1 / 13

Rule & Options Analysis - Background

Review Group 264 Rules & Options Analysis for BSSOQ Methodology Changes Post MOD244 16 th September 2009. Rule & Options Analysis - Background. xoserve tasked with investigating : Scenarios specifically concerning reducing booked capacity and enabling DM SOQ to be reflective of this reduction

velvet
Download Presentation

Rule & Options Analysis - Background

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Review Group 264Rules & Options Analysis for BSSOQ Methodology Changes Post MOD24416th September 2009

  2. Rule & Options Analysis - Background • xoserve tasked with investigating: • Scenarios specifically concerning reducing booked capacity and enabling DM SOQ to be reflective of this reduction • As the DM SOQ is limited by not being less than the BSSOQ: • Investigate current rules and possible options for changing the derivation and timescales applied to the BSSOQ regime • Enable the DM BSSOQ and subsequent DM SOQ to be more reflective of current capacity requirements • Possibility to reduce DM SOQ more easily / frequently

  3. Rule & Options Analysis - Context • BSSOQ rules and processes are defined in UNC and UK Link • Changes to BSSOQ regime may require changes to UNC and systems • Timescales and changes therefore are considered to be longer term rather than short term (post winter 2010) • As a result, transitional relief options (options with ability to implement in short term) are available but limited • Defining Rules & Options analysis is still ongoing • Details presented give an indication of options being investigated and indicative details • Next stages re: progress to be determined

  4. Rule & Options Analysis - Current BSSOQ Process • BSSOQ reviewed during June each year • Represents peak day consumption for the previous winter (Oct – May) • New BSSOQ value applied 1st October • DM SOQ can be reduced during capacity reduction period (CRP: Oct – Jan) • DM SOQ cannot be confirmed lower than the BSSOQ • During the BSSOQ Review, INT sites can have an increased BSSOQ • Revision of the BSSOQ can take up to 2 years, therefore limiting the ability to reduce the DM SOQ

  5. Rule & Options Analysis – Considerations Analysis has considered the following: • Changes to BSSOQ regime should not introduce greater volatility in BSSOQ or DMSOQ where demand is stable • i.e. BSSOQ should reflect consumptions that contain all winter months to identify the peak • Reasonable constraints and incentives against unreasonable capacity profiling should be maintained • i.e. restrict ability to increase and decrease DM SOQ at any time • Provide a reflective SOQ and SHQ to DN’s that is fit for purpose (supply security / system planning) • Where BSSOQ timings have been changed CRP timings would also need to be changed to allow benefit to be realised

  6. Rule & Options Analysis – Option A • Change timing of annual BSSOQ Review and CRP • Shorten BSSOQ period to run from Oct 1st to Mar 31st • CRP changed to Apr 1st to Nov 1st (extended from 4 to 8 months) • Shortens ‘Winter’ period (removes April and May: estimate 35 sites impacted) • Allows quicker review and change of BSSOQ post winter period • Aligns charge rate impact of BSSOQ with other charge rate changes • Discontinue manual review of BSSOQ calculation (minimal impact) and update revised BSSOQ effective from April 1st • BSSOQ unchanged until next April (subject to appeals / ratchets) • Permit BSSOQ appeals based on more accurate historic data

  7. Rule & Options Analysis – Option A Cont. • Where demand is changing: • The Shipper could reduce their DMSOQ in April to new BSSOQ giving earlier reduction in charges / revenue by 6 months • FIRM – profiling as now, the Shipper could reduce DMSOQ in April and increase in October to accommodate ratchet incentives applying • INT – as no ratchet applies, behaviour will be similar to now (maintain April DMSOQ throughout) • Option would shift when Shippers will reduce their DMSOQ (from Oct to Apr) but should not alter the limited ability to profile DMSOQ • Costs / Timescales: £57k to £80k • Feasible for April 2011

  8. Rule & Options Analysis – Option B • Two BSSOQ Updates per year using shorter BSSOQ period • 1: Oct – Update BSSOQ based on UWP from Jan to May • 2: Apr – Update BSSOQ based on UWP from Oct to Feb • CRP would start in April, end in mid-winter • Where demand is changing: • Shipper could reduce DMSOQ in Apr and Oct to new BSSOQ giving earlier reduction in charges / revenue by 6 months and every 6 months • BUT – could introduce additional within year fluctuations in BSSOQ as both reviews do not consider full winter period (misses some winter months) • Costs / Timescales: £70k to £100k • Not considered to be feasible due to missing winter period

  9. Rule & Options Analysis – Option C • Two BSSOQ Updates per year using a full set of winter consumption periods • 1. Oct – BSSOQ based on UWP from Oct previous year to May current year • 2. Apr – BSSOQ based on UWP from Mar previous year to Feb current year • CRP would start in April, end in mid-winter • UWP based on periods that contain all winter months • Where demand is changing: • Shipper could reduce DMSOQ in Apr and Oct to new BSSOQ giving earlier reduction in charges / revenue by 6 months and every 6 months • Could introduce additional within year fluctuations in BSSOQ but only where actual peak demand is changing • Costs / Timescales: £70k to £100k (as per Option B) • Feasible for April 2011

  10. Rule & Options Analysis – Option D • Rolling BSSOQ Review • Each month update BSSOQ based on peak consumption from the most recent period that contains all winter months (in last 12 months) • CRP would continue all year (to enable benefit of BSSOQ change) • Where demand is changing: • The BSSOQ would be reflective of most recent peak demand • Could introduce fluctuations in BSSOQ and DM SOQ throughout the year • Profiling could occur but would have to be undertaken within the month. • Costs / Timescales; As Option C (£70k to £100k), anticipated to be more expensive due to additional system changes & risks due to update frequency • Possible long term Option

  11. Rule & Options Analysis – Radical Options • Radical Options - with more significant issues requiring investigation: • 1. Re-define BSSOQ as average winter day consumption of previous gas year • 2. Re-define the BSSOQ as AQ / 365 • Option 1 & 2 allow greater reduction / flexibility in SOQ due to a lower BSSOQ • 3. Discontinue or redefine the BSSOQ before MOD90 is implemented • Is BSSOQ value required? • Appropriate mechanisms need to be in place to maintain integrity of DMSOQ

  12. Possible Analysis – Transitional Relief – Option • Transitional / short term relief options are limited and would require investigation of feasibility, costs and appropriateness • Preferred option has been stated here • Require minimal system change & utilise current processes • Retrospective Rebate – where demand has been significantly below the prevailing BSSOQ for at least 12 consecutive months, issue a rebate • Based on difference between BSSOQ and peak daily consumption from 12 month period • And where Shipper has also retrospectively reduced their DMSOQ to the BSSOQ in last 12 months • Validate changes to monitor inappropriate behaviour

  13. Rule & Options Analysis – Next Steps • Additional areas to be considered? • Limited transitional / short term relief options available – progress? • Issue with feasibility and appropriateness of long term options – progress?

More Related