Delivering East West Rail Patrick O’Sullivan
Project Components Key East West Rail Link – Phase 1 (WCML) (MML) East West Rail Link – Phase 2 Milton Keynes Electric Spine – Oxford to Bletchley Electric Spine – Bletchley to Bedford Water Eaton Oxford Winslow Islip Bicester Town Bletchley Bedford Parkway Aylesbury Vale Parkway To London To London Paddington Marylebone (Great Western) To Aylesbury
Funding agreed by Office of Rail Regulation Foundations for Bicester chord line installed and earthworks commenced 25Km of newt fencing installed and hibernaculae constructed Badger setts stopped up and new setts constructed Bat surveys required by English Nature completed to their satisfaction Water Eaton grain silo demolished and site clearance at Banbury Road commenced Various earthworks and structures designs in progress Carillion Buckingham JV announced as preferred bidder on 5 December £87.4m main works contract with CBJV for signing Secretary of State for transport to visit line on 13 February Railway will close on Friday 14 February until start of new services in August 2015 On target for programme completion date East West Rail Phase 1
Current Issues Developing Output Specification DfT aspirations for enhanced specification Industry consultation through Industry Plan Group Legal Powers Integrating Electric Spine Interface with High Speed 2 Maintaining momentum
Developing Output Specification Industry Plan Group Established November 2013 Objective to establish support from TOCs and other Stakeholders for conditional outputs Specification to be agreed at third IPG in March 2014 Options to be developed and costed by December 2014 ECAM process to confirm funding and programme options
Developing Output Specification Legal Powers Will be critical path item – Phase 1 powers took 2½ years Strategy for obtaining powers being developed EWR works in Claydon / Little Kimble areas included in HS2 Hybrid Bill
Developing Output Specification Existing To Milton Keynes East West Rail core scheme To Bedford Potential East West Rail Electrification throughout Oxford to Bletchley. Potential additional W12 gauging / load capability works not included in core scheme. Bletchley Swanborne Winslow Potential connection to Down Fast To Bicester To London Euston
Integrating Electric Spine Oxford – Bletchley confirmed as priority route Bletchley – Bedford likely to be delivered later: Signalling capacity Level crossings Stations Single line sections Bedford station Relationship with Midland Main Line EWR first part of Central Traction Power Supply Strategy
Interface with High Speed 2 To Banbury To Birmingham Bicester North Site of proposed HS2 Maintenance Depot Bicester Town Claydon LNE Junction To Bletchley To Oxford Calvert waste disposal site Existing Electrification throughout Oxford to Bletchley (Excluding Claydon to Aylesbury. Potential additional W12 gauging / load capability / signalling / line speed works not included in core scheme. East West Rail core scheme Potential East West Rail Proposed HS2 alignment To London Marylebone To Aylesbury and London Euston
Interface with High Speed 2 Aylesbury Town Aylesbury Vale Parkway To London Marylebone To Bletchley To Birmingham To London Euston Little Kimble Existing East West Rail core scheme Potential East West Rail To Princes Risborough Proposed HS2 alignment
Interface with High Speed 2 To London Marylebone Sidings Princes Risborough Little Kimble Monks Risborough To Aylesbury Existing Potential East West Rail To Banbury
EWR Powers included in hybrid bill Mutual Programme Risk: HS2 Powers assent in Summer 2015 EWR to be available for HS2 construction traffic via Claydon after 2018 EWR to be built on final alignment with bridges in place HS2 project team included in Industry Plan Group Interface with High Speed 2
Non-abortive work progressed pending final determination: Verification of 2009 Atkins report Develop Output Specifications & ECAM process Boundary definition & encroachment identification Develop level crossing strategy Structural surveys (including Bletchley flyover) Bletchley – Milton Keynes capacity study Environmental Impact Assessment Formulated consents strategy & draft consents applications Communications & consultation Develop signalling control & power supply strategies Maintaining Momentum