230 likes | 241 Views
This document provides an overview of the Herschel Satellite Acceptance Test Campaign, including the instruments consolidation scenario, agenda, project team organization, instrument test matrix, constraints to instrument test, current schedule and test flow, instrument verification status at satellite level, and agreements and MoM signature.
E N D
Herschel Satellite Acceptance test campaign Instruments consolidation scenario
Agenda • 14:00 1- Introduction & Objectives • 14:05 2- Herschel S/C Acceptance campaign flow • 14:20 3- Project Team Organisation • 14:35 4- Instrument Test Matrix • 15:20 5- Constraints to Instrument Test • 16:00 6- Current S/C Schedule and Test Flow • 16:15 7- Instrument verification status at S/C level • 16:45 8- AOB • 17:30 9- Agreements and MoM signature
Introduction & Objectives • Herschel Integrated Team & Instrument Teams fully aligned for the Satellite acceptance tests: • Consolidation of instrument verification at satellite level • Objectives, environment, boundary conditions, organisation • procedure/scripts to be prepared/delivered by instrument teams • how to coordinate instrument involvement at satellite level tests • Better understanding of the situation / schedule evolvements, • Ways to improve the preparation and execution coordination, • Instruments interface cooperation and relationship,
Herschel S/C Acceptance Campaign Flow 1/2 IST1 & SVT1 in He I I&T,UFT & SFT in Warm Conditions IST1 in Warm Conditions Cryostat Evacuation & Cool-down Cryostat Cool-Down & HSS/Telescope integration He II Production & Top-up TV/TB in He II EMC R in He II SOVT1 in He II IST1 & SPT1 in He II Mechanical in He I IST2 & SPT2 in He II FAR He II -> He I conversion He II Production & Top-up
Herschel S/C Acceptance Campaign Flow 2/2 FAR Process SOVT2 in He II SVT2 in He I Leak check, Packing & departure to KRU He II -> He I conversion End of acceptance activities S/C AFT & Preparation for launch in He I He II Production & Top-up Hydrazine filling in He I Combined operations Launch Campaign
Industrial Project Team Organisation 2/2 • Herschel Integrated team, technical main points of contacts • Schedule = Denis Montet • Engineering = Bernard Collaudin • Product Assurance = Andy Knight • Verification = Test Directors (see organigramme) • AIT = Test Conductors (see organigramme)
ESA Project Team Organisation 1/2 HERSCHEL/PLANCK Programme Manager T. Passvogel Senior Admin.Ass./Documentalist I. Luthold R Webb Herschel Secretary H/P Launcher L. Di Napoli H/P Payload G. Crone Operations. M. Krassenburg Herschel S/C L. Di Napoli Planck S/C T. Passvogel (act.) PA U. Gageur S/C System Eng. L. Di Napoli Herschel AIV F. Pedersen S/C System Eng. S. Thürey (act.) Planck AIV O. Piersanti Instruments A. Heske Ground Segment L. Aloy Herschel PA U. Gageur Instruments L. Perez-Cuevas Operations M. G. Sarah Mechanical N. Nikolaizig ACMS I. Rasmussen Planck PA P. Olivier ACMS D.Zorita Mech/Therm AIV M. Braghin Instruments PA J. Rautakoski Instruments C. Scharmberg Software F. de Bruin System Tests A. Gatti Software J. Windsor (act) System Tests J. Patterson Instruments S. Madden AIT QA A. Aarts Electrical B. Jackson Electrical Funct. F. Wechsler Electrical S. Thürey Project Control G. Gonzalez Herschel Cryostat C. Jewell Therm/Mech/Prop A. Schnorhk Instrument AIT K. Goodey Therm./Mech. C. Damasio Planck P/L B. Guillaume Cost Control M. van der Vlis Planning P. Oldeman Telescopes D. Doyle
ESA Project Team Organisation 2/2 • Herschel ESA team, technical main points of contacts • AIV = Flemming Pedersen • Schedule = Flemming Pedersen • S/C Product Assurance = Ulrich Gageur • Instruments Engineering = Carsten Scharmberg • Cryostat = Chris Jewell • Instruments Product Assurance = Ian Rautakoski
Instruments Test Specification • H-P-2-ASP-TS-1083_2.0 - Herschel Instruments FM IST Test specification • Specification established in collaboration between Industry/ESA and instruments teams, to specify instruments tests to be performed on Satellite level, and to remain the reference for these tests. • Double goal: • To instruments teams : To specify/explain which instruments test will be performed at satellite level (Objectives, environment, boundary conditions, organisation), and consequently which procedure/scripts instruments have to prepare • To specify to S/C AIT : Specify which instrument test will be performed (configuration, environment, duration, sequence …), and how or organize it. • Covers UFT, SFT, IST/commissioning, IST/RMS, SPT, TV, + define instruments state during EMS and S/C IST. • Collects & manage Instruments test procedures. Central site on ftp: • ftp://ftp.hp-instruments.as-b2b.com/industry_to_instruments/Herschel FM Integration & tests • Has been built from an overall test table elaborated with instruments (now updated from available procedures: last one = Herschel instruments FM IST_2007-11-26.xls) • Issue 1 published in Sept 06. Comments received from this date have been incorporated in issue 2 draft • In agreement with ESA, Issue 2draft 3 released (Industry/ESA/Instruments) for comments. Ready for signature • Today, comments on this issue 2 draft 3received from SPIRE & ASED. Distributed as an excel database (= detailed change log: Change notice - H-P-2-ASP-TS-1083 - Instrument IST spec.xls)
Test conditions • cryostat conditions • Was specified in IID-A (section 7.3.5) - based on analysis • Here are the expected conditions for test – Based on STM campaign
Constraints to instruments tests 4/4 Constraints for S/C IST
Current S/C Schedule and Test Flow December January February March April LSS slot OBA MIP 27.11.2007 BH closure 08.12.2007 S/C @ ESTEC 05.01.2008 Start cool-down 21.01.2008 Helium I 12.02.2008 Helium II 22.02.2008 HeII top up SFT PACS repair Evacuation Bake-out Cool-down - HSS -Telescope EMC C Packing, Transport & setup SOVT AFT RMS IST debug & warm IST & SVT SPT EMC TV/TB IST Christmas Break Start IST 08.01.2008 Start SPT 27.02.2008 End SOVT 14.03.2008 S/C in LSS 04.04.2008
Overview of tests • Test and test preparation status
VerificationSFT/WFT Evaluation • SPIRE WFT 1 (Vertical)
VerificationSFT/WFT Evaluation • SPIRE WFT 2 (Horizontal)
VerificationSFT/WFT Evaluation • HIFI SFT
VerificationSFT/WFT Evaluation • PACS SFT