320 likes | 491 Views
Gareth Walker, BSc, PhD, MRSC. Application of Radioactivity and the Law to Contaminated Land and Demolition Projects. Contents. Introduction to legislation Introduction to contamination land assessment, and demolition & decommissioning projects Three case studies. Overview of Legislation.
E N D
Gareth Walker, BSc, PhD, MRSC Application of Radioactivity and the Law to Contaminated Land and Demolition Projects
Contents • Introduction to legislation • Introduction to contamination land assessment, and demolition & decommissioning projects • Three case studies
Overview of Legislation • Main legislation for this presentation • Nuclear Installations Act 1965 • Radioactive Substances Act 1993 • Including Exemption Orders • Ionising Radiation Regulations 1999 • Environmental Protection Act 1990, Part IIA • Site Waste Management Plan Regulations 2008 • DEFRA policy on Low Level Waste Management (2007)
Why Undertake an Assessment? • Obligation & Liability management • Obligated to comply with legislation • If they fail to comply, are they liable? • What is the extent of the liability?
Types of assessments • Will be focussing on contaminated land and demolition/decommissioning assessment • Assessed through • Contaminated land characterisation • Risk assessment • Remediation options and cost assessments • Waste management • Materials characterisation
Case Studies • Contaminated land assessment • Sellafield characterisation • Working in partnership with Serco Assurance • Radiological risk assessment at Hunterston A • Demolition and decommissioning assessment • Waste management during decommissioning and demolition at Bradwell
Considerations Prior to Contaminated Land Assessment • Aim of the assessment Contaminant Source Pathway Receptor • Leads to a potentially significant pollutant linkage • Does the pollutant linkage represent an unacceptable risk?
Drilling at Sellafield – Overview • Installation of boreholes • Vertical holes (up to 60 m) • Understanding ground profile (geology) • Collection of soil and groundwater samples • Spatial understanding from soil analysis • Contaminant transport • Source identification and understanding • Pollutant linkages (radiological and chemical) • Conceptual model building
Characterisation at Sellafield • Elements of legislation driving this project • NIA65 • RSA93 • IRR99 • Drilling boreholes into land with unknown concentrations, isotopes and forms of radioactive contamination • Fission products • Daughter isotopes • Chemical properties • Mobility by dissolved phase/colloidal transport
Summary - Sellafield • Worker safety paramount – drillers, engineers and general site staff • Must maintain nuclear and environmental safety • Source terms must be defined • Pathways and receptors must be defined • Potential liability relating to contaminated land must be understood
Radiological Risk Assessment - Overview • Hunterston A is in the process of decommissioning and moving towards de-licensing parts of the site • Driver is to put the site into a care and maintenance period • Assessment of risk to people and the environment arising from land quality issues at Hunterston A • Through this assessment, understanding the liability associated with potentially contaminated land
Radiological Risk Assessment - Overview • Used land quality data gathered between 2000 and 2008 • Review of data and comparison to current legislation • NIA65 • RSA93 • EPA90, Part IIA • Guidance (statutory) • Establish the extent of risk, if any, to people and the environment • Does the site have a liability it needs to address?
Radiological Risk Assessment – Part IIA • Contaminated Land Report (CLR) -11 framework followed to assess risk • Tiered approach • Phase 1 completed in early 1990s • Characterisation completed • Areas of Potential Concern (APCs) identified • Potentially significant pollutant linkages identified • Generic qualitative risk assessment (GQRA) • Conservative approach • Screens each APC through risk assessment process – further work required?
Radiological Risk Assessment – Part IIA • Developed a qualitative risk table • Based on the MoD Defence Estates methodology, and input from other consultancies to Defence Estates • In consultation with Magnox North • Assesses pollutant linkage based on • Magnitude of potential consequence (i.e. Severity) • Magnitude of probability (i.e. Likelihood) RISK = SEVERITY X LIKELIHOOD
Radiological Risk Assessment – Part IIA DESCRIPTORS FOR SEVERITY OF CONSEQUENCE OF CONTAMINANT SOURCE-RECEPTOR LINKAGE
Radiological Risk Assessment – Part IIA DESCRIPTORS FOR PROBABILITY OF CONSEQUENCE OCCURRING
Radiological Risk Assessment – Part IIA DESCRIPTORS OF Risk significance RISK = SEVERITY X LIKELIHOOD
Radiological Risk Assessment – Part IIA • Apply to each individual APC • This will define: • Is more work required? • What work is required? • When can you stop?
Radiological Risk Assessment - Summary • Using this risk assessment approach allowed: • An assessment that is compatible with current law and guidance • England & Wales – human health only • Scotland – also, water and ecological environments • Significance of pollutant linkages to be assessed in a consistent manner across the NDA land-holding • Potential contaminated land liability to be better understood, more readily prioritised and therefore managed
Considerations Prior to Demolition and Decommissioning Assessment • Legislation and guidance requires quantification of waste and materials for site-wide Integrated Waste Strategy (IWS) or Site Waste Management Plan (SWMP) • The correct characterisation of items and materials will form part of an IWS or SWMP • Location and extent of chemical and radioactive contamination must be identified
Waste Classification • Waste classification and fate • Intermediate Level Waste – remains at site creating the waste • Low Level Waste – shipped to the LLWR at Drigg • Very Low Level Waste – hazardous waste landfills with RSA93 licence • Exempt waste – no regulatory control; free release • All waste removed from the site must be, as far as is reasonably achievable, re-used or recycled, with minimum final disposal
Waste Management During Decommissioning - Summary • Context for determination of a site strategy for the management of decommissioning wastes and items is determined by Site Waste Management Plan regs • Previously required an IWS (EGG01) • Waste management plans should be developed “with appropriate regulatory and stakeholder involvement” and should take into account current best practice • e.g. Nuclear Industry Code of Practice • Current decommissioning policy for nuclear sites in under review • SD:SPUR / SAFESPUR / SAFEGROUNDS / CoRWM
Summary • Obligation and liability management • Legislation – grey areas; overlap; changes • On-site as opposed to off-site • Complex sites • Long histories; many stakeholders • Pollutant linkages • Characterise; Assess; Mitigate • Waste management • During characterisation • During remediation • During demolition & decommissioning
Acknowledgements • Sellafield contaminated land team • Hunterston A (Magnox North & Hugh Richards) • Bradwell (Magnox South)
Gareth Walker, BSc, PhD, MRSC Application of Radioactivity and the Law to Contaminated Land and Demolition Projects