IBL CO2 coolingcontrol system development status10.04.2013 Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC
Presentation overview Control cabinets – progress Localbox – progress Chilllercontrolsystem Vacuumsystem
Control cabinets – status Control/electrical rack layout design completed Electrical schematics nearly completed by Florian 95% of control hardware components ordered and delivered Assembly by EN/CV in progress
Localbox for maintenanceoperation Mechanicalassemblywelladvanced (PH/DT) Allcomponents are ordered Front panel to be graved with P&ID by NIKHEF Electricalassemblyalreadystarted
Chilllercontrol system We decided to bulidup the chillercontrol system by ourself Base on expirence from MARCO coolingsystem
Chilllercontrol system WorksplitedbetweenPH/DT and EN/CV Electrical schematicby PH/DT Components integration in the cabinet byPH/DT Construction and cabling of the cabinet byEN/CV Purchaseof components: Frequency inverterandexpansion valves controllers by PH/DT Electrical components by PH/DT and EN/CV Electrical cupboards byEN/CV
Vacuum system Contact with TE-CRG-CE (Controls and ElectricalSupport)
ThankYou Controlsystem development status IBL CO2 cooling10thApril2013