/tmp/20120913235008646628_2309.

More Related