350 likes | 456 Views
Production of Gasoline Components from Synthesis Gas. ChE 397 Senior Design Group Alpha Ayesha Rizvi Bernard Hsu Jeff Tyska Mohammad Shehadeh Yacoub Awwad 2011.03.08. Presentation Overview. Recap PFD/ flowsheet Heat Duties Sizing Economics Summary. Recap. H 2.
E N D
Production of Gasoline Components from Synthesis Gas ChE 397 Senior Design Group Alpha Ayesha Rizvi Bernard Hsu Jeff Tyska Mohammad Shehadeh YacoubAwwad 2011.03.08
Presentation Overview • Recap • PFD/flowsheet • Heat Duties • Sizing • Economics • Summary
Recap H2
Questions from last presentation • Will the Carbon steel be weakening at our high temperatures? • Should be fine, below max recommended T • Should we separate our Aromatics? • Numbers last time were unduly high, normal now • Don’t quote retail prices • Gasoline price quotes are spot prices from the EIA
Process Changes • Fluidized bed Methanol to Gasoline reactor • Continuous regeneration • No DME reactor • Different product separation scheme • Different product distribution (closer to normal gasoline)
Design Basis • 6000 Short tons syngas/day • 518 °F (270 °C) • 725 psi (5 Mpa) • Product • Gasoline – 16,300 bpd • LPG – 4350 bpd
Methanol Reactor Hot MeOH Product (3) Syngas (1) Warm Water(4) MeOH-Water HX Recycle Syngas from Comp (2B) MeOH REACTOR Recycle Syngas To Comp (2A) Cooled MeOH Product (6) Steam (5)
MeOH Recycle and HX Cool Rec. Syngas(8) Cooled MeOH Product (6) Recycle Syngas To Comp (2A) MeOH-Syngas HX Purge Syngas (10) Hot Rec. Syngas (9) Cooler MeOH product(7)
To MTG Reactor Cool Rec. Syngas (8) Cold Light Gas (11) Cooler MeOH Product (7) Light Gas—MeOH HX Hot HCs(15) Product-MeOH HX Cold MeOH (13B) Flash Light Gas Out (12) Cooler Cooled MeOH(13A) Cool HCs (17 A) Warm MeOH (16) (14) MeOH to MTG
Hot HCS(15) MTG Reactors Warm MeOH (16) MTG Reactors Heater Hot MeOH (17 B )
Product Refining Cool HCs (17A) CWS (18) Cold Light Gas (11) 2nd Gas HX Warm Water (4) Deethanizer Pump HCs(22) Cooled HCs (19) Pump HCs(23) C3+ HCS (24) Cooler Decanter Cold HCs (20) ‘Dirty’ Water (21)
Offgas (26) Water ‘Clean’ Water (25 A) ‘Dirty’ Water (21) CWS (18) Water Flash Extra Cooling H2O (25 B)
Product Refining II LPG (30) LPG + Pentanes (28) Debutanizer Pentanes (31) C3+ HCs(24) Hydrocarbon Separator Gasoline Product (32) Gasoline (29)
Heat Duties • Heaters/coolers, HX, reactors, dist. col. • The rest are adiabatic • Light gas burning not included
Sizing • Reactor sizing done by hand • Used LHSV/GHSV data • Other sizing done in ASPEN • Distillation Columns • 25-40 trays • 6.5 – 8.5 ft Diameter • 64 – 92 ft High • Heat Exchangers • 1,000 – 10,000 ft2
Methanol Reactor Sizing Calculations • Boiling water reactor • Catalyst on tube side • 400 psia steam • Tube area fraction = .45 • GHSV = 8,000 hr-1 • 1:4 D:H ratio • D = 8.3 ft, H = 33.2 feet
Process Economics • Detailed summary in IPE • TIC (ISBL) = $22,050,000 • Indirect field costs = $1,900,000 • Non field costs =$3,400,000 • Total startup cost = $27,350,000 • Upkeep = $16,700,000/year • Includes catalyst prices and utilities
Field Cost Distribution D O L L A R S
Non-Field Cost Distribution D O L L A R S
Indirect Field Cost Distribution D O L L A R S
Utilities • Cooling water • 70,000 gpm • 4 Million Dollars/year • 100 psia Pressure Steam • 30.4 Klb/hr • 2 Million Dollars/year • 400 psia Pressure steam • 157.5 Klb/hr • 14.8 Million Dollars/year • Steam generation • Steam costs not included in upkeep
Catalyst Pricing • http://www.nrel.gov/docs/fy11osti/47594.pdf
Syngas and Product Cost • Syngas cost = $250/ton • Total syngas cost / year = $500 Million • Gasoline price = $2.25/gallon ($94.5/bbl) • EIA spot price • LPG price = $1/gallon ($42/bbl)
Outside Battery Limit Process Economics • Total Installed Cost (TIC) didn’t include buildings, etc. • Factor of 8 • New TIC = $218 Million • About 45% of syngas cost/year • Gasoline and syngas prices
Final Economics • Total revenue per year = $575 Million • Profit = $56 Million/year • IRR = 26% (20 year plant life) • Simple payback = 3.8 years
Summary • 16,300 bbl/day gasoline • 4,350 bbl/day LPG • Lots of potential for heat recovery • 26% IRR • Gasoline and syngas price
Steam Gen. from MeOH reactor • -475 MMBTU • 10% lost • 440 KLb per hour • Enough to satisfy our requirements • Working with gasifier group • Use in process • Electricity generation
Methanol to Gasoline Reactors Sizing Calculations Size of Reactors
Block Flow Diagram CO Cooling and Separation Methanol to Gasoline (MTG) Reactors MeOH Methanol Reactor MeOH H2, CO H2 Purge H2, CO Hydrocarbons Water C1/C2 Liquefied Petroleum Gas Water Separation 2nd Distillation Column Heavy Hydrocarbons Deethanizer (Dist. Col.) Hydrocarbons Water Gasoline
Carbon Steel Limits • Max temp based on creep = 450 C • Max temp based on rupture = 540 C • Our max temp = 380 C Heat Resistant Materials by Joseph R. Davis