Delivering East West Rail Patrick O’Sullivan

Stay updated on the latest developments of the East West Rail project phases, funding details, stakeholder engagements, and future plans for seamless rail connectivity. Follow the progress from Milton Keynes to Oxford and Bletchley to Bedford.

vlewis
Download Presentation

Delivering East West Rail Patrick O’Sullivan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Delivering East West Rail Patrick O’Sullivan

  2. Proposed New Passenger ServicesWestern Section

  3. Project Components Key East West Rail Link – Phase 1 (WCML) (MML) East West Rail Link – Phase 2 Milton Keynes Electric Spine – Oxford to Bletchley Electric Spine – Bletchley to Bedford Water Eaton Oxford Winslow Islip Bicester Town Bletchley Bedford Parkway Aylesbury Vale Parkway To London To London Paddington Marylebone (Great Western) To Aylesbury

  4. Phase 1 Oxford to Bicester

  5. Funding agreed by Office of Rail Regulation Foundations for Bicester chord line installed and earthworks commenced 25Km of newt fencing installed and hibernaculae constructed Badger setts stopped up and new setts constructed Bat surveys required by English Nature completed to their satisfaction Water Eaton grain silo demolished and site clearance at Banbury Road commenced Various earthworks and structures designs in progress Carillion Buckingham JV announced as preferred bidder on 5 December £87.4m main works contract with CBJV for signing Secretary of State for transport to visit line on 13 February Railway will close on Friday 14 February until start of new services in August 2015 On target for programme completion date East West Rail Phase 1

  6. Phase 2 Bicester & Princes Risborough to Bedford

  7. Current Issues Developing Output Specification DfT aspirations for enhanced specification Industry consultation through Industry Plan Group Legal Powers Integrating Electric Spine Interface with High Speed 2 Maintaining momentum

  8. Core Specification

  9. Enhanced Specification

  10. Developing Output Specification Industry Plan Group Established November 2013 Objective to establish support from TOCs and other Stakeholders for conditional outputs Specification to be agreed at third IPG in March 2014 Options to be developed and costed by December 2014 ECAM process to confirm funding and programme options

  11. Developing Output Specification Legal Powers Will be critical path item – Phase 1 powers took 2½ years Strategy for obtaining powers being developed EWR works in Claydon / Little Kimble areas included in HS2 Hybrid Bill

  12. Developing Output Specification Existing To Milton Keynes East West Rail core scheme To Bedford Potential East West Rail Electrification throughout Oxford to Bletchley. Potential additional W12 gauging / load capability works not included in core scheme. Bletchley Swanborne Winslow Potential connection to Down Fast To Bicester To London Euston

  13. Integrating Electric Spine Oxford – Bletchley confirmed as priority route Bletchley – Bedford likely to be delivered later: Signalling capacity Level crossings Stations Single line sections Bedford station Relationship with Midland Main Line EWR first part of Central Traction Power Supply Strategy

  14. Interface with High Speed 2 To Banbury To Birmingham Bicester North Site of proposed HS2 Maintenance Depot Bicester Town Claydon LNE Junction To Bletchley To Oxford Calvert waste disposal site Existing Electrification throughout Oxford to Bletchley (Excluding Claydon to Aylesbury. Potential additional W12 gauging / load capability / signalling / line speed works not included in core scheme. East West Rail core scheme Potential East West Rail Proposed HS2 alignment To London Marylebone To Aylesbury and London Euston

  15. Interface with High Speed 2 Aylesbury Town Aylesbury Vale Parkway To London Marylebone To Bletchley To Birmingham To London Euston Little Kimble Existing East West Rail core scheme Potential East West Rail To Princes Risborough Proposed HS2 alignment

  16. Interface with High Speed 2 To London Marylebone Sidings Princes Risborough Little Kimble Monks Risborough To Aylesbury Existing Potential East West Rail To Banbury

  17. EWR Powers included in hybrid bill Mutual Programme Risk: HS2 Powers assent in Summer 2015 EWR to be available for HS2 construction traffic via Claydon after 2018 EWR to be built on final alignment with bridges in place HS2 project team included in Industry Plan Group Interface with High Speed 2

  18. Non-abortive work progressed pending final determination: Verification of 2009 Atkins report Develop Output Specifications & ECAM process Boundary definition & encroachment identification Develop level crossing strategy Structural surveys (including Bletchley flyover) Bletchley – Milton Keynes capacity study Environmental Impact Assessment Formulated consents strategy & draft consents applications Communications & consultation Develop signalling control & power supply strategies Maintaining Momentum