SLAC ILC Accelerator Program. DOE HEP Program Review June 14 th , 2005. Outline and Breakouts. Outline Program overview CDR Efforts L-band RF development Breakouts L-band RF R&D Adolphsen e+/e- Source development & E-166 Sheppard Beam Delivery System & ATF-2 & ESA Seryi
E N D
SLAC ILC Accelerator Program DOE HEP Program Review June 14th, 2005
Outline and Breakouts • Outline • Program overview • CDR Efforts • L-band RF development • Breakouts • L-band RF R&D Adolphsen • e+/e- Source development & E-166 Sheppard • Beam Delivery System & ATF-2 & ESA Seryi • Accelerator operations Tenenbaum • Instrumentation Development Ross • ILC Civil studies & cost issues for Snowmass Asiri
SLAC ILC Program • SLAC ILC Department is focused on the ILC machine design • Presently the largest group focused on the ILC accelerator design • More than 70% of the ILC is ‘warm’ technology that we know well • Funding is 16.2 M$ from DOE plus ~0.5 M$ from US-Japan • 2 M$ of the DOE funding is used to support the ILC programs at LBNL, LLNL, and BNL • SLAC group has roughly 40 people in ILC Department plus another 40~50 people matrixed across the lab • Nominal program is roughly 65 FTEs • Presently under-running due to redirection from the NLC program, personnel losses to LCLS, and the accident recovery at SLAC but expect to catch up during summer
SLAC ILC and the GDE • Barry Barish has been chosen to lead the GDE and Gerry Dugan is the American Regional Director • GDE organization not yet completely clear • Working with Barry and Gerry to formulate FY06 program • Near term plans from the GDE: • Develop a baseline design in a ‘CDR’ with regional sites by the end of CY06 • Establish an R&D program focused on improvements (cost and performance) to the baseline design • Use 2nd ILC Workshop at Snowmass to begin definition of baseline • Barry: “the SLAC group is essential to develop the CDR” • Develop accelerator design with other international groups • Work with Fermilab FESS group on site development in the US
ILC Working Groups and Snowmass • Goal for 2nd ILC Workshop at Snowmass: • Start making choices for Baseline Configuration Document and determine remaining work to decide on BCD by 12/05 • Develop focused R&D program for cost reduction and/or improved performance • Develop site models for three different regions • Informal ILC organization will be used for Snowmass • 6 subarea Working Groups with three conveners apiece • Four of the 6 US region co-conveners are from SLAC ILC • Possibly 5 more ‘global’ working groups with possible SLAC leaders • Organization is bottoms-up with coordination provided by Nick Walker, Kaoru Yokoya, and myself working with the WG conveners • SLAC ILC group is working on documentation for the meeting that will compare options for the BCD
SLAC FY05 ILC Program • NLC group was redirected towards ILC • Developed a program aimed at the topics identified in the 2003 Technical Review Committee report and at the 1st ILC Workshop • Description at: http://www-project.slac.stanford.edu/ilc/slacprogram.html • The 2003 TRC identified 1 ‘R1’ and 15 ‘R2’ R&D items • DESY, Fermilab, and KEK are focused on the outstanding R1 and the R2 on the linac sub-unit test • SLAC is focused on the other 14 of the 15 R2 items and is working with US labs, KEK, UK groups, and DESY • SLAC is using technical expertise to study paths for cost reduction • High power rf (klystrons, couplers, circulators, and rf distribution) and solid state modulators
SLAC FY06 ILC Program • Program for FY06 has two main elements • Development of the ILC CDR • Overall design: Beam parameters, Optics, Emittance preservation, Stability/alignment, Instrumentation, Availability, MPS, and Operational issues • Electron & Positron sources and Damping rings • Linac design and wakefields/cavity optimization • Beam Delivery System and Interaction Region • Conventional construction implications and site development • Continuing R&D on linac rf technology • Klystrons, modulators, rf distribution, and couplers • Not (much) SC Cavity fabrication • Plan is posted on SLAC ILC website: http://www-project.slac.stanford.edu/ilc/slacprogram.html
