Injector / Linac Installation Current Status. Manager-Kathleen Ratcliffe Project Schedule R.M. Boyce Major Partner-Mechanical Fabrication Department Installation Underway!. 2006 Installation. Sector 21. Sector 20. Laser. BC1 Out. Bunch Compressor 1. Vault. X-Band Compressor. L1.
E N D
Injector / Linac Installation Current Status • Manager-Kathleen Ratcliffe • Project Schedule R.M. Boyce • Major Partner-Mechanical Fabrication Department • Installation Underway!
2006 Installation Sector 21 Sector 20 Laser BC1 Out Bunch Compressor 1 Vault X-Band Compressor L1 Insertion/SAB Wall
Linac Status • Downtime Installation 8/~20 Weeks of Linac Access • Prep and Removal Complete • Installation Priority • Linac Housing / Return to A-Line Operation January 07 • Vacuum Envelope & All Safety Systems • Injection Vault / Laser Schedule and Controls • SLAC Resources / MFD and Others • Hardware Ready • System Schedule / Commissioning • Good Design, Teamwork, Control
Future EO/BL TD11 (Stopper) Wire Scanner / PMT BL11/12 BC 1 Out
Chambers & Supports BC1 Diagnostics 4 Dipoles 2 Tweeker Quads Bunch Compressor 1
WC 293 Removable 60cm X-Band X-Band Compressor
The X-band accelerator section Klystron, modulator being power tested prior to installation.
L 1 2ea 9 ½ Ft DLWG
Linac Accelerator Section Removal Before Making room for the Insertion, L-1 and L-X regions After
SDMP / Stopper SAB Dipole OTRS1 / ANL Insertion / SAB BX 02 Dipole
E- Injection Vault
The Injector Vault Cable plant, vault ready for beamline components.
Wall 3 Wire Scanners BX 01 Dipole BBS Radiation Stopper
Heater Table Heater Phase 1
L0A L0B L0A / L0B
SAB Dipole Gun / GTL Laser Table Gun
Gun-to-Linac area Laser table uv Gun L0a Spectrometer GTL
Linac Downtime Issues • BPM feed-through 10-9 He leak • Old problem / New again (~3/23 BPMs On Temporary Hold) • BC 1 Diagnostics • 2/3 Assemblies close with Fab. SLA BPM is probably late for January. • Late components: • BLM 11 (BLM 12 will be in) • Toroids (All Locations / Vendor Failure) • Vacuum chambers in insertion region. (next slide) • Spool pieces are being fabricated to not prevent Commissioning Start. • Scheduled Downtime will be needed to install these components January : March to support current Commissioning schedule.
LCLS Injection LCLS Insertion region Linac beam Vac Chambers late for January Linac integrity needed for ESA program in Jan.
Injector Installation Status • Injector installation has taken second priority to Linac installation. • Injector vault: • Floor and cable plant installed • Injector beamline: • Accelerator structures, L0a ready, L0b in final bake • RF waveguide needs to go through bake • Gun in hot test at Klystron Mfg • 2nd gun is in pre-braze cold-test. • Vault Supports & Tables waiting DB start. • except for the GTL supports & table
Injector Installation Issues • Water system under pressure to make schedule! • 1 BPM in GTL waiting feedthrough resolution. • Late: • Torroids are not delivered from Vendor • The GTL stand is out for quote • Estimate it will be here 11/16 for installation 11/20. • Laser table installation begins 11/27 • The Gun will be ready by Laser Table install. • GTL is late, released for machining. • Working all issues with MFD to expedite schedule. • Improve on 2/15/07 Date.
Some Good Stuff • Good Design with Solid Documentation. • Active Data Base • Interconnect Control • Component Histories • Non-Compliance • Effective Teamwork MFD/MD/KLY/AD • Downstream Linac under design!