130 likes | 141 Views
This service allows generators to connect to the transmission system and integrate into the network. It includes studies to assess system impacts and necessary upgrades, as well as the process of negotiating and executing interconnection agreements.
E N D
Generator Interconnection Studies & Agreements Charles Hendrix
Generator Interconnection Service • Energy Resource Interconnection Service – allows a generator to be eligible to use the existing firm or non-firm capacity of the Transmission System on an “as available” basis • Customer must still request Transmission Service • Network Resource Interconnection Service – allows the Transmission Owner to construct the necessary upgrades to integrate the generator into the Transmission System in a manner comparable with other Network Resources • Customer must still request Transmission Service
Generator Interconnection Service • Neither Energy Resource Interconnection Service or Network Resource Interconnection Service gives the generator any right to deliver energy to any customer or point of delivery
Generator Interconnection Studies Process • Definitive Interconnection System Impact Study (DISIS) – Studied in Clusters • Facility Study • Limited Operation Study • Interconnection Agreement
DISIS – Powerflow Analysis • Models built from the Integrated Transmission Planning Models • Includes all upgrades with NTC • Includes a look over the 10 year planning horizon so no short term outages accounted for • SPP Footprint divided into 12 sub-regions (groups) for interconnection study purposes
DISIS – Powerflow Analysis • Distinct dispatch for each interconnection request in the cluster study for each season • All Energy studied to be sunk in SPP footprint
DISIS – Powerflow Analysis • AC Contingency Analysis • Constraints Identified and transmission reinforcements required for • ERIS – overloads with 20% sensitivity factor • NRIS – overloads with 3% sensitivity factor • Neither ERIS nor NRIS conveys right to deliver • Upgrade Costs shared on a MW impact basis
DISIS – Transmission Upgrades • If long lead time upgrades with NTC are found to mitigate the constraints identified in the DISIS Study, this is documented in the study as a required upgrade for the Generator • This requirement also documented in the Generator Interconnection Agreement (GIA)
Facility Studies • Performed by the transmission owner • +/- 20% estimate of interconnection facilities and network upgrades • Short Circuit Analysis – verify circuit breaker duty ratings
Limited Operation Impact Study (LOIS) • Customer may request to interconnect before the completion of long lead time upgrades identified in the DISIS • An additional study (LOIS) is evaluated taking the following into consideration • Customer’s requested COD • Higher-queued generation in service • Neglecting generators that haven’t built • Existing transmission infrastructure
Limited Operation Impact Study (LOIS) • AC Contingency Analysis • Constraints Identified – LOIS may be denied (or temporary cap identified) for • Overloads with 20% sensitivity factor • Otherwise Generator can interconnect on ‘as available’ basis until higher queued generator comes into service • Conditions documented in GIA
Interconnection Agreement • Draft GIA presented to Customer after completion of Facility Study • Customer given 60 days to negotiate with transmission owner for construction milestones • GIA is finalized, executed, and filed at FERC if necessary