EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE. The EUSO-BALLOON AIT-Development plan. Sylvie Dagoret-Campagne LAL, Orsay , Baptiste Mot, IRAP , Toulouse. - Purpose - Main sequences - Resources (manpower and GSE), including location
E N D
EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE The EUSO-BALLOON AIT-Development plan Sylvie Dagoret-Campagne LAL, Orsay, Baptiste Mot, IRAP, Toulouse • - Purpose • - Main sequences • - Resources (manpower and GSE), including location • -Main activities of the assembly and integration of the subsystems • -Final integration and tests
EUSO-BALLOON, a HighlyModular instrument • 4 subsystems : • « electrical » (DP,PDM,DP) • 1 mechanical, • DP : 11 components (boards), • PDM : 5 components (boards), • PWP : 1 • Each component under the responsibility (design, fabrication, procurement) of different laboratories world wide spread. • Phase B Phase C&D • Need AIT/AIV procedures • Need resource evaluation • Need time evaluation (planning) AIT Development plan and GSE
Main sequences of Integrations Optics Tests: RIKEN-JP/UAH-US tests EC-Unit Integration: MATRA-LAL Instrument Integration: B.I.S CNES Full electronicsintgration: APC PDM integration: APC Final Tests: B.I.S CNES ElectronicIntegration: LAL Mechanicsassembly: B.I.S CNES Data processing Integration: INFN-Naples time AIT Development plan and GSE
Manpower for AIT Full integration : Subsystem/ electronicintegration : DP integration: AIT Development plan and GSE
GSE-PDM AIT Development plan and GSE
GSE-CAL AIT Development plan and GSE
GSE-DP and GSE-Opt AIT Development plan and GSE
PDM AIT activities sequence Integration Tests & Validation Component Pre-assembly Pre- Integration Component test Assembly PAECM1 EC-Unit PAECM2 IEC1 AP1 IEC2 AP3 CAPHEEC1 HVPS THV1 THV2 CAKIEC1 IEC3 TECA1 AP2 EC-ASIC TECA2 IEL1 TrigPDM IEL2 TPD1.. N PDM-B AIT Development plan and GSE
PDM AIT activitieslist AIT Development plan and GSE
PDM-AIT Activitieslist AIT Development plan and GSE
DP-Activitiessequence AIT Development plan and GSE
DP-AIT Activitieslist … ID1 ID5 AIT Development plan and GSE
Pre-Integration EC-ASIC and PDM-B EC-ASIC board Charge injection ASIC Power supply Logic analyzer PDM board EC-ASIC board PDM board Computer Multimeter NI(PC interface) AIT Development plan and GSE
PDM-B-DP Pre-Integration AIT Development plan and GSE
INTERFACES TESTED UP TO NOW FOR HARDWARE DP EC-Front GPSR IR-CAM EC-DYNODE CLKB LVPS-DP1 EXT MAPMT EC-HV CCB EC-ANODE SIREN SPACEWIRE /PCI CNES Telemetry CPU EC-ASIC LVPS-DP2 DST Batteries PDM-B Bat Controller LVPS-PDM HVPS2 PWP HK HVPS1 LVPS-HK Sensors Motors EC-Back PDM DP TLS
Optical AIT Activitieslist TOP 1 TOP 2 AIT Development plan and GSE
PWP Activitiessequence AIT Development plan and GSE
Activities- Taskforms Example of description of a task • All activities are referred by an acronym, • Each activity is performed in a sequence of AIT-AIV of a subsystem of of the instrument • They are tracked in activity forms by AIT managers • Description : • Component, • Configuration, • GSE, • Task details, procedures, results AIT Development plan and GSE
Final AIT-AIV Resp : IRAP location : CNES • Overview of Integration Phases • Sequence of integrations • Global tests • Transport and flight campaign preparation • Flight campaign #1 AIT Development plan and GSE
1.SEQUENCE FOR INTRUMENT INTEGRATION Preliminary + IR-CAM Assembly AIT Development plan and GSE
2.GLOBAL TESTS Preliminary AIT Development plan and GSE
3.TRANSPORT AND FLIGHT-CAMPAIGN PREPARATION Preliminary AIT Development plan and GSE
Preliminary Flight campaign #1 AIT Development plan and GSE
Conclusions • Main phases of AIT identified : • Subsystems • Instrument (Final), • Many activities identified for subsystem AIT and their component integration, • Test procedures assessed, • Some activities can be done in parallel, some in sequences. • Merging points. • Activities are inserted in a sequence of AIT of the subsystems, • Types of activities: • Component tests, pre-integration, assembly, integration, tests and validation, calibration. • Resources in manpower for AIT distributed, location of the activities, including the management. • Resources in GSE listed, • Timing estimated, • Activities follow-up: • AIT-AIV will be controlled and tracked by the AIT managers using activities forms. AIT Development plan and GSE