1 / 26

ILC Program discussion M. Ross 14.09.2004 TTF2 - long term schedule Modul status

ILC Program discussion M. Ross 14.09.2004 TTF2 - long term schedule Modul status Plans for production (Hans Weise and Bernd Petersen – TESLA Coll. Technical Board meeting, 07.09.2004 – last week) SLAC involvement. Schedule until 2007.

vangie
Download Presentation

ILC Program discussion M. Ross 14.09.2004 TTF2 - long term schedule Modul status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ILC Program discussion M. Ross 14.09.2004 TTF2 - long term schedule Modul status Plans for production (Hans Weise and Bernd Petersen – TESLA Coll. Technical Board meeting, 07.09.2004 – last week) SLAC involvement

  2. Schedule until 2007 Saturation in wavelength range 30-120 nm July 2005 User operation (extended period) Operation with long bunch train Dec. 2005 User operation (extended period) 3rd Harmonic RF system and ACC6 installed Feb. 2006 1 GeV beam energy (total 48 cav ~=meters) April 2006 Saturation 6 nm June 2006 User operation (extended period) Seeding Option installed Dec. 2006 Seeding demonstration April 2007

  3. https://ttfinfo.desy.de The TTF electronic logbook

  4. Schedule looks like being FEL dominated. Is this true? For 2005 we assume 9 weeks of FEL user operation 2 months FEL studies 2 months accelerator studies (diagn. etc.) includes photon diagnostics 2 months of dedicated acc.module tests This means: 4 months to be discussed

  5. A must: - HPP of the relevant cavities M5/C6, M1/C8(?). Others ??? • long time operation of M5 at high gradients in steps from 20 • MV/m to 25+MV/m: - what are the typical problems? - any change in dark current? - how close can we go to the gradient limit? • processing behaviour after interruptions / shut down

  6. The individual modules ACC1(M2*) HPP of C7.(Z53) if not successful, attenuator in order to get 4x15MV/m and 4x20MV/m average ACC2(M1*) optimze attenuators of cavities C1, C2, and C6 so that we get 22MV/m average ACC3(M3*) HPP of C7 (S28) ACC4(M4) measure Qo / Eacc between 15 and 24MV/m long time operation at highest possible gradients incl. measurement of dynamic losses at 2K, 4K, and 40/80 K ACC5(M5) dark current measurement C6 (AC77) -> HPP -> dark current if required, attenuator C6 attenuator for C8 (AC60 limits module at 25MV/m measure Qo / Eacc between 15 and 28/30? MV/m average long time operation at 25MV/m and at max. gradient incl. measurement of dynamic losses at 2K, 4K, and 40/80K ==> at gradients >15MV/m we never measured the dyn. losses of a complete module at 4k and 40/80K ACC6(M6) 8 EP-cavities at 35MV/m 8 modified tuners with piezos 2K-magnet

  7. In General • develop robust algorithm for Lorentz force compensation and test with • piezo tuners at M6 and M1/C5. • failure recogination and exception handling, esp.close to performance • limit - measurement and optimization of amplitude and phase stability (within bunch train, from train to train, long time) - automized operation (FSM) of LLRF • test next generation of LLRF (developed for XFEL: increased ampl. and • phase stability requirements) - beam based feedback algorithms (energy, phase, bunch length)

  8. Cavities @ ACC1 EP cavity

  9. Cavities @ ACC2

  10. Cavities @ ACC3 Couplers conditioning was not completed before the module measurement : coupler 4 vac.valve was closed. Conditioning completed later. During Module 3 disassembly couplers antennae touched cavity surface.

  11. Cavities @ ACC4

  12. Cavities @ ACC5

  13. Cavity preparation general comments After several technical problems: EP is working now reliably General assumptions for schedules: no 1400 C treatment of new cavities Requirement for next modules: 35 MV/m for each cavity Assumption for the schedules: Each second cavity will reach 35 MV/m ( this is also assumed for retreated cavities) with reference to latest experience CHECHIA test for each cavity Modul 6 needs cavities out of the new ZANON production Not yet considered in the schedules: Clean room will need 3 weeks of maintenance/repair in the next months

