180 likes | 334 Views
Zion Status Update for Zion Community Advisory Panel. November 25, 2013 Patrick Daly . Safety. 4 recordable injuries for the year (last one in July) More that 2 million hours worked to date. Agenda. Project Status update Trust fund update Change in Management. 2013 Major Work Activity.
E N D
Zion Status Update forZion Community Advisory Panel November 25, 2013 Patrick Daly
Safety • 4 recordable injuries for the year (last one in July) • More that 2 million hours worked to date.
Agenda • Project Status update • Trust fund update • Change in Management
2013 Major Work Activity • Complete Construction of the ISFSI • Accept fuel transfer equipment • Commence fuel transfer operations • Complete U-2 reactor internals segmentation • U-1 reactor internals segmentation • Continue equipment removal from Aux building • Continue radiological release of balance of plant • LTP development & site characterization • Shipment of B&C waste to WCS • Rail shipments of LLW to Clive
2014 Major Activities • Package GTCC waste from both units • U-2 reactor vessel segmentation • Complete U-1 Rx Vsl internals segmentation, start Rx Vsl segmentation • Fuel Transfer operations • Finalize preparation of LTP • Waste shipments to WCS and EnergySolutions • Aux building equipment removal • Remaining components from U-2 containment
Reactor Vessel Internals Segmentation • U-2 completing work on lower internals, will follow with GTCC waste • Work complete with the BMT • Preparing for Rx Vsl segmentation early 2014, mock ups complete Cutting on Lower internals Unit 1
Reactor Vessel Cutting Head Cutting head
RV segmentation ventilation unit Ventilation and control room
Waste Operations 2013 Class A waste disposal B&C disposal, on hold pending cask availability
ISFSI Construction Complete and manned
Fuel Transfer Preparations • All preparations completed to support fuel movement • Waiting for final NRC inspection/approval • Received 39 of 61 transportable storage canisters (TSC) • Training & NRC required dry runs completed • Canister processing • Stack-up and transport • Mock fuel loading • Canister welding