SLC, E-158 Experimental Basis for the ILC Design Bunch Compression SLC, FFTB, ASSET, E-158 SLC and FEL’s SLC and(ATF2 in the future) ePreservation BDS & IR TESLA Test Facility (SMTF & STF in the future) Linac rf system ATF, 3rd Gen Light Sources, SLC Damping Rings e+ / e- Sources
ILC System Design and Operational Issues • Extensive simulation of sub-systems • Balance emittance budgets and specify system tolerances impact on overall beam parameters • Study operational issues • Design for availability and work on detailed availability models big impact on layouts and configuration but hard to quantify • Develop beam tuning algorithms specify beam instrumentation requirements and layout • Consider high-level controls software requirements (applications) for beam control specify control system requirements • Develop Machine Protection Scenarios • Specify active and sacrificial protection systems • Specify beam tuning stations
Electron and Positron Sources • Electron source • Continuing photocathode development • Creating space to begin laser and gun development • Need to start design simulations • Positron source (program with LLNL) • Studying target design for undulator, conventional, and Compton sources • Radiation damage • Thermal shock / beam damage • Engineering issues (high rotation speed, remote handling) • Capture and optics studies • Normal conducting capture structure design and fabrication • Complete E-166 polarized positron production (summer 2005)
Damping Rings • Damping ring design (program with LBNL) • Optics and tuning studies and collective effects • Bunch compressor design • SEY studies for electron cloud (program with LBNL) • Laboratory measurements in PEL • Building three chambers for PEP-II installation to verify solutions • ATF at KEK • Instrumentation (NanoBPM, laser wires, optical anchor) • Beam studies (ORM, BBA, FBII, Wiggler) • ATF Kicker replacement • ATF stripline kicker development • FONT/Feather 3ns kicker from LLNL/SLAC
Damping Ring Optics • New optics proposed based on PEP-II non-interleaved sextupole correction Pi-cell and FODO cell designs Dynamic aperture in Dogbone Damping Ring designs TME (DESY TDR) Pi-cell (low a Pep-II) FODO (high a Pep-II) Injected positron beam: ex = ey = 1x10-6 m-rad, tracked using LEGO with single-mode wigglers and multipole errors in the other magnets.
Electron Cloud Simulations Electron density in units of e m3 as a function of time for an arc bend in the 6km DR option assuming a beam pipe radius 22mm and including an antechamber design (full height h=10mm).
SEY Studies in PEP LER • Building three chambers for PEP-II • One with a load-lock system to allow laboratory measurement of a sample after exposure to the PEP-II vacuum environment • Two ‘grooved’ chambers to verify a proposal by Mauro Pivi and Gennady Stupakov
Linac Beam Line Design • Quadrupole alignment • Use a SC linac quadrupole from DESY to study shunting alignment ability – very important to achieve desired tolerances • Continue program for NC quadrupoles • BPM tests (program with TTF, ATF and LCLS) • Develop and test high resolution BPMs • Laser wire (program at ATF and PETRA3) • Work with other groups to test high resolution laser wires • Cavity diagnostics (program at TTF) • Add HOM detectors to SC cavities at TTF to determine beam-cavity location – very important especially for high shunt impedance cavities with small aperture • Measure vibration due to SC cryogenic equipment • Important for conventional layout and BDIR
Beam Delivery System • Optics design and layout (program with UK groups) • Study variations of BDS with different crossing angles, collimation systems, L*, etc understand tradeoffs • ATF-2 at KEK • Demonstration of new FFS using ATF beam • Proposal is being assembled – detailed contributions to be defined • Specialty magnets (program with BNL) • SC final quadrupoles are being prototyped at BNL • End Station A Test Facility (with UK and University groups) • MDI instrumentation studies, collimator wakefield studies • Construct IR mock-up
