1 / 7

Target Lab. Update

Updates on oven structure design, optics components, NMR signal adjustments, EPR setup, software testing, cell production progress, and future research plans discussed in the Transversity Collaboration Meeting.

vanessam
Download Presentation

Target Lab. Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Target Lab. Update Transversity Xiaohui/Joe/Yi/Chiranjib Transversity Collaboration Meeting Tuesday… 11th Dec. 2007

  2. Target Lab. OPTICS TARGET AREA

  3. Oven Structure/Design/Test • Support tube broken initially • Couple of weeks delay • Oven temp test with the temporary • support structure done • Could reach 250 deg C • .New pick up coils installed / tested • EPR coil mounted temporarily • Overall, system ready after • a long break ! /working

  4. Optics/Lasers • Almost all components for the 3 lines identified • Most of them ordered and in house now • Optics design completed • 6 single FAP and 2 duo FAP in lab. • 1 new duo FAP and 1 new single FAP ordered • Alignment done with two lasers now

  5. Tests • Pumping going on • Initially problems with NMR signal due to bad • adjustment of the pick up coils • Adjustment done and now NMR works fine • Q-coil test, RF field measurement done as part of the • new system check • EPR set up and being worked on • Cell characterization on list • Spin flip /DAQ being worked on ( more in Yi’s slides • and Xiaohui’s on Friday )

  6. Other…. • All new software together with GeN ones to be tested • Plan to have 20 cells. 16 already made • ( 17th one is being processed in W&M and 18th one was • broken…..repaired @ Princeton…..back in UVA) • Compass research @UKY almost close to being finished • Moment- of- Inertia to be measured shortly ( Gretchen) • Soon another same system to be made

  7. In another few weeks :::::::::::: • Plan to continue working on NMR/EPR with • improvements to test the new cells • more spin flip tests Thanks to Wolfgang, Jian Ping, Todd, Al, Susan Ameya, Aidan, Jaideep ……

More Related