Project Plan Review • Project Plan Review Propulsion • Propulsion Lead Mark Blanton • Date and Milestone • September 25-26 Propulsion Preliminary Design Review #1 Analysis • Preliminary Propulsion System Sizing • Determine characteristics of motor, propeller, gearbox, and battery system • September 26 Propulsion PDR #1 DR2 Presentation • September 27 Propulsion PDR #1 Rework • September 28 Propulsion PDR #1
Project Plan Review • Project Plan Review Propulsion • Date and Milestone • October 3-5 Propulsion Experiment • Test Stand Construction Beginning Oct. 3rd ending Oct. 5th • Propulsion Experiment Procedure Developed by Oct. 5th • October 11-12 Propulsion Experiment • Evaluation of different motor and propeller combinations using Boeing Tunnel at ASL • Provides hard data concerning performance for propulsion sizing • October 13-14 Propulsion Experiment Analysis/Propulsion PDR #2 • October 15 Propulsion Experiment DR2 Presentation • October 16 Propulsion PDR#2 Rework • October 17 Propulsion PDR#2 Presentation • Final Sizing of the Propulsion System
Project Plan Review • Project Plan Review Propulsion • Date and Milestone • October 18-22 Thiokol Report – Propulsion Section Analysis • October 23 Thiokol Report – Propulsion Section Presentation to DR#2
Project Plan Review • Project Plan Review Structures • Date and Milestone • September 28 Finalize Composite Supplier • October 1 Wing Construction Method & Wing Test Plan • October 2 Fuselage Construction Method & Wing and Fuselage Interface • October 5 Structures and Weight PDR • October 12 Wing Test Model Complete • October 14 Test Wing Model • October 15 Analyze Wing Test Results
Project Plan Review • Project Plan Review Structures II • Date and Milestone • October 15 Analyze Wing Test Results • October 16 Preliminary Fuselage Layout, Wing Test Summary, & Fuselage Loft • October 18 Landing Gear Design Complete • October 20 Final Structure Design • October 22 Report Draft • October 23 Draft to Group • October 30 Final Analysis and Parameter Verification
Project Plan Review • Project Plan Review Aerodynamics • Date and Milestone • September 29 Airfoil Selection • October 2 Aircraft Sizing Code Complete • October 3 PDR 1 • October 5 Develop CFD Model • October 13 CFD Model Complete • October 17 Preliminary Results for PDR 2 • October 19 PDR 2
Project Plan Review • Project Plan Review Aerodynamics II • Date and Milestone • October 20 Report Draft • October 23 Draft to Group • October 30 Final Analysis and Parameter Verification
Project Plan Review • Project Plan Review Controls • Date and Milestone • September 30 SM, CG, and NP estimations • October 1 Aircraft Sizing Code • October 1 VT and HT estimations • October 3 Preliminary Aircraft and Systems T.F. • October 8 Preliminary Control Surface Sizing • October 11 VT, HT, Ctrl. Surf., trade studies/PDR to Group • October 12 PDR
Project Plan Review • Project Plan Review Controls II • Date and Milestone • October 17 Final Ctrl. Surf. Analysis • October 21 Aircraft and systems simulation in Simulink • October 22 Report Draft • October 23 Draft to Group • October 24 PDR 2 • October 30 Final Analysis and Parameter Verification