Civil Construction and Sites • Working with the Fermilab team to develop an Illinois site and a reference site • DOE has urged consideration of an Illinois site but it is important to understand the advantages and disadvantages • For Snowmass • Investigate 5 possible Illinois sites and create a matrix to compare sites • Investigate cost of configuration options • For BCD (December 2005) • Select Illinois site and compare withreference site; submit to DOE • For CDR (December 2006) • Develop selected Illinois site with cost and schedule
Project Management • Need to establish configuration control for the ‘CDR’ and subsequent TDR • Ewan Paterson is putting together a proposal to manage • The collider configuration • Collider construction project cost and schedule • Possibly the R&D program cost and schedule • Barry Barish will create configuration control board • Members from the accelerator design team • Members from the engineering team • Need to structure the ‘CDR’ work and work packages • Many discussions but need to move forward before Snowmass • Need to establish a structure for the BCD documentation • 1st cut being made by Nick, Kaoru, and myself
L-Band RF System R&D • SLAC has strong expertise in rf power generation and lots of experience from the X-band rf program to apply to ILC • Goal: reduce cost of the rf system (which is roughly 15% of TPC in USLCTOS cost estimate) and improve performance (better reliability, higher efficiency, …) • Working on solid state modulators, L-band klystrons, and other rf components • Many of these components could be part of the BCD – if not should be part of the long-range R&D program • Collaborating with Fermilab on three projects for the SMTF: • Modulator switches • Bayonet box for cryo-system • Electron-beam welding of SC cavities
Modulator R&D • Baseline design is FNAL/DESY/PPT modulator • Single switch with bouncer circuit and 12:1 transformer • Efficiency is pretty good; reliability uncertain; transformer is large and stray fields impact the dogbone damping ring • SLAC effort is evaluating options • Receiving an SNS power converter-modulator which should have good efficiency • Building Marx generator style which should provide similar efficiency and 100% availability and lower cost • Building switch for FNAL bouncer-style modulator • Working with Diversified Technologies in SBIR program (??) to test another series-switch modulator • Looking at high voltage cables for power distribution
Klystrons • Three industrial vendors for ‘baseline’ 10MW MBK tubes • Still very little real experience with multi-beam klystrons • Thales has delivered two refurbished tubes to DESY • CPI 10MW tube was accepted by DESY – may come to SLAC later • Toshiba 10MW tube is still under test • Four elements to SLAC program • Develop L-band sheet beam klystron • Study klystron / modulator options • More conservative 5MW tube or lower power PPM tubes • Decide which (if any) of these to pursue further • Buy L-band rf power at SLAC (needed for experience and other elements of program) • Possibly work with DESY and CPI on CPI 10 MW tube
Other RF Topics • Large number of ideas and requests for help • Constructing an SC ‘materials’ test facility • Studying TTF3 coupler designs and limitations • Looking at new approachesfor the rf distribution that would reduce the number of components • Working on concepts for new high power circulators and industrialization of low power (400 kW) circulators
Major Test Facilities • End Station B • Complete X-band program in NLCTA • Create new L-band rf Test Facility • Develop klystron and modulators for ILC • Test normal conducting structures for e+/e- sources • Construct coupler test facility • Facilities also available in Klystron Test Lab • End Station A • Study Interaction Region issues and instrumentation • Mockup of full IR • ATF/ATF-2 (Located at KEK but with big SLAC participation) • Test final focus system using very low emittance beam • Work on the linac test facilities around the world: TTF, SMTF, and STF
End Station B Program • NLCTA completed restart review and will turn on this week • Complete X-band program at NLCTA • Test CERN structure and other gradient studies • Test active switching technology • Will decommission 8-pac modulator and install a 2-pac modulator to allow for future use of the 300 MeV X-band linac • Create facility to construct prototype collimators for the LHC • Adaptation of NLC consumable collimator technology to allow the LHC to reach design luminosity (part of US-LARP) • Support E-163 laser acceleration experiment • Start construction of an ILC L-band test facility next slides
