An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Intertie Transactions Failure Working Group Tuesday April 19, 2005

  2. Agenda • Introduction • Summary of data • Review of definitions • Review of data • Discussion and Next Steps

  3. Summary of Data • Total Monthly Scheduling Deviation on all Interchanges • By Import/Export • By reason for scheduling deviation • By total monthly MWhs • As a percentage of Monthly Trade • By transaction count

  4. Summary of Data (Cont’d) • Monthly Scheduling Deviation by Interchange: Michigan, Manitoba, Minnesota, TransEnergie (HQ), NYISO. • By Import/Export • By reason for scheduling deviation • By total monthly MWh • As a percentage of Monthly trade • By transaction count • By On-Peak Exports or Imports and Off-Peak Exports or Imports

  5. Summary of Data (Cont’d) • Anonymous Participant Failure Rate from August 2003 to February 2005 for all interfaces • Expressed as a percentage of all scheduling deviations • Expresses as a percentage of the Participants total trade (similar calculation as guideline failure ratio)

  6. Definitions • Pre-Dispatch Constrained Schedule (PDC). The final PDC schedules issued prior to the delivery hour. • Dispatch Constrained Schedule (DC). DC schedules contain all transactions which began at the start of the delivery hour. • Scheduling Deviation in MWhs = PDC schedules in MWhs – DC schedules in MWhs • Percentage of Monthly Scheduling Deviation = Monthly Scheduling Deviation in MWhs / Monthly PDC schedules in MWhs

  7. Definitions - continued • Percentage of Export Monthly Scheduling Deviation = Monthly Export Scheduling Deviation in MWhs / Monthly Export PDC schedules in MWhs • Percentage of Import Monthly Scheduling Deviation = Monthly Imports Scheduling Deviation in MWhs / Monthly Import PDC schedules in MWhs • By Interchange: • Percentage of Total Monthly Scheduling Deviation = Monthly Scheduling Deviation in MWhs for Intertie / All Monthly PDC schedules in MWhs for the Intertie

  8. Definitions - continued • By Interchange: Percentage of Monthly Export Scheduling Deviation = Monthly Export Scheduling Deviation in MWhs for Intertie / All Monthly Exports in MWhs for the Intertie Percentage of Monthly Import Scheduling Deviation = Monthly Import Scheduling Deviation in MWhs for Intertie / All Monthly Imports in MWhs for the Intertie • Percentage of Monthly Export On-peak Scheduling Deviations = Monthly Scheduling Deviation for On-peak Exports in MWhs / Monthly PDC schedules for On-peak Exports in MWhs

  9. Definitions - continued • Percentage of Monthly Export Off-peak Scheduling Deviations = Monthly Scheduling Deviation for Off-peak Exports in MWhs / Monthly PDC schedules for Off-peak Exports in MWhs • Percentage of Monthly Import On-peak Scheduling Deviations = Monthly Scheduling Deviation for On-peak Imports in MWhs / Monthly PDC schedules for On-peak Imports in MWhs • Percentage of Monthly Import Off-peak Scheduling Deviations = Monthly Scheduling Deviation for Off-peak Imports in MWhs / Monthly PDC schedules for Off-peak Imports in MWhs

  10. Definitions - continued • Ratio 1 = MP(A) failures due to Tag or Economics in MWhs/ All MP(A) Scheduling deviations in MWhs • Ratio 2 = MP(A) failures due to Tag or Economics/ All MP(A) Trade in MWhs • similar to guideline failure ratio