1 / 14

Chapter 4 Job Order Costing

Chapter 4 Job Order Costing. Job Costing vs. Process Costing Procedure of Job Costing Actual vs. normal Costs CC: Problems 4.37 (10%) and 4.39 (10%) (same as in 11th ed.) . Building Block Concepts of Costing Systems. The following five terms constitute the building blocks

weston
Download Presentation

Chapter 4 Job Order Costing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 4Job Order Costing Job Costing vs. Process Costing Procedure of Job Costing Actual vs. normal Costs CC: Problems 4.37 (10%) and 4.39 (10%) (same as in 11th ed.)

  2. Building Block Concepts of Costing Systems The following five terms constitute the building blocks that will be used in this chapter: • A cost objectis anything for which a separate measurement of costs is desired. • Direct costs of a cost object are costs that are related to the particular cost object and can be traced to it in an economically feasible way. • Indirect costs of a cost objectare costs that are related to the particular cost object but cannot be traced to it in an economically feasible way. • Cost poolis a grouping of individual cost items. • Cost allocation baseis a factor that is the common denominator for systematically linking an indirect cost or group of indirect costs to a cost object.

  3. Cost Tracing Direct Costs Cost Object Cost Allocation Indirect Costs Relationships between Building Block Concepts Cost Assignment . . . Different Cost Pools use different allocation bases using allocation bases

  4. Job-Costing and Process-Costing Systems • There are two basic systems used to assign costs to products or services: • Job costing • In a job-costing system, the cost object is an individual unit, batch, or lot of a distinct product or service called a job. • Process costing • In process costing, the cost object is masses of identical or similar units of a product or service. • Process costing allocates costs among all the products manufactured during that period.

  5. General Approach to Job Costing • The following seven-steps approach is used to assign actual coststo individual jobs: • Identify the chosen cost object(s). • Identify the direct costs of the job. • Select the cost-allocation base(s). • Identify the indirect costs associated with each cost-allocation base • Compute the rate per unit of each cost-allocation base used to allocate indirect costs to the job. • Compute the indirect costs allocated to the job. • Compute the cost of the job by adding all direct and indirect costs assigned to it.

  6. General Approach to Job Costing • D. L. Sports manufactures various sporting goods. • D. L. is planning to sell a batch of 25 special machines (Job 100) to Healthy Gym for $104,800. • A key issue for D. L. Sports in determining this price is the cost of doing the job.

  7. Direct materials $45,000 Direct labor 14,000 Factory overhead 13,125 Total $72,125 The 7 steps: Step 1: The cost object is Job 100. Step 2: Identify the direct costs of Job 100. • Direct material = $45,000 • Direct manufacturing labor = $14,000 Step 3: Select the cost-allocation base. • D.L. chose machines hours as the only allocation base for linking all indirect manufacturing costs to jobs. • Job 100 used 500 machine hours. • 2,480 machine hours were used by all jobs. Step 4: Identify the indirect costs. • Actual manufacturing overhead costs were $65,100. Step 5: Compute the rate per unit. • Actual indirect cost rate is $65,100 ÷ 2,480 = $26.25 per machine hour. Step 6: Compute the indirect costs allocated to the job. • $26.25 per machine hour × 500 hours = $13,125 Step 7: Compute the cost of Job

  8. Two Major Cost Objects • Products • Responsibility centers • flexible budget versus actual cost

  9. Actual Costing and Normal Costing • Actual Costing is a job-costing system that uses actual costs to determine the cost of individual jobs. • Actual costing is a method of job costing that traces direct costs to a cost object by the actual direct-cost rate(s) timesthe actual quantity of the direct cost input(s) • and allocates indirect costs using indirect costs to a cost object by using the actual indirect-cost rate(s) timesthe actual quantity of the cost allocation base. • Normal Costing allocates indirect costs based on the budgeted indirect-cost rate(s) times the actual quantity of the cost allocation base(s).

  10. Purchase of materials and other manufacturing inputs Conversion into work in process inventory Conversion into finished goods inventory Sale of finished goods Transactions and bookkeeping: see problem 4-37

  11. Underallocated and Overallocated Costs • Underallocated indirect costs: The allocated amountof indirect costs is lower than the actually incurred amount • Overallocated indirect costs: The allocated amountof indirect costs is higher than the actually incurred amount • Possibilities to balance the accounts: • Write-Off to Cost of Goods-Sold • proration (see problem 4-39) • Adverse incentives of prorating underallocated costs: • induces managers to “store” overhead costs • why should work-in-process produced below capacity be worth more? Justified only if capacity is scarce in the next period.

  12. Exercise:What is the total cost of the stay of patient Fred Adams? • Cowley County Hospital uses a job-costing system for all patients who have surgery. In March, the pre-operating room (PRE-OP) and operating room (OR) had budgeted allocation bases of 4,000 nursing hours and 2,000 nursing hours, respectively. The budgeted nursing overhead charges for each department for the month were $168,000 and $132,000, respectively. The hospital floor for surgery patients had budgeted overhead costs of $1,200,000 and 15,000 nursing hours for the month. For patient Fred Adams, actual hours incurred were eight and four hours, respectively, in the PRE-OP and OR rooms. He was in the hospital for 4 days (96 hours). Other costs related to Adams were: Pre-OP-costs OR-costs In-room-costs Patient medicine $ 200 $500 $2,400 Direct nursing time $1,000 $ 2.000 $ 3,000

  13. 4-37 Data • not included from Dec. 31st: • direct manuf. labor $5,000, indir. manuf. labor: $1,000 • miscellaneous manufacturing overhead: $1,000 • direct manufacturing labor cost Jan.1st to Dec. 30th: $150,000 • Beginning balances of materials, work-in-process, and finished goods control accounts • Adjusting and closing entries (over- and underallocations  cost of goods sold) • Ending inventory balances

  14. 4-39 Data • No beginning inventories; Budget 2007: • direct manufacturing labor: $420,000 • manufacturing overhead: 252,000 • Incomplete jobs (Dec. 31st, 2007) • #1768B, total dir. manuf. labor cost: $11,000, machine time: 287 hrs. direct materials: $22,000 • #1819C, total dir. manuf. labor cost: $39,000 machine time: 647 hrs. direct materials: $42,000 • Total debits to manufacturing overhead control:$186,840 • total direct manufacturing labor: 20,000 hrs, $400,000 • Ending finished goods control: $156,000, incl. dir.manuf. labor: $40,000 • Revenues: $2,700,680, CoGS: $1,600,000, marketing costs: $857,870, cost-plus 40% of cost. • T-account analysis • Over- or underallocated overhead? • Proration, based on: a) ending balances, b) allocated overhead before proration • Compare operating income with and without proration • Cost of job #1819C under proration according to 3b).

More Related