End Station B L-Band RF Test Facility • Build two L-band test stations next to NLCTA in ESB • Test modulators and klystrons • Provide rf power for NC accelerator structures and couplers
Longer Term L-band RF R&D Goals • All stations in End Station B will be run 24/7 • FY06: • Complete 1st station for rf component testing and experience • Test normal conducting structure for positron system • Develop coupler test stand • Start testing of circulators and other rf components • FY07: • Complete 2nd station to test Marx Generator (and CPI klystron?) • Test couplers for SMTF at Fermilab • FY08: • Finish 3rd and 4th stations with improved modulator/klystron designs • FY09: • Construct 10 additional stations in ESA or Klystron Test Lab to begin industrialization process, lifetime testing, and optimization
End Station A Test Facility For Prototypes of Beam Delivery and IR Components http://www-project.slac.stanford.edu/ilc/testfac/ESA/esa.html Collimator design, wakefields (T-480) BPM energy spectrometer (T-474) Synch Stripe energy spectrometer (T-475) IP BPMs, kickers EMI (electro-magnetic interference) IR Mockup PAC05 paper/poster: SLAC-PUB-11180, e-Print Archive: physics/0505171
ATF-2 at KEK • ATF-2 would be the BDS test facility • Follow-on to FFTB • New FFS optics • Operational issues • Train next generation
Reasons to develop the ATF-2 • Many reasons to develop the ATF-2 • Luminosity issues will be extremely challenging in the LC • Likely more challenging than achieving the beam energy • Complete FFTB studies • FFTB never demonstrated routine operation of FFS • Need to implement full feedback control and optimization • Operate with ILC like bunch train and demonstrate IP feedback • Operate with stable low emittance beam from ATF DR • Provide demonstration and experience concurrent with ILC construction • FFTB experience will be over 15 years old • Train new generation of physicists • Provide a visible test facility for project reviewers and sponsors
Collaborative Meetings • ILC Status Meeting – bi-weekly: SLAC, ANL, BNL, Cornell, Jlab, FNAL, LBNL, LLNL • Availability and MPS – monthly: SLAC, DESY • LET – bi-weekly: SLAC, Cornell, FNAL • e+ source – bi-weekly: SLAC, LLNL • @ Daresbury wks – SLAC would lead CDR effort • DR – bi-weekly: LBNL, ANL, Cornell, FNAL, SLAC • E cloud – weekly: SLAC – also irregular with LBNL, CERN, and KEK • ATF– irregular: SLAC, Cornell, LBNL, LLNL, UK • BDS – weekly: SLAC, BNL, FNAL, Oregon – also monthly: EU & Japan • MDI – monthly: SLAC, FNAL, Orsay, UK, many US universities • ESA – weekly: SLAC, UK, universities • ATF2 – irregular: SLAC, KEK, UK • Instrumentation – irregular: SLAC, KEK, DESY • SMTF – biweekly: SMTF collaboration • Conventional facilities – weekly: SLAC, FNAL
SLAC ILC Budget • FY05 DOE ILC budget is 22.7 M$ • 16.2 M$ to SLAC • 1.95 M$ LBNL, LLNL, BNL • 14.25 M$ at SLAC plus US-Japanfunds • FY06 DOE budget is 25 M$ • Distribution is unknown • Developing a detailed plan for FY06 based on 14.25 M$ at SLAC and 3.8 M$ LBNL, LLNL, and BNL plus 0.5 M$ US-Japan funds • Working with Robin Staffin, Barry Barish, and Gerry Dugan • Maintain flexibility to deal with budget increase or decrease • Having difficulty keeping people on ILC given the uncertainty • Lost 10 people so far in FY05
Summary • Last year has been difficult • Technology choice forced redirection of effort • Major accident and subsequent shutdown • Budget shortfall and layoffs in FY05 and large uncertainty in FY06 • Strong program addressing many of the critical design issues • SLAC program addresses 14 of the 15 “R2” items identified by the 2003 TRC report as well as many additional problems • Program descriptions for FY05 and FY06 are posted on web site • Working with GDE to further develop FY06 program • Program is focused on overall accelerator design issues as well some technology development concepts • Makes use of SLAC expertise to lead ILC design efforts worldwide • Many programs could grow but some will require new people