1 / 38

Introduction

This project discusses the foundation analysis for the construction of the new CAPA High School building in Pittsburgh, Pennsylvania. The analysis compares the use of caissons and auger cast piles as foundation systems, considering factors such as bearing capacity, cost, and construction duration.

wcummings
Download Presentation

Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction Center for Creative and Performing Arts High School (CAPA High School) Pittsburgh, Pennsylvania Joshua Castillo Construction Management

  2. Agenda • General Project Information • Existing Building Systems • Foundation Analysis • Site Plan Analysis • “Astrovision” Video Screen Analysis • Conclusions

  3. General Project Information • Existing Site and Old Building • Downtown Pittsburgh • Adjacent to Allegheny River • Donation of Site and part of Existing Building • Existing Building Usage • Bar and Lounge 1st Floor • Jazz Club 2nd and 3rd Floors • CAPA use Floors 4-6 • Unoccupied 7th and 8th Floors • Residence on 9th Floor Penthouse

  4. General Project Information • New CAPA Building • Approximately 120,000 SF, 7 Stories • Full- Functioning High School Including: • Classrooms and Labs • Staff and Faculty Offices • Cafeteria and Gym • Below Grade Parking Lot • Focus in Creative and Performing Arts • 5,500 SF Theater • 4 Studios RENDITION OF CAPA BUILDING

  5. Existing Building Systems • Foundation System • Caissons with spanning Grade Beams • Slab on Grade and CIP Concrete Walls Below Grade • Framing System • A36 Steel Framing and Details • Mechanical systems • Complete with 2 AHU, air Distribution Ducts, Diffusers, Registers, Dampers, and Grilles • Electrical systems • Dry-Type Distribution Transformers • Low Volt Distribution Switch Boards • Light and Power Panel Boards for Wiring

  6. Existing Building Systems • Façade Systems • East Side: • CMU on Entire Side adjacent to Feiser Building • West Side: • Brick and Aluminum Windows • South Side: • Same as West other than Building Connection to Existing • North Side: • Glass Curtain Wall Spanning Height • “Astrovision” Video Display Screen • Brick and Aluminum Windows Connection to Existing Building

  7. Foundation Analysis • CAPA Originally Designed with Caissons • Caisson Construction Methods • Drill Holes • Reinforce Walls to Prevent Collapsing • Pump Water Out • Place Steel Reinforcing • Place Concrete

  8. Foundation Analysis • Problems with Using Caissons • Difficult to Construct in unstable Soil Conditions • High Water Table • Steel Casing as Hole Wall supports • Pump Water or use Tremie Method to Place Concrete • Variable Construction • Eight Sizes of Caisson Diameters Ranging from 2 ½ ft to 6 ½ ft across the site

  9. Foundation Analysis • Problems with Using Caissons • Duration of Installation • Time to Install Steel Casing • Time to Pump Water • Drill, Reinforce Hole Walls, Place Steel Reinforcing, then Pour Concrete

  10. Foundation Analysis • Auger Cast Piles (ACP’s) as an Alternative • Auger Cast Pile Construction Method • Drill Hole • Concrete Placed as Drill Bit is Removed • Steel Reinforcing Placed after Concrete is Placed • ACP’s used in a Cluster require a Pile Cap to tie them together 1.Drill Bit 2.Pressurized Concrete 3.Auger Cast Pile

  11. Foundation Analysis • Using ACP’s as an Alternative Foundation • General Benefits of Using ACP’s • Speed of Installation • Less Material Costs • Bearing Capacity • Overall Reduced Costs • Problems with Using ACP’s • Susceptible to Variability • More ACP’s Required than Caissons

  12. Foundation Analysis • Comparing the Two Foundation Systems Caissons VS Auger Cast Piles • Structural Bearing Capacity • Cost differences in Material and Construction • Constructability and Length of Time to Install

  13. Foundation Analysis • General Bearing Capacity QUltimate = QP + QS = AP(CNC+ ЧLNq + ЧNЧ) + Σ∆L(AS)S • Surface-Friction per Unit Area S = KSσ Tan∂ where: KS = Ave. Coeff. of Earth Pressure on Pile Shaft Steel Lined Caissons  KS=1.1 Concrete Alone  KS=1.5 *ACP’s can have 36% more Surface-Friction Bearing Capacity than Steel lined Caissons