  14. Performance of some Cavities EP re-treated at DESY(already limited performance after BCP )

  15. Next cryomodules Modul 6 : ‚high gradient module‘, all cavities 35 MV/m, type III design: Ready : May 2005 Modul 7: ‚ linac spare module‘, type II design TESLA meeting at ZEUTHEN -> all cavities EP treated, 35 MV/m Helium vessel of type III have to be produced !!! -> decision needed (type II cavities& vessels available, flanges have to be exchanged) Ready : December 2005

  16. Schedule Module 6 (Axel Matheisen)

  17. Cryomodule parts Tuners: ( at present no piezo tuners available !!!) Mechanical parts for 17 tuners on DESY site ( incl. 2 ‚mirrored‘) To be delivered this week: 16 control units + 12 motors Another 7 motors will arrive in about 3 weeks from now Magnet packages: 1 TTF-design package ready on DESY site ( + 1 Sstruct) 1 TESLA-design coil will be delivered to DESY in October 04 (TESLA-design package can be used in modul 6 without BPM) BPMs : ??? 2 old TTF-type available Main couplers ( 40 ordered): type III couplers for module 6 at Desy, 30 DESY type III couplers will be delivered to Orsay until end of this year

  18. Cryomodule parts (cont.)modules beyond 6 &7

  19. Single Module Test Stand( Yury Bozhko –MKS1-) Some details: Cryogenic equipment: After EU call for tender now in the process of making contracts RF-equipment: Modulator, puls-transformer on DESY site Klystron ordered, will be delivered in 2005 Call for tender for wave guides etc…. Civil engineering: Final specifications ready, procedures prepared and will be started now

  20. Single Module Test Stand (Yury Bozhko) First operation / commissioning: November 2005

  21. SLAC participation in TTF2 program – discussions from the Orsay Tesla collaboration meeting • Our near-term program is to commission the longitudinal phase space monitor – transverse cavity ‘LOLA IV’ and provide long term tools that facilitate its use. • We proposed SLAC participation at TTF2 for the following (basically in response to informal ‘feelers’). • HOM signals for position measurement • Cavity dark current • Optical fiber-based stable RF distribution • Beam – based alignment • Less formal discussions were held on: • Beam phase monitoring • Hardware development – power supplies • LLRF (commissioning and learning) • There is an operating laserwire in the PETRA ring – (RHUL/DESY/Oxford) • Each one deserves a thesis in itself – some are critical for LC design / construction

  22. Transverse deflection cavity studies • Goal: • Prove the device for measurement of ultra-short bunch length, energy correlations and transverse slice emittance • Precision, calibrated tool for complex physical process • Vital for FEL and LC • Develop the application software to facilitate its use • Beam dynamics tests of CSR-generated emittance growth • Resolution: • 10um σ_z (30fs) (50m β, 600MeV) • Vertical kick allows measurement of Є_x vs z, δvs z on different screens • Study of incoming correlations – ‘pitch’ angle • Martin Nagl, Holger Schlarb, Karsten Klose

  23. Higher Order Mode studies • Goal: • Prove use of HOM for cavity beam position absolute measurement • Develop system for HOM use to minimize wakes and emittance growth • Cavity / cryomodule fab / assy alignment test • Resolution • ~50μm • Offset / phase shift caused by coupler location(s) ~150 μm depending on which mode (Dohlus) • Test / compare beam – based alignment using quad shunt • Nicoleta Baboi, Rita Papparella, Olivier Napoly

  24. Dark Current Studies • Goal: • Measure on axis (up / down) cavity dark I over long term • Build, install and equip (controls and signal processing) simple single cell external cavity • Resolution • ~1 nA accuracy for each module • (30pA is thermal limit with moderate shunt impedance) • There is no precision dark I monitor in Checchia (single cavity horizontal test stand) – recent measurements use radiation monitors • Vertical test stand coupler/valve geometry precludes their use • Hans Weise and Manfred Wendt

  25. Stabilized – optical fiber RF distribution • SLAC equipment donated to TTF (was unused at SLAC) • Fiber, fiber stretcher, xmit/receive, fiber couplers • Student project to use this hardware (+ much more needed) to build a stabilized link. • ~100fs / multi-km stability (200 fs demonstrated in 2001) • FEL requirements are much tighter – but for somewhat shorter distances (20fs / 1 km – 5e-9) • Henning Weddig / Stefan Simrock / students

More Related