2010/11 Construction Projects Update

2010/11 Construction Projects Update. Board Meeting August 17, 2010. Prepared by: Mr. Douglas Barge Mr. Art Hand Ms. Carrie Hargis. Y:Business ServicesFinancial ModelingConstruction PlanningWaterfall #9 B08-17-10. Table of Contents. DESCRIPTION. PAGE #. 1 2 3-4 5-7

vaughan
Download Presentation

2010/11 Construction Projects Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2010/11 Construction Projects Update Board Meeting August 17, 2010 Prepared by: Mr. Douglas Barge Mr. Art Hand Ms. Carrie Hargis Y:\Business Services\Financial Modeling\Construction Planning\Waterfall #9 \ B08-17-10

  2. Table of Contents DESCRIPTION PAGE # 1 2 3-4 5-7 8-9 10 A-1 • Opening Comments • Certificates of Participation (COPs) • State Construction Funds • Measure “K” Project Detail • Measure “L” Project Detail • Closing Comments • Appendix • COPs Debt Service Analysis i

  3. Opening Comments • We will start by reporting on the 2007 Certificates of Participation (COPs) debt and a plan to buy down the debt using the $7.7M the District has received from the State for the Tokay mold abatement project • Next we will show an updated construction plan with funding provided • To arrive at a funding plan staff has: • Incorporated the impact of previous Waterfall #8 (July 2010 report) • Adjusted funding between projects to cover existing obligations and recaptured resources no longer needed • Accounted for all new income from the State • Including paying back “temporary borrowing” between projects • Accounted for impact of recent Qualified School Construction Bond (QSCB) • It is important to remember these funds cannot be used to support general operations 1

  4. Certificates of Participation (COPs)Debt Re-Payment Status ii

  5. COPs Debt Re-Payment Status On-Going Annual Pmt Debt Svc Pmt Principal Paid Project Description COPS Source A. Lawrence Repairs $2,900,000 Williams $2,497,316 B. Tokay Repairs - Local 2,868,273 R.R.M. $143,669 ^ C. Tokay Repairs - State 7,731,727 St Facilities 7,590,000 * D. Unspent COPs Proceeds COPs 347,684 E. Total $13,500,000 $10,435,000 $143,669 * Received State funds of $7,771,669 to apply towards repayment of debt ^ Principal balance equals $3,065,000; Payments will increase to $292,763 during course of re-payment Note: Project increased prior to finalizing sale of COPs 2

  6. Arrival of State Construction Funds iii

  7. New State Funds - Received MGMT DESCRIPTION AMOUNT 8711 Delta Sierra Science Classroom $ 1,132,491 8712 Morada Science Classroom 1,179,172 8916 Tokay High Addition (Science) 1,725,209 8928 Lodi High Addition 594,260 8958 Lodi High Modernization 4,571,430 Total New State Funds $ 9,202,562 3

  8. Waterfall Summary by Fund 4

  9. Measure “K” Bonds Waterfall #9 iv

  10. Measure “K” Project Detail Waterfall #8 * Change Project Description Waterfall #9 I. Modernization A. Elkhorn $600,000 ($500,000) $100,000 B. Lodi High 0 3,750,000 3,750,000 C. Tokay Colony (310,000) 50,000 360,000 D. Live Oak (160,000) 100,000 260,000 0 E. Needham 119,271 119,271 F. Total Modernization $1,339,271 $2,780,000 $4,119,271 II. Renovations A. Lodi High $250,000 $4,450,000 $4,700,000 B. Lodi Middle (450,000) 300,000 750,000 C. Vinewood 550,000 (275,000) 275,000 550,000 D. Lakewood (250,000) 300,000 E. Independence North 0 250,000 250,000 F. Total Renovations $2,100,000 $3,725,000 $5,825,000 *Includes approved budget transfers following Waterfall #8. 5

  11. III. Additions A. Lockeford $3,000,000 $1,375,049 $4,375,049 IV. Other Projects 0 $315,000 A. Playground Equip. Replace. $315,000 B. Cafeteria Upgrades 600,000 600,000 0 C. McNair 700,000 $1,733,043 2,433,043 D. Bear Creek Phase I 2,834 (2,834) 0 E. Borchardt/Larson Painting 120,000 120,000 F. Morada Bus Loop 70,000 70,000 48,524 G. Unallocated 230,901 279,425 H. Total Other Projects $1,848,735 $1,968,733 $3,817,468 V. Total Projects $8,288,006 $9,848,782 $18,136,788 Measure “K” Project Detail – cont. Waterfall #8 * Project Description Waterfall #9 Change *Includes approved budget transfers following Waterfall #8. 6

  12. Measure “K” Project Highlights • Lodi High Renovation – Project will address deficiencies in theclassrooms of the school’s permanent wings, including flooring, painting and window replacement • Cafeteria Upgrades – In cooperation with Food Services, this project will improve the efficiency and aesthetics of the serving areas at Lodi High, Lodi Middle and Morada Middle Schools • Borchardt/Larson Painting – Portions of the original paint applications at each of these schools have failed over time. This expanded warranty repair project will repaint each school in total. • Independent Study High (North) Renovation – This site requires upgrades in many areas, including sliding replacement, new flooring, handicap accessibility modifications and window replacement. 7

  13. Measure “L” Bonds Waterfall #2 v

  14. Measure “L” Project Detail Project Description Waterfall #1 Waterfall #2 Change A. Future K-6 D $2,000,000 $2,000,000 0 B. Academy High 2,000,000 2,000,000 0 C. Safety Projects 1,700,000 1,700,000 0 D. Playground 300,000 300,000 0 $2,311,663 E. Unallocated 11,568,173 13,879,836 F. Total $17,568,173 $2,311,663 $19,879,836 8

  15. Measure “L” Project Highlights • Academy High School - This “green technology” themed small high school will provide state-of-the-art learning opportunities in a school-of-choice environment • Atlas Tract Elementary – Anticipated to be the first new K-8 elementary school constructed in the LUSD • Measure L Safety Projects – With the last phase of Measure L safety money expenditures, several North Stockton school sites will receive critically needed fire alarm and intercom replacements 9

  16. Closing Comments vii

  17. Closing Comments • With funding having arrived from the State we can continue with our original plan of paying down the COPs debt • Reorganizing existing resources and declaring the new State resources gives the District the ability to move forward with its capital improvement program • The projects shown here represent a shift in the District's construction philosophy from new school needs to modernization/ rehabilitation of existing facilities • Future state reimbursements for projects such as the Lockeford Addition will become available to support other construction needs • Regular updates on the progress of this latest phase of District construction will be provided to the Board and the Superintendent 10

  18. The End

  19. Appendix • Debt Service Analysis A-1 • Project Funding Details B-1

  20. Debt Service Analysis A-1

  21. Project Funding Details – All Funds B-1