1 / 24

Question of the day

Question of the day. If you were the boss, what would you do for cost estimation?. Cost Estimation. Estimates based on LOC. Prediction Formulas.  >1. E=  X .  =1.  <1. cost. Size. TTYP1 – which one did Henry Ford experience?. Cost Estimation Models. LOC models Boehm's COCOMO

uzuri
Download Presentation

Question of the day

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Question of the day • If you were the boss, what would you do for cost estimation?

  2. Cost Estimation Estimates based on LOC

  3. Prediction Formulas >1 E=X =1 <1 cost Size TTYP1 – which one did Henry Ford experience?

  4. Cost Estimation Models • LOC models • Boehm's COCOMO • Putnam's Model (SLIM) • non-LOC models • Function Points • combination • COCOMO2

  5. Boehm's COCOMO • Software Engineering Economics • Prentice-Hall c1981 • type COCOMO in a search engine - many www sites

  6. COnstructive COst MOdel • Basic • macro - overview of whole project with one metric of KSLOC • Intermediate • multiplicative adjustment factors • Detailed • applying model to each phase

  7. Modes of Software Development • Organic • detached, often batch • Semidetached • e.g. transaction processing • Embedded • e.g. os kernel

  8. Programmer Effort • Application Programs • PM = 2.4 * (KDSI)1.05 • Utility Programs • PM = 3.0 * (KDSI)1.12 • Systems Programs • PM = 3.6 * (KDSI)1.20

  9. Example for effort • Size Appl Util Sys • 5K 13.0 18.2 24.8 • 10K 26.9 39.5 57.1 • 15K 41.2 62.2 92.8 • 20K 55.8 86.0 131.1 • 25K 70.5 110.4 171.3 • 30K 85.3 135.3 213.2 • 35K 100.3 160.8 256.6 • 40K 115.4 186.8 301.1 • 45K 130.6 213.2 346.9 • 50K 145.9 239.9 393.6

  10. Development Time (Months) • Application Programs • TDEV = 2.5 * (PM) 0.38 • Utility Programs • TDEV = 2.5 * (PM) 0.35 • Systems Programs • TDEV = 2.5 * (PM) 0.32

  11. Example for development time • size appl util sys • 5K 6.63 6.90 6.99 • 10K 8.74 9.06 9.12 • 15K 10.27 10.62 10.66 • 20K 11.52 11.88 11.90 • 25K 12.60 12.97 12.96 • 30K 13.55 13.93 13.91 • 35K 14.40 14.80 14.75 • 40K 15.19 15.59 15.53 • 45K 15.92 16.33 16.25 • 50K 16.61 17.02 16.92

  12. Average Staffing Levels • Calculate by dividing PM by TDEV

  13. Example for staffing levels • size appl util sys • 5K 1.96 2.63 3.55 • 10K 3.08 4.37 6.26 • 15K 4.01 5.87 8.71 • 20K 4.84 7.23 11.02 • 25K 5.60 8.51 13.21 • 30K 6.30 9.72 15.33 • 35K 6.97 10.87 17.39 • 40K 7.60 11.98 19.39 • 45K 8.20 13.05 21.35 • 50K 8.79 14.09 23.27

  14. Productivity • The productivity is defined as LOC per time unit. • The usual units are LOC/Programmer-Day • Divide final size of project by total programmer-days of effort for the whole software development

  15. TTYP2 • What is the effort, productivity, staffing and delivery time for an application project that takes 82K loc? • What is the effort, productivity, staffing and delivery time for a system project that take 200K loc?

  16. COCOMO Effort Multipliers • product attributes • required reliability 0.75 - 1.40 • data-base size 0.94 - 1.16 • product complexity 0.70 - 1.65 • computer attributes • execution time constraint 1.00 - 1.66 • main storage constraint 1.00 - 1.56 • virtual machine volatility 0.87 - 1.30 • computer turnaround time 0.87 - 1.15

  17. Putnam's Cost Estimation Model • macro-estimation model that uses LOC • relationship between cost and the amount of time available for the development effort. • The model supports the 'mythical man-month' idea

  18. Putnam's Model • Uses the Rayleigh Curve • Shows Instantaneous Programmer-power vs Time • Empirically verified on other projects

  19. Rayleigh Curve • The rayleigh curve is a product of at times e raised to the -bt squared • The at dominates at first giving a steep rise and then the negative power of e lowers the value slowly

  20. Rayleigh Curve • y : instantaneous programmer-power • K : total lifecycle cost ( in programmer-years) • t : time from beginning of project • td: delivery time • e= 2.71828...

  21. Software Equation • There must be a relationship between the lifecycle development effort, the development time and the size of the project. • This relationship is given in the Software Equation

  22. Software Equation • Ss = C*K1/3 td4/3 • where: • Ss is the estimated size of the software system • K is the total lifecycle effort in programmer-years • C is the technology constant • td is the development time (in years)

  23. Putnam by spread-sheet

  24. Summary • What could you do as a manager to improve cost estimation?

More Related