1 / 12

Ohio Regulatory Framework For Distributive Generation

Ohio Regulatory Framework For Distributive Generation. M. Howard Petricoff Vorys, Sater, Seymour & Pease LLP. Types of Distributive Generation. Emergency Back Up Generation Not Run In Parallel Required by other state and federal regulations PURPA Co-Generation 1978 Energy Policy Act

vince
Download Presentation

Ohio Regulatory Framework For Distributive Generation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ohio Regulatory FrameworkForDistributive Generation M. Howard Petricoff Vorys, Sater, Seymour & Pease LLP

  2. Types of Distributive Generation • Emergency Back Up Generation • Not Run In Parallel • Required by other state and federal regulations • PURPA Co-Generation • 1978 Energy Policy Act • Amended by 2005 Energy Policy Act • IPP \ User Owned Generation

  3. Restructuring – Chapter 4928 ORC • Franchised Monopoly on the generation and sale of power under state law is ended • Permitted to run in parallel for self use • Permitted to sell power to others – under CRES Rules

  4. ORC § 4928.11

  5. Key Points ORC § 4928.11 • (A) • “The rules regarding interconnection shall seek to prevent barriers to new technology and shall not make compliance unduly burdensome or expensive.” • (B) • EDU must report annually to the Commission

  6. OAC 4901:1-22-01 Rules on Interconnection • Non discriminatory • Uniform • EDU must file tariffs that provide for interconnection

  7. OAC 4901:1-22-04 • EDU to set up a Queue – first come first serve • Minor modification – won’t lose your spot • Time Schedule • No Construction four weeks • If upgrades are needed – 2 weeks • If EDU cannot makes these dates – written notification • Pre-interconnection system impact study may be required by the EDU • DG and request back up

  8. OAC 4901:1-22-03 • (A) Physical connection requirements set by the current IEEE standards • (B) OAC 4928.17 apply, including offering discounts for dropping interconnection.

  9. OAC 4901:1-10-28 Net Metering • Open to fuel cells, small micro turbines, solar, wind, biomass or hydro • No cost to generator – other than site & Prep • EDU tariffs • Rules for measuring • 1% limit on the EDU – Some EDU out now

  10. Hurdles • Rate Design • POLAR Charges • 1% Rule • Possible – Pre Installation Study • Possible – Upgrade costs

More Related