1 / 14

Totem Gas Systems ( T1 , T2 )

Totem Gas Systems ( T1 , T2 ). F. Hahn and S. Haider PH / DT1. Outline. Work package General layout and functionality Mixer unit Gas Distribution unit Schedule Cost estimate Conclusions. Gas system work package. 2 gas systems: CSC (T1) and GEM (T2)

verdi
Download Presentation

Totem Gas Systems ( T1 , T2 )

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Totem Gas Systems( T1 , T2 ) F. Hahn and S. Haider PH / DT1

  2. Outline • Work package • General layout and functionality • Mixer unit • Gas Distribution unit • Schedule • Cost estimate • Conclusions S.Haider, F.Hahn PH/DT1

  3. Gas system work package • 2 gas systems: CSC (T1) and GEM (T2) • 2 mixer units (not for 07 startup) • 4 UX distribution units • Each endcap 1 rack with 2 distribution units for T1 and T2 • Pipe work done by TOTEM and/or Criotec • 2 control racks: • 1 in SG and 1 in US for T1 and T2 • In SG, each system will have it’s own PLC control • User interface in PVSS S.Haider, F.Hahn PH/DT1

  4. Can we run from the CMS CSC mixer? General parameters S.Haider, F.Hahn PH/DT1

  5. Schematic overview of the gas systems Gas Rack situated on HF platform S.Haider, F.Hahn PH/DT1

  6. Gas mixing unit (not for ‘07 startup) S.Haider, F.Hahn PH/DT1

  7. Comments Mixer Module • Both Mixer staged until second year of LHC running. • In the first year: • T1: Gas could be taken from CMS mixer ? (I have contacted OleG P. no reaction for the moment…) • Otherwise one could use pre-mixed bottles like for T2. S.Haider, F.Hahn PH/DT1

  8. UX distribution unit for T1 and T2 Altogether there will be two racks of this type, one for each endcap. S.Haider, F.Hahn PH/DT1

  9. ~3 m T2 telescope 5 planes with 2 x 3 chambers Gas System: 3 chambers (on the same plane) are connected to one common gas supply S.Haider, F.Hahn PH/DT1

  10. Pipe connections for T1 and T2 UX distribution rack (one endcap): CO2 line for backup T2 To / from T2 T1 To / from T1 US UX US-UX supply / return Note: Return lines 4x Ø =12 mm And Analysis lines 4xØ = 6mm Are unused for the moment. Gas exhaust into the cavern! Analysis lines S.Haider, F.Hahn PH/DT1

  11. Gas pipes from Racks to Chambers: T1 : supply 10 * Ø = 4/6 mm Return 10 * Ø =10/12 mm T2 : supply 10 * Ø = 4/6 mm Return 10 * Ø =10/12 mm Supply lines from USC: through central cable chain underneath CMS Top view: CMS Interaction Point T2 T1 T2 T1 Note: Due to infrastructure all pipe runs have flexible parts requiring cable chains, etc. flexibles UX distribution Rack for T1 and T2 S.Haider, F.Hahn PH/DT1

  12. Schedule • Production: • All material for 2 distribution racks are at CERN • Assembly will start beginning of February,- finish probably March, delivery > April possible • Installation • Cables are procured now (by CMS / Totem) and installed for +Side from May onward • Gas rack installation will start around June • In July, Criotec will install the gas pipes to the UX racks • Commissioning • Probably toward the end of 06 (t.b.c.) S.Haider, F.Hahn PH/DT1

  13. Mixer will increase by ~2’000 SFr Preliminary cost estimate S.Haider, F.Hahn PH/DT1

  14. Conclusions • The Totem UX distribution racks are well established in our production line. Mixers will come later. • Construction of UX racks has started, they will be ready in two months. S.Haider, F.Hahn PH/DT1

More Related