1. West Los Angeles College Food CourtRequest for Information November 17, 2009 “Go West. Go Far.”
2. Agenda 10:00 a.m. Attendees sign in
10:15 a.m. Welcome and Introductions
10:20 a.m. College Background and Objectives
10:30 a.m. Overview of Project
10:40 a.m. Discussion of Site Plan
11:00 a.m. Questions
3. Introduction to the Team
Mark Rocha, College President
John Oester, Vice President of Administrative Services
Anne Diga, Associate General Counsel
Roma Nandlal, Facilities Assistant
Steven Jacobson, CPM Turner
4. Scope of Proposed Project Joint Occupancy Lease to:
Provide food services within a central kitchen design layout of approximately 7,012 square feet.
Provide tenant improvements within a proposed allowance budget to customize food and dining space.
5. Scope of Project (Cont’d) Food services provided by a single food operator and/or vendor which includes a diverse and nutritious blending of food items
Welcoming creative ideas in dining area design and food services
Provide an attractive dining environment for students, faculty and staff
Provide source of catering for campus meetings and events.
Potential lease rental with revenue sharing prospect with College
Possible tenant improvement allowance offered by College
6. Not in scope for this project… Not another school cafeteria
7. College Background Information and Objectives Who are we and what do we do?
70 acre campus
Accredited public education institution providing transfer and associate degrees
Serving 10,000 regular and extension students
Day and evening programs
Community service program
Logistics and demographics of campus
Student and staff
5,750 morning students
1,375 lunch hour students
2,575 evening students
400+ faculty and staff
8. College Background Information and Objectives (cont’d) Current food service on campus
Special events on campus and future campus facilities
College objectives
Quality food service provider
Good food
Reasonable prices
Enhance the campus environment
Campus supporter
9. Site Condition Proposed Student Services Center
Maps and Drawings
Parking
Other construction
on-going
11. Food Service Site Plan
12. Overview of Process
Questions and
suggestions submitted
RFP developed and issued
Submittal Deadline
Evaluation Criteria/Evaluation Panel
Recommendation by College President
Notice of Award
Board Approval
Lease negotiated and executed
13. Proposed Project Timeline Optional RFI Meeting November 17, 2009
RFP Issued by District - January 8, 2010
RFP Pre-Proposal Conference – January 22, 2010
RFP Submittals Due to District – February 20, 2010
Evaluate Proposals - March 2010
Notification of Award - March 2010
Negotiate and Execute Lease - March 2010 – April 2010
Construction improvements Begins April 2010
Construction improvements completed – Summer 2010
Food Court Open - September 2010
14. Questions?
15. We appreciate your attendance.