Programme Details Meeting of the SPC 1145 Hrs. • Welcome by Prof. Khilar 1145 Hrs. • Summary of Current Work by Prof. Joshi 1150 Hrs. • Plan of Work in ’03-04 by Prof. Joshi 1155 Hrs. • Plan of Work beyond ’04 by Prof. Joshi 1205 Hrs. • Discussions by SPC Members 1215 Hrs. • Concluding Remarks by Prof. Khilar 1255 Hrs.
Summary of Tasks Completed During 2002-2003 • Syllabus for Revised SD&E Implemented. • HILS Facility Phase-I for MAV Completed. • Aero./Prop. Data Generation for MAV Started. • MDO of Flexible Wing with NASTRAN Completed. • MDO Framework Version 2.0 Partly Completed. • 3-D Duct Design with CFD Partly Completed. • MDO Using RSM/DACE etc. Initiated.
Expenditure During 2002-2003 • Infrastructure & Salary, Major Components • Unspent Balance 35.27 L. Reallocation Requested
Proposed Plan Until March ’04 Educational Programme in SDE • Support to Theory & Laboratory Courses • 2 M. Tech. Students for 2 Year Period • 1 Dual Degree Student for 14 Months HILS Phase-II Development • Sensor Hardware Identification • Refinement of Sensor Models • Realistic GPS Simulator • Interfacing Radio Control Equipment • Evolution of More Complex NGC Algorithms.
Proposed Plan Until March ’04 MAV Activities • Requirement Capture/Aero./Prop. Data for KADET • Definition of Waypoint & Closed Loop Path Planning • Interfacing of Sensor with Micro-controller • Design, Fabrication & Flight Test of 2 Feet Aircraft MDO Studies • Interfacing of WingOpt with ANSYS • Studies on Surrogate Modelling, DACE & RSM • Upgradation of “Engine” Software Module • 3D Duct Design Optimization
Proposed Plan Until March ’04 MDO Framework Version 2.0 • Functional Completion of Analysis, Optimizer, Execution & Configuration Managers • Completion of GUI for Data Dictionary, Wrapping & Problem Formulation Flying Platform Activities • Mission Related Information by Flying KADET • GPS Sensor Characterization • Sensor Fusion and Package Design • Multi-Axis Rate Measurement
Proposed Plan Until March ’04 Systems Engineering Teaching Aids • Complete Case Study of at least two Products • Application of SE Process to Electro-mechanical Flight Control Actuator of Lakshya • Application of SE Process to NGC for MAV. Workshop, Seminars, Meetings • International Conference on MSO-DMES • Special Lectures in Short Term Course by NIAS • CEP in Mechatronics; MCA, SPC, JPC Meetings
Proposed Plan Until March ‘04 Expenditure Plan for 2003-2004 • Salary Major Component • Authorization Requested to Exceed Expenditure by 10-15%
CASDE Plan Beyond March ‘04 CASDE completes 5.5 years on March 2004. • Rs. 98 Lakhs Phase-II Proposal submitted to ARDB • SDE Educational Programme • MDO Studies & MDO Framework Development • System Design & Integration Studies • Autonomous MAV Through SE Practices • Following additional tasks are of interest to CASDE • Survey of Conceptual Design Methodologies • Procurement of PC Based SE Process Tools • Education/Training of Aero. Systems Designers