  14. Foundation Analysis QUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS Average Unit Surface-Friction FS= C+ ½ KS(Ч-G) L (tan Ø) Assumptions: Ø = 12° C = 6 KN/m^2 Ч = 18 KN/m^3

  15. Foundation Analysis • Ultimate Bearing Capacity Comparison • Average Length of 50 Feet • 24” Diameter • Surface-Friction Comparison Caissons  FS = 20.5 KN/m^2 ACP’s  FS = 25.85 KN/m^2

  16. Foundation Analysis • Ultimate Bearing Capacity Comparison QUltimate = AP(CNC+ ЧLNq + ЧNЧ) + ASFS Caissons QUlt =QP + QS = 140.3 + 598.6 =738.9 KN =168 kips ACP’s QUlt =QP + QS = 140.3 + 753 = 893.3 KN =200 kips

  17. Foundation Analysis • Pile Cap Design • Based on # of Piles / Cluster • All Pile Caps used were 49” deep • Four different pile layouts • Four different size pile caps

  18. Foundation Analysis

  19. Foundation Analysis • Foundation Cost Comparison • System Estimates Using: • Means Cost Guides • Walker’s Building Estimating • General Contractor Consulting

  20. Foundation Analysis • Means Cost Guide Results

  21. Foundation Analysis • Duration of Foundation Construction • Foundation System Duration Estimates Using: • Means Cost Guides • General Contractor Consulting

  22. Foundation Analysis • Means Cost Guide Duration Results

  23. Site Plan Modification • A Discrepancy Affecting the Site Layout • Location of Existing Sanitary Sewer Line • Located 5 Feet closer to Building than shown on Drawings • Changes that were Made • Redesign of shoring system • Hand Excavation

  24. Site Plan Modification • Location of Foundation Problem • West Side Caissons are too Close to Sewer Line

  25. Site Plan Modification • 1st Possibility • Reduce Width of Entire Vault Area 1-2 ft • Leave Caissons/Piles at the edge

  26. Site Plan Modification • Effects of Reducing Vault Area Width • Positive Effects • Less Congestion for Foundation Installation • No Change in Building Superstructure • Negative Effects • Vault Area Will be More Congested • Vault is Pre-cast Concrete

  27. Site Plan Modification • 2nd Possibility • Move West Side Caissons/Piles East 5 ft

  28. Site Plan Modification • Effects of Partial Foundation Relocation • Positive Effects • Less Congestion for Foundation Installation • Building Superstructure Stays the Same • Negative Effects • Located in the Central Axis of the Vault Area • Creates 1 to 1 Cantilever on Grade Beams

  29. Site Plan Modification • Solution • Move West Side Foundation Piers 5ft East • Move Entire Vault Area 10 ft South

  30. “Astrovision” Video Display Screen Analysis • What is it? • 22ft X 37ft Video Screen • 112 Individual Modules

  31. “Astrovision” Video Display Screen Analysis • Problem With Screen Design • No Outlet to Disperse Heat Generated • Could Cause Damage to the Screen • Could Cause Excess Heat in Building • Possible Solution • Add Louvers to Disperse Heat

  32. “Astrovision” Video Display Screen Analysis • Effects of Adding Louvers • Screen is Able to be Cooled • Eliminates Potential Damage to Itself • Better Chance of Lasting Expected Lifetime • Eliminates Excess Heat Exposure of Building • Reduced Screen Size to Account for Louvers • Loss of 3 Lines of Screen Modules (21 Modules)

  33. “Astrovision” Video Display Screen Analysis • Effects of Adding Louvers • Reduced Screen Size • Loss in Aesthetical Quality of Screen • Overall Cost of Screen is Reduced • Added Cost of Louvers

  34. “Astrovision” Video Display Screen Analysis • Change in Cost With Louvers

  35. Conclusions • Foundation Analysis PROS • ACP’s have Better Surface-Friction making their Bearing Capacity higher than Steel Lined Caissons in the right soil conditions. • Using ACP’s Would Save Money and Time CONS • More potential for Displacement • Increased Chance of Variability in the Shafts • Site Plan Modification • Resizing the Vault Area Would Not be a Practical solution • Relocating the Foundation Caissons Reduces the Structural Integrity of the Vault Area • Move Entire Vault Area away from Potential Traffic Loads • Screen Redesign with Louvers • Saves Money in Initial and Repair Costs • Loss in Aesthetical Quality

  36. AE Faculty • Mascaro Construction • Tom Weber • Marc Delrossi – Project Engineer • Family and Friends

  37. Questions?